Village of Addison Sealed Solicitation

Title: Byron Storm Sewer Installation

Deadline: 7/13/2020 10:00 AM   (UTC-06:00) Central Time (US & Canada)

Status: Awarded

Solicitation Number: 20-6-1

Description:

The Village of Addison is currently seeking bids for the Byron Storm Sewer Installation project. The project consists of installing approximately 800 lineal feet of 21-Inch storm sewer mains and appurtenances, in Byron Avenue/Road from Rohlwing Road to just east of JoAnn Lane. 


Documents:

Documents as of 6/23/2020
Login to view documents
Addition 1

Posted: 7/9/2020

Type of Addition: Addendum 1

Overview:

Amended Drawing

The aerial drawing within the bid packet is incorrect. The storm sewer line was incorrectly designated as new. This storm sewer line is existing.

 

The storm sewer running north/south along Rohwling is an existing 36” RCP storm sewer that will require a new 5’ diameter manhole to be installed and connected to the existing 26” RCP and new, proposed 21” storm sewer. 

 

The corrected drawing is attached.

Deadline: 7/13/2020 10:00 AM

Solicitation #: 20-6-1

Documents:

Addition 2

Posted: 7/9/2020

Type of Addition: Answers to Inquiries

Overview: Please review the questions and answer sheet.

Solicitation #: 20-6-1

Documents:

Addition 3

Posted: 7/13/2020

Type of Addition: In Review

Documents:

Addition 4

Posted: 7/28/2020

Type of Addition: Award Information

Overview: John Neri Construction Addison, IL

Amount: $193,500.00

Addition 5

Posted: 7/28/2020

Type of Addition: Award Information

Overview: John Neri Construction Addison, IL

Amount: $193,500.00

Posted: 7/9/2020

Type of Addition: Addendum 1

Overview:

Amended Drawing

The aerial drawing within the bid packet is incorrect. The storm sewer line was incorrectly designated as new. This storm sewer line is existing.

 

The storm sewer running north/south along Rohwling is an existing 36” RCP storm sewer that will require a new 5’ diameter manhole to be installed and connected to the existing 26” RCP and new, proposed 21” storm sewer. 

 

The corrected drawing is attached.

Deadline: 7/13/2020 10:00 AM

Solicitation #: 20-6-1

Documents:

Posted: 7/9/2020

Type of Addition: Answers to Inquiries

Overview: Please review the questions and answer sheet.

Solicitation #: 20-6-1

Documents:

Posted: 7/13/2020

Type of Addition: In Review

Documents:

Posted: 7/28/2020

Type of Addition: Award Information

Overview: John Neri Construction Addison, IL

Amount: $193,500.00

Posted: 7/28/2020

Type of Addition: Award Information

Overview: John Neri Construction Addison, IL

Amount: $193,500.00