University of Alabama in Huntsville Sealed Solicitation
Title: 30 Ton Rubber Tire Gantry C
Deadline: 8/6/2019 1:30 PM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Solicitation Number: B002629
Description:
NOTIFICATION REQUEST FOR FORMAL PROPOSAL
Proposal Number: B002629
RESPONSE DUE BY: 08/06/2019
30 Ton Rubber Tire Gantry Crane B002629
THE UNIVERSITY OF ALABAMA IN HUNTSVILLE REQUESTS PROPOSAL FOR ITEMS/SERVICES AS PER THE POSTED SPECIFICATIONS ATTACHED FROM THE PROCUREMENT SERVICES below.
To register go to WEBSITE: http://www.uah.edu/business-services/vendors/bid-opportunities Vendor Registration
The vendor bid opening day will be August 06th at 1:30pm. I will need an automated bid loaded to UAH Vendor Registry.
Documents:
Documents as of 7/23/2019 |
---|
Login to view documents |
Addition 1
Posted: 8/8/2019
Type of Addition: Awarded to M-Jack Products
Overview: The bid is awarded by total low to M-Jack Products as the apparent lowest responsible bidder, meeting specifications.
Amount: $345,900.00
Documents:
Question 1
Posted: 7/31/2019
Question: (1) I see the RFQ asked for freight to be included but does not state anything about assembly or erection. We would normally provide a Technician at no cost to assist in assembling and erecting the machine and UAH would need to provide (2) personnel to assist plus the necessary cranes and a man lift to erect the rubber tire gantry crane. We can however provide a turn-key erection of the rubber tire gantry crane for an additional cost which would cover all manpower and necessary equipment, is this what is expected? (2) I do not see cab air conditioning in the specs which would not be a standard item on our rubber tire gantry cranes, does the end user require air conditioning in the cab?
Response: 1. If you a Technician at no cost you would put this on the bid as reference. 2. Add an option list for all items not listed on the bid. List as a option for the air conditioning.
Posted: 8/8/2019
Type of Addition: Awarded to M-Jack Products
Overview: The bid is awarded by total low to M-Jack Products as the apparent lowest responsible bidder, meeting specifications.
Amount: $345,900.00
Documents:
Posted: 7/31/2019
Question: (1) I see the RFQ asked for freight to be included but does not state anything about assembly or erection. We would normally provide a Technician at no cost to assist in assembling and erecting the machine and UAH would need to provide (2) personnel to assist plus the necessary cranes and a man lift to erect the rubber tire gantry crane. We can however provide a turn-key erection of the rubber tire gantry crane for an additional cost which would cover all manpower and necessary equipment, is this what is expected? (2) I do not see cab air conditioning in the specs which would not be a standard item on our rubber tire gantry cranes, does the end user require air conditioning in the cab?
Response: 1. If you a Technician at no cost you would put this on the bid as reference. 2. Add an option list for all items not listed on the bid. List as a option for the air conditioning.