City of Griffin Sealed Solicitation
Title: Griffin Golf Course Bridge Replacements
Deadline: 3/19/2024 2:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status: In Review
Solicitation Number: 24-007
Description: The project consists of the demolition of two single span concrete bridges (Bridge A and Bridge B) and replacing them with Contech aluminum bottomless box culverts. The box culverts will require concrete foundations and will have aluminum wingwalls provided in the Contech package. One bridge will require a new storm box and related 18” storm pipe.
The project will require concrete work related to the bridge slab and barrier walls. A portion of the existing drives and parking lot will require asphalt demolition and replacement.
Pre-Bid Meeting Date: 2/27/2024 2:00 PM
Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-bid meeting.A Mandatory Pre-Bid Meeting will be held at 2:00 pm on Tuesday, February 27, 2024 at the project site located at 625 Camp Northern Road, Griffin, Georgia 30224. All attendees will be required to sign in, and the resultant list will denote those allowed to submit a Bid for the project. After an initial presentation by the Engineer, bidders will be allowed to tour the site and become familiar with the existing conditions.
Documents:
Documents as of 2/13/2024 |
---|
Advertisement_for_Bidders..pdf |
Addition 1
Posted: 2/14/2024
Type of Addition: Addendum #1
Overview: Date Extensions
Deadline: 3/19/2024 2:00 PM
Solicitation #: 24-007
Documents:
Addition 2
Posted: 3/5/2024
Type of Addition: Addendum #2
Deadline: 3/19/2024 2:00 PM
Solicitation #: 24-007
Documents:
Addition 3
Posted: 3/13/2024
Type of Addition: Pre-Bid Sign In Sheet
Solicitation #: 24-007
Documents:
Addition 4
Posted: 3/14/2024
Type of Addition: Addendum #3
Overview: Addendum No. 3, dated March 14, 2024
Solicitation #: 24-007
Documents:
Addition 5
Posted: 3/14/2024
Type of Addition: Addendum #4
Overview: Addendum No. 4, dated March 14, 2024
Solicitation #: 24-007
Documents:
Addition 8
Posted: 3/21/2024
Type of Addition: In Review
Documents:
Addition 9
Posted: 3/26/2024
Type of Addition: NOIA
Overview: No recommendation is official until ten (10) days have passed since the NOIA has been posted AND it has been approved by the Board of Commissioners, if applicable. The successful supplier listed is instructed not to proceed until a contract, PO or other official notice is given by the contracting office.
Documents:
Posted: 2/14/2024
Type of Addition: Addendum #1
Overview: Date Extensions
Deadline: 3/19/2024 2:00 PM
Solicitation #: 24-007
Documents:
Posted: 3/5/2024
Type of Addition: Addendum #2
Deadline: 3/19/2024 2:00 PM
Solicitation #: 24-007
Documents:
Posted: 3/13/2024
Type of Addition: Pre-Bid Sign In Sheet
Solicitation #: 24-007
Documents:
Posted: 3/14/2024
Type of Addition: Addendum #3
Overview: Addendum No. 3, dated March 14, 2024
Solicitation #: 24-007
Documents:
Posted: 3/14/2024
Type of Addition: Addendum #4
Overview: Addendum No. 4, dated March 14, 2024
Solicitation #: 24-007
Documents:
Posted: 3/21/2024
Type of Addition: In Review
Documents:
Posted: 3/26/2024
Type of Addition: NOIA
Overview: No recommendation is official until ten (10) days have passed since the NOIA has been posted AND it has been approved by the Board of Commissioners, if applicable. The successful supplier listed is instructed not to proceed until a contract, PO or other official notice is given by the contracting office.
Documents: