Dorchester County Sealed Solicitation

Title: Construction of Ladson Road Fire/EMS Station

Deadline: 1/18/2022 2:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: IFB 2022-26

Description: Construction of a combined Fire/EMS Station on Ladson Road. Engineer's specifications and drawings will be posted no later than December 7th.


Pre-Bid Meeting Date: 12/15/2021 2:00 PM

Pre-Bid Meeting Details: Council Chambers, 201 Johnston Street, St. George, SC 29477


Documents:

Documents as of 12/8/2021
Login to view documents
Login to view documents
Login to view documents

PLANHOLDERS:

Date Company Name
12/2/2021 12:56:06 PM Haskell
12/2/2021 12:58:23 PM Hood Construction
12/2/2021 1:11:22 PM Edifice LLC
12/2/2021 1:14:38 PM First Class Construction LLC
12/2/2021 1:16:35 PM Edifice
12/2/2021 1:27:18 PM Trident Construction
12/2/2021 1:48:50 PM J Musselman Construction
12/2/2021 1:53:03 PM Gatch Electrical Contractor
12/2/2021 2:06:12 PM J. Davis Construction
12/2/2021 2:24:54 PM DBS Corporation
12/2/2021 3:06:22 PM Satchel Construction, LLC.
12/2/2021 3:35:06 PM Davis Builders, LLC
12/3/2021 2:06:57 AM IMS
12/3/2021 7:55:52 AM Moseley Architects
12/3/2021 8:43:58 AM J.R. Wilson Construction Co., Inc.
12/3/2021 9:32:38 AM LCK
12/3/2021 10:46:25 AM Hill Construction
12/3/2021 11:46:50 AM Mashburn Construction
12/4/2021 10:16:14 AM Matrix Engineering
12/6/2021 9:23:46 AM JE Dunn Construction
12/7/2021 7:57:26 AM Truluck Construction
12/8/2021 7:40:20 AM Way of Life Lawn & Maintenance LLC
12/8/2021 8:29:50 AM SouthCon Building Group
12/8/2021 8:31:34 AM Complete Solutions Contracting
12/8/2021 8:50:05 AM HITT Contracting
12/8/2021 9:27:56 AM MedPro Systems, llc
12/8/2021 9:57:33 AM C. Merrill Construction
12/9/2021 8:55:08 AM EMCS
12/9/2021 4:28:38 PM Brunson Construction
12/9/2021 4:34:05 PM Nixon Power Services
12/11/2021 12:00:55 PM HITT Contracting
12/13/2021 11:12:23 AM EMCS
12/15/2021 1:34:48 PM Robbins Construction Group
12/16/2021 7:59:54 AM Branks General Contractors
12/16/2021 3:49:01 PM Level Utilities LLC
12/20/2021 9:59:53 AM Kennedy Grading and Excavation
12/20/2021 10:22:42 AM Banks Construction Company
12/21/2021 10:22:05 AM Allen Butler Enterprises LLC
12/21/2021 1:23:32 PM Bohicket Construction
12/22/2021 9:18:39 AM Ajax Building Corporation Southeast
12/22/2021 9:24:27 AM Robbins Construction Group
12/22/2021 10:21:47 AM Phillips Industrial Services
12/22/2021 10:44:43 AM Dodge Data & Analytics
12/22/2021 3:53:35 PM Sumwalt Associates
12/27/2021 12:11:29 PM Consolidated Electric Inc.
1/6/2022 9:47:16 AM AAG Architects
1/6/2022 2:25:40 PM Infinger Construction Group
1/6/2022 3:26:58 PM Deltek
1/7/2022 10:39:36 AM FERGUSON WATERWORKS
1/7/2022 5:02:51 PM Safeway Signaling Ltd. Co. LLC
1/7/2022 11:53:15 PM North America Procurement Council, Inc. PBC
1/11/2022 9:09:32 AM Palmetto Sitework Services, LLC
1/11/2022 10:54:32 AM Ajax Building Company, LLC
1/11/2022 12:59:57 PM dodge data and analytics
1/11/2022 2:52:43 PM Dodge Data & Analytics
1/11/2022 3:33:59 PM The Schneider company
1/13/2022 6:32:58 AM RFx Analyst, Inc.
1/13/2022 10:53:07 AM Brantley Construction Company, LLC
1/13/2022 11:52:50 AM Dodge Data
1/13/2022 12:03:27 PM Pyramid Contracting
1/13/2022 1:23:51 PM Envirosmart
1/13/2022 2:37:44 PM Allston Farrell Construction
1/13/2022 11:02:49 PM AG Ltd
1/16/2022 12:03:28 AM Charles Abatement LLC
1/17/2022 9:26:38 AM Boomerang Design
1/18/2022 2:50:34 PM K & K Industries, Inc
1/18/2022 4:40:54 PM Leitner Construction Company
1/18/2022 5:46:03 PM Soil Consultants Inc.
1/19/2022 10:05:15 AM Design Build Construction
1/19/2022 10:27:29 AM IP Builders, Inc.
1/20/2022 12:01:22 AM North America Procurement Council Inc., PBC
1/20/2022 10:41:28 AM Construction Journal
1/21/2022 12:08:51 PM Swamp Fox Utilities
1/21/2022 10:52:01 PM Dodge Data & Analytics
1/24/2022 12:12:07 PM EnviroSmart Inc.
1/25/2022 12:37:09 PM Orwill Solutions, Inc.
1/27/2022 2:54:35 PM Soil Consultants, Inc.
1/31/2022 12:32:15 PM Weston & Sampson
2/3/2022 4:55:30 PM ConstructConnect
2/9/2022 4:56:53 PM IPW Construction Group, LLC
2/15/2022 12:18:49 PM MedPro Systems, LLC DBA: MPS Construction
2/23/2022 1:20:58 PM Clean Masters
3/1/2022 3:13:38 PM CARBRA Construction and Design, Inc.
3/24/2022 11:45:08 AM Infinger Construction Group LLC
4/1/2022 6:52:29 PM Dorchester County
5/4/2022 2:42:59 PM Red Bay Constructors
6/3/2022 8:20:07 AM Johnson-Laux Construction, LLC
6/6/2022 9:38:52 AM Palmetto Sitework Services LLC
7/23/2022 3:37:13 PM Dodge Data & Analytics
11/1/2022 3:55:19 PM Rahman‘s painting and Repairs, LLC
11/12/2022 3:45:47 PM TUPCO Inc.
1/5/2023 7:31:51 PM Ben Cox Company
7/31/2023 7:32:34 AM dach enterprises
1/9/2024 11:20:21 PM PWXPress
Addition 1

Posted: 12/8/2021

Type of Addition: Solicitation Update

Overview: This is not considered an official addenda, but just a note to inform potential bidders that the drawings and specifications have been added to the solicitation.

Addition 2

Posted: 12/17/2021

Type of Addition: Pre-Bid Sign-in Sheet

Documents:

Addition 3

Posted: 12/22/2021

Type of Addition: Addendum

Overview: This addendum extends the bid opening date and answers questions received.

Documents:

Addition 4

Posted: 1/6/2022

Type of Addition: Addendum

Overview: This addendum answers question and clarifies additional details.

Documents:

Addition 5

Posted: 1/11/2022

Type of Addition: Addendum 3

Overview: Additional clarifications and answers to questions

Documents:

Addition 6

Posted: 1/13/2022

Type of Addition: Addendum 4

Overview: Additional clarifications 

Documents:

Addition 7

Posted: 1/18/2022

Type of Addition: In Review

Addition 8

Posted: 1/18/2022

Type of Addition: Unofficial Bid Tab

Overview:

Documents:

Addition 9

Posted: 7/22/2022

Type of Addition: Award Information

Overview: Awarded to Design Build Construction LLC.

Documents:

Question 1

Posted: 12/2/2021

Question: Are there any plans and specs available to receive? If so can you email to nikki.hughes@es-integrated.com

Response: Drawings and specs have been uploaded as of 12/8.

Question 2

Posted: 12/6/2021

Question: Would you please add Bohicket Construction LLC as a plan holder please?

Response: You will be automatically added if you download the bid documents, which were added this morning.

Question 3

Posted: 12/8/2021

Question: What is the correct date of the pre-bid meeting? This website lists it as 12/15/2021 and the specifications call out 12/14/2021.

Response: December 15th, 2021, at 2:00PM. 201 Johnston Street, St. George, SC 29477

Question 4

Posted: 12/8/2021

Question: Please confirm L/D's, page 6 of the solicitation says $500/day for substantial completion, Specs Article 8- 8.B.1 says $1,000/day

Response: Confirmed $500/day, will address in future addendum.

Question 5

Posted: 12/16/2021

Question: In the specs it lists all these things needing painting. Just confirming that none of these will come factory finished or left galvanized. Mechanical items to be painted include, but are not limited to, the following: 1. Piping, pipe hangers, and supports. a. Paint exposed gas piping Safety Yellow. 2. Heat exchangers. 3. Tanks. 4. Ductwork. 5. Insulation. 6. Motors and mechanical equipment. 7. Accessory items. Electrical items to be painted include, but are not limited to, the following: 1. Conduit and fittings. 2. Switchgear. 3. Panelboards. H. Block Fillers: Apply block fillers to concrete masonry block at a rate to ensure complete coverage with pores filled EXTERIOR PAINT SCHEDULE A. Zinc-Coated Metal with Semi-Gloss Direct to Metal (“DTM”) Acrylic Enamel Finish: 2 topcoats of DTM semi-gloss enamel over acrylic bonding primer, with min. total DFT of 2.5 mils B. Exterior fiber cement siding: Top coat(s) for total DFT of 10 mils minimum over primer/sealer. INTERIOR PAINT SCHEDULE A. Concrete Masonry Units: Low-VOC Acrylic Eg-shell Finish. 2 coats over filler, with total DFT not less than 2.5 mils B. Gypsum Drywall Systems with Satin Acrylic Enamel Finish: Prime coat not required on items delivered shop primed. C. Ferrous Metal: Semi-Gloss Direct to Metal (“DTM”) Acrylic Enamel Finish (“AC”): 1 coat over primer, with total DFT not less than 2.5 mils D. Ferrous Metal with Latex Dry Fog Flat Finish and mildew resistance properties: One finish coat over primed exposed steel roof construction. (Note: Coordinate with masking and painting accent color exposed ductwork as indicated.) E. Zinc-Coated Metal: Semi-Gloss Direct Acrylic Enamel Finish: 2 coats over primer, with min. total DFT of 2.5 mils EXTERIOR HIGH-PERFORMANCE COATING SYSTEMS A. Ferrous Metal: Provide the following finish systems over exterior ferrous-metal surfaces

Response: Please let us know if Addendum One, Item 7.A.2 does not fully address your question.

Posted: 12/8/2021

Type of Addition: Solicitation Update

Overview: This is not considered an official addenda, but just a note to inform potential bidders that the drawings and specifications have been added to the solicitation.

Posted: 12/17/2021

Type of Addition: Pre-Bid Sign-in Sheet

Documents:

Posted: 12/22/2021

Type of Addition: Addendum

Overview: This addendum extends the bid opening date and answers questions received.

Documents:

Posted: 1/6/2022

Type of Addition: Addendum

Overview: This addendum answers question and clarifies additional details.

Documents:

Posted: 1/11/2022

Type of Addition: Addendum 3

Overview: Additional clarifications and answers to questions

Documents:

Posted: 1/13/2022

Type of Addition: Addendum 4

Overview: Additional clarifications 

Documents:

Posted: 1/18/2022

Type of Addition: In Review

Posted: 1/18/2022

Type of Addition: Unofficial Bid Tab

Overview:

Documents:

Posted: 7/22/2022

Type of Addition: Award Information

Overview: Awarded to Design Build Construction LLC.

Documents:

Posted: 12/2/2021

Question: Are there any plans and specs available to receive? If so can you email to nikki.hughes@es-integrated.com

Response: Drawings and specs have been uploaded as of 12/8.

Posted: 12/6/2021

Question: Would you please add Bohicket Construction LLC as a plan holder please?

Response: You will be automatically added if you download the bid documents, which were added this morning.

Posted: 12/8/2021

Question: What is the correct date of the pre-bid meeting? This website lists it as 12/15/2021 and the specifications call out 12/14/2021.

Response: December 15th, 2021, at 2:00PM. 201 Johnston Street, St. George, SC 29477

Posted: 12/8/2021

Question: Please confirm L/D's, page 6 of the solicitation says $500/day for substantial completion, Specs Article 8- 8.B.1 says $1,000/day

Response: Confirmed $500/day, will address in future addendum.

Posted: 12/16/2021

Question: In the specs it lists all these things needing painting. Just confirming that none of these will come factory finished or left galvanized. Mechanical items to be painted include, but are not limited to, the following: 1. Piping, pipe hangers, and supports. a. Paint exposed gas piping Safety Yellow. 2. Heat exchangers. 3. Tanks. 4. Ductwork. 5. Insulation. 6. Motors and mechanical equipment. 7. Accessory items. Electrical items to be painted include, but are not limited to, the following: 1. Conduit and fittings. 2. Switchgear. 3. Panelboards. H. Block Fillers: Apply block fillers to concrete masonry block at a rate to ensure complete coverage with pores filled EXTERIOR PAINT SCHEDULE A. Zinc-Coated Metal with Semi-Gloss Direct to Metal (“DTM”) Acrylic Enamel Finish: 2 topcoats of DTM semi-gloss enamel over acrylic bonding primer, with min. total DFT of 2.5 mils B. Exterior fiber cement siding: Top coat(s) for total DFT of 10 mils minimum over primer/sealer. INTERIOR PAINT SCHEDULE A. Concrete Masonry Units: Low-VOC Acrylic Eg-shell Finish. 2 coats over filler, with total DFT not less than 2.5 mils B. Gypsum Drywall Systems with Satin Acrylic Enamel Finish: Prime coat not required on items delivered shop primed. C. Ferrous Metal: Semi-Gloss Direct to Metal (“DTM”) Acrylic Enamel Finish (“AC”): 1 coat over primer, with total DFT not less than 2.5 mils D. Ferrous Metal with Latex Dry Fog Flat Finish and mildew resistance properties: One finish coat over primed exposed steel roof construction. (Note: Coordinate with masking and painting accent color exposed ductwork as indicated.) E. Zinc-Coated Metal: Semi-Gloss Direct Acrylic Enamel Finish: 2 coats over primer, with min. total DFT of 2.5 mils EXTERIOR HIGH-PERFORMANCE COATING SYSTEMS A. Ferrous Metal: Provide the following finish systems over exterior ferrous-metal surfaces

Response: Please let us know if Addendum One, Item 7.A.2 does not fully address your question.