Town of Bluffton Sealed Solicitation

Title: Buck Island - Simmonsville Sidewalks, Phase 6

Deadline: 5/26/2021 2:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: 2021-49

Description:

The Town of Bluffton is soliciting competitive sealed bids from experienced and qualified Offerors to construct approximately 2,000 linear feet of concrete sidewalk in the Simmonsville Road right of way from Sugaree Drive south to connect with existing sidewalk.  The project includes grading and stormwater infrastructure.    

 The general scope of services includes the following:

1.     Demolition

2.     Erosion control

3.     Drainage

4.     Paving

5.     Mobilization, stakeout, traffic control and materials testing

 


Documents:

Documents as of 4/29/2021
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Addition 1

Posted: 5/17/2021

Type of Addition: Addendum 1

Overview: Q&A

Documents:

Addition 2

Posted: 5/27/2021

Type of Addition: Award Information

Documents:

Question 1

Posted: 5/12/2021

Question: According to section 9 of the Special Conditions of the bid documents, “The cost for testing shall be paid by the Owner”. Is the item for “Materials Testing” on the bid schedule just for coordination of the testing and for materials that are brought to the project (IE. Asphalt/Concrete Mix Designs)?

Response: The bid schedule line item is for the contractor's coordination efforts with the materials testing/geotech firm to be hired by the Town.

Posted: 5/17/2021

Type of Addition: Addendum 1

Overview: Q&A

Documents:

Posted: 5/27/2021

Type of Addition: Award Information

Documents:

Posted: 5/12/2021

Question: According to section 9 of the Special Conditions of the bid documents, “The cost for testing shall be paid by the Owner”. Is the item for “Materials Testing” on the bid schedule just for coordination of the testing and for materials that are brought to the project (IE. Asphalt/Concrete Mix Designs)?

Response: The bid schedule line item is for the contractor's coordination efforts with the materials testing/geotech firm to be hired by the Town.