Title: 23-CPHD-ITBPW-379 11th Street Park Improvements

Deadline: 12/5/2022 2:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: 23-CPHD-ITBPW-379

Description: For the provision of all material, labor and resources for park renovation at 11th street Park


Pre-Bid Meeting Date: 11/16/2022 9:00 AM

Pre-Bid Meeting Details: A virtual prebid conference will be held at 9:00 a.m. on Wednesday, November 16, 2022, on Microsoft Teams to allow potential Bidders an opportunity to obtain clarification of the specifications and requirements of the solicitation. To join the meeting, please click the following link in the solicitation, or join by dialing +1 347-973-6905 and enter Conference ID 546728036#. ATTENDANCE AT THE PREBID CONFERENCE IS OPTIONAL.


Documents:

Documents as of 11/23/2022
Attachment C - Virginia DOLI Wage Determination.pdf
23-CPHD-ITBPW-379 Addendum 1.pdf
23-CPHD-ITBPW-379 Addendum 2.pdf
Revised Attachment A v2 - Project Manual & Specifications.pdf
Revised Attachment B - Construction Drawings & Plans.pdf
L-03 Landscape Conservation Plan.pdf
Revised 23-CPHD-ITBPW-379.pdf
23-CPHD-ITBPW-379 Addendum 3.pdf
Prebid Conference Sign In Sheet - 23-CPHD-ITBPW-379 11th Street Park Improvements.txt.xlsx
Addition 1

Posted: 12/5/2022

Type of Addition: In Review

Documents:

Addition 2

Posted: 3/1/2023

Type of Addition: Award Information

Documents:

Question 1

Posted: 11/4/2022

Question: Detail 1/L-08 provides some quarries which presumably the seeding aggregate must be procured from for the exposed aggregate sidewalks. The manufacturer listed (Fletcher Granite – 978-320-4129) stated they don’t provide aggregate in ½-3/4” sizing. Please clarify what aggregate should be used for the seeding on the exposed aggregate finish

Response: Please see addendum 2

Question 2

Posted: 11/16/2022

Question: Will the pre-bid attendance roll be posted?

Response: Please refer to Addendum #3

Question 3

Posted: 11/18/2022

Question: Sheet E-01 Detail 5 calls for (2) 4” ducts to be installed from the utility pole to the utility meter. Detail 2 on same sheet calls for (2) 2” ducts to be installed. Please advise if we are too install (2) 2” since this is a 20a service.

Response: Please refer to Addendum #3

Question 4

Posted: 11/18/2022

Question: Sheet E-01 Detail 7 is calling for a 24” pole base. The base of the fixture is going to be 8” in diameter. Please confirm if the 24” diameter pole base is correct.

Response: Please refer to Addendum #3

Question 5

Posted: 11/18/2022

Question: Sheet E-01 Detail 7 is calling for the pole base to be flush with the ground. As this will be a grass area, the fixture would not have protection from lawnmowers. Please advise if pole base is to be flush as shown or revised and raised 4” above grade (to make the pole base 3’4” in total height).

Response: Please refer to Addendum #3

Question 6

Posted: 11/18/2022

Question: Re: the electrical ductbank that needs to be installed under N. Danville Street, would the road closure be for an entire day and reopened at the end of each day? Or can the road be permitted closed for 3 days?

Response: Please refer to Addendum #3

Question 7

Posted: 11/18/2022

Question: Please provide a quantity for how many bike racks are required as none are shown on the site plan.

Response: Please refer to Addendum #3

Question 8

Posted: 11/18/2022

Question: Does Detail E/L-02 apply for the entire new sidewalk? If not, please clarify where this detail is applicable. Please also clarify where detail 1/L-08 is applicable for the new sidewalk.

Response: Please refer to Addendum #3

Question 9

Posted: 11/18/2022

Question: Please provide basis of design for root aeration geo-composite matting shown on detail E/L-02.

Response: Please refer to Addendum #3

Question 10

Posted: 11/18/2022

Question: Please provide a detail for brick paver and curb/gutter reinstallation.

Response: Please refer to Addendum #3

Question 11

Posted: 11/18/2022

Question: Who is responsible for obtaining and paying for the permit for this project?

Response: Please refer to Addendum #3

Posted: 12/5/2022

Type of Addition: In Review

Documents:

Posted: 3/1/2023

Type of Addition: Award Information

Documents:

Posted: 11/4/2022

Question: Detail 1/L-08 provides some quarries which presumably the seeding aggregate must be procured from for the exposed aggregate sidewalks. The manufacturer listed (Fletcher Granite – 978-320-4129) stated they don’t provide aggregate in ½-3/4” sizing. Please clarify what aggregate should be used for the seeding on the exposed aggregate finish

Response: Please see addendum 2

Posted: 11/16/2022

Question: Will the pre-bid attendance roll be posted?

Response: Please refer to Addendum #3

Posted: 11/18/2022

Question: Sheet E-01 Detail 5 calls for (2) 4” ducts to be installed from the utility pole to the utility meter. Detail 2 on same sheet calls for (2) 2” ducts to be installed. Please advise if we are too install (2) 2” since this is a 20a service.

Response: Please refer to Addendum #3

Posted: 11/18/2022

Question: Sheet E-01 Detail 7 is calling for a 24” pole base. The base of the fixture is going to be 8” in diameter. Please confirm if the 24” diameter pole base is correct.

Response: Please refer to Addendum #3

Posted: 11/18/2022

Question: Sheet E-01 Detail 7 is calling for the pole base to be flush with the ground. As this will be a grass area, the fixture would not have protection from lawnmowers. Please advise if pole base is to be flush as shown or revised and raised 4” above grade (to make the pole base 3’4” in total height).

Response: Please refer to Addendum #3

Posted: 11/18/2022

Question: Re: the electrical ductbank that needs to be installed under N. Danville Street, would the road closure be for an entire day and reopened at the end of each day? Or can the road be permitted closed for 3 days?

Response: Please refer to Addendum #3

Posted: 11/18/2022

Question: Please provide a quantity for how many bike racks are required as none are shown on the site plan.

Response: Please refer to Addendum #3

Posted: 11/18/2022

Question: Does Detail E/L-02 apply for the entire new sidewalk? If not, please clarify where this detail is applicable. Please also clarify where detail 1/L-08 is applicable for the new sidewalk.

Response: Please refer to Addendum #3

Posted: 11/18/2022

Question: Please provide basis of design for root aeration geo-composite matting shown on detail E/L-02.

Response: Please refer to Addendum #3

Posted: 11/18/2022

Question: Please provide a detail for brick paver and curb/gutter reinstallation.

Response: Please refer to Addendum #3

Posted: 11/18/2022

Question: Who is responsible for obtaining and paying for the permit for this project?

Response: Please refer to Addendum #3