City of Griffin Sealed Solicitation
Title: Griffin/Spalding Wayfinding Signage Project
Deadline: 10/12/2021 2:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status: Cancelled
Solicitation Number: 22-003
Description: The City of Griffin intends to install Wayfinding Signs in Griffin/Spalding County. This project will be for directional signage that will be placed throughout Spalding County and the City of Griffin to direct tourist/visitors to key points of interest throughout the community. The project consists of 39 signs to be placed in various areas along streets and highways.
Documents:
Addition 1
Posted: 9/17/2021
Type of Addition: Addendum #2- Q&A
Overview:
Deadline: 10/12/2021 2:00 PM
Solicitation #: 22-003
Documents:
Addition 2
Posted: 9/17/2021
Type of Addition: Addendum #1 correction
Overview: Added Attachment to documents for correction of Color--- No Blue signs as addendum describes.
Documents:
Addition 3
Posted: 9/27/2021
Type of Addition: Addendum#4 Questions Answers
Documents:
Addition 4
Posted: 10/12/2021
Type of Addition: Addendum
Documents:
Question 1
Posted: 9/17/2021
Question: Questions for Griffin: 1) Does the break away hardware, that is required for the base… need to be included in the bid price? 2) Some locations have 2 arrows and others have 6 arrows, Are the signs all the same size? 3) in reference to question 2/ If some panel layouts are larger, will the height from grade need to change? This will also causing the height of the post to be taller. 4) How do you want the sign delivered? on multiple pallets? Do you have the facility and equipment to off load large pallets?
Response: We have already responded to this question. Please see the public solicitation.
Posted: 9/17/2021
Type of Addition: Addendum #2- Q&A
Overview:
Deadline: 10/12/2021 2:00 PM
Solicitation #: 22-003
Documents:
Posted: 9/17/2021
Type of Addition: Addendum #1 correction
Overview: Added Attachment to documents for correction of Color--- No Blue signs as addendum describes.
Documents:
Posted: 9/27/2021
Type of Addition: Addendum#4 Questions Answers
Documents:
Posted: 9/17/2021
Question: Questions for Griffin: 1) Does the break away hardware, that is required for the base… need to be included in the bid price? 2) Some locations have 2 arrows and others have 6 arrows, Are the signs all the same size? 3) in reference to question 2/ If some panel layouts are larger, will the height from grade need to change? This will also causing the height of the post to be taller. 4) How do you want the sign delivered? on multiple pallets? Do you have the facility and equipment to off load large pallets?
Response: We have already responded to this question. Please see the public solicitation.