Florence County Sealed Solicitation
Title: Florence County Industrial Park East (Phase I Improvements)
Deadline: 6/22/2021 2:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status: Awarded
Solicitation Number: 22-20/21
Description:
Improvements
to approximately 18-acre parcel within the Florence County Industrial Park
East, Florence County, South Carolina. The development will include an
approximately 100,200 SF mass graded pad and site improvements, ±635 linear feet of asphalt paved roadway,
and asphalt paved dedicated right-turn lane, including gravel turnaround, with center
concrete curb and gutter island, clearing and grubbing; grading; erosion
control; ditched storm drainage system with RCP culverts with wet stormwater
detention pond; ±80 of 12” DIP water line extension, ±810 linear of 12” PVC - C900 - DR 18 water
line extension, jack & bore ±45 linear feet of 20” steel casing; ±3,734
linear feet of 12” PVC – SDR 26 sewer service line.
Pre-Bid Meeting Date: 5/10/2021 10:00 AM
Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-bid meeting.
Documents:
Documents as of 5/3/2021 |
---|
Login to view documents |
Login to view documents |
PLANHOLDERS:
Date | Company Name |
---|---|
5/4/2021 8:11:33 AM | Wiley Easton Construction, Inc. |
5/4/2021 9:09:54 AM | Greenwall Construction Service, Inc. |
5/4/2021 9:49:24 AM | CBG Inc. |
5/4/2021 2:17:08 PM | EnviroSmart Inc. |
5/4/2021 2:21:01 PM | Kiewit Infrastructure South Co. |
5/5/2021 8:26:22 AM | North America Procurement Council Inc., PBC |
5/5/2021 8:41:42 AM | Mashburn Construction |
5/5/2021 12:57:31 PM | Soil Consultants Inc. |
5/5/2021 2:09:27 PM | RWF Construction, LLC |
5/6/2021 9:19:31 AM | Triangle Grading & Paving, Inc. |
5/10/2021 8:17:48 AM | North American Construction Company |
5/10/2021 10:28:18 AM | Contractor Services of Kershaw, LLC |
5/10/2021 3:32:04 PM | AOS Specialty Contractors, Inc. |
5/11/2021 4:52:48 PM | The Schneider company |
5/12/2021 11:05:57 AM | AO Hardee & Son, Inc. |
5/12/2021 11:10:03 AM | Palmetto Corp of Conway |
5/12/2021 11:11:59 AM | Richardson Construction Company |
5/12/2021 11:58:36 AM | LCI-Lineberger Construction, Inc. |
5/12/2021 7:21:13 PM | Civil Site Consultants, LLC |
5/13/2021 2:10:59 PM | JF Contractors |
5/17/2021 10:38:50 AM | JF Contractors |
5/21/2021 9:37:41 AM | Palmetto Corp |
5/21/2021 3:31:28 PM | Industrial Paving Inc |
5/22/2021 6:24:38 AM | industrial paving |
5/24/2021 10:46:51 AM | KCI Technologies Inc |
5/26/2021 11:21:24 AM | L & L Contractors |
5/26/2021 12:07:30 PM | Coastal Asphalt |
5/26/2021 3:19:07 PM | Coastal Commercial Roofing Co., Inc |
6/1/2021 4:07:26 PM | Campbell Pavement |
6/2/2021 9:26:41 AM | S&ME, Inc. |
6/3/2021 9:44:24 AM | Gardner Roofing, Inc |
6/3/2021 3:38:14 PM | Spann Roofing & Sheet Metal |
6/8/2021 10:26:07 AM | Palmetto Corp |
6/8/2021 10:26:31 AM | Gilbert Construction |
6/8/2021 10:32:21 AM | Ajax Building Corporation Southeast |
6/8/2021 11:44:47 AM | Ben Cox LLC |
6/8/2021 12:35:52 PM | Goodson Construction Co., Inc |
6/8/2021 5:11:24 PM | Complete Utilities, LLC |
6/8/2021 9:58:33 PM | Ervin Engineering |
6/9/2021 6:07:30 AM | E.E. Reed Construction - East Coast, LLC |
6/9/2021 8:51:16 AM | Palmetto Corp of Conway |
6/9/2021 2:54:03 PM | HATCHELL LANDSCAPE LLC |
6/10/2021 6:51:24 PM | Deltek |
6/14/2021 8:42:43 AM | CAROLINA PAVEMENT MARKINGS, INC. |
6/15/2021 7:36:13 PM | Site Concepts |
6/17/2021 8:08:50 AM | Davis & Floyd, Inc. |
6/21/2021 1:19:07 AM | AG Ltd |
6/21/2021 11:34:18 AM | Green Wave Contracting, Inc. |
6/21/2021 12:52:44 PM | Bluebook Network Building & Construction |
6/22/2021 8:29:48 AM | Phoenix Spirit Group, LLC |
6/22/2021 12:56:02 PM | R.E. Goodson Construction Co., Inc. |
6/22/2021 2:50:39 PM | Granger Landscapes, Inc. |
6/22/2021 5:52:40 PM | Digging Deep Construction |
6/23/2021 12:51:03 PM | Palmetto Corp of Conway |
6/23/2021 1:21:19 PM | Landmark Construction Co., Inc. |
6/23/2021 1:31:00 PM | Cherokee, Inc. |
6/23/2021 1:41:41 PM | Kirven Construction, Inc. |
6/23/2021 2:38:54 PM | C.R. Jackson Inc. |
6/23/2021 3:00:25 PM | Dodge Data & Analytics |
6/23/2021 4:19:29 PM | ConstructConnect |
6/28/2021 9:08:58 PM | Driggers Construction, LLC |
6/29/2021 4:15:18 PM | Construction Journal |
7/15/2021 2:15:11 PM | Dodge Data |
7/19/2021 6:51:22 AM | Chipley Company, Inc |
10/9/2021 6:49:02 PM | RFx Analyst, Inc. |
1/12/2022 8:54:53 AM | MNB Construction Inc. |
2/9/2022 7:19:13 AM | Gaster's Grading Co., Inc |
4/5/2022 9:20:49 PM | Sawyer construction |
Addition 1
Posted: 5/10/2021
Type of Addition: CAD File Release Form
Overview: Please fill the release form and submit to pfletcher@florenceco.org to request the CAD file.
Documents:
Addition 2
Posted: 5/12/2021
Type of Addition: Addendum No. 1
Overview:
This addendum revises the bid form (adds divisionalsubtotals and add alternate 1 for stone) This addendum also addresses questions concerning earthwork/Geotech and indexing materials.
Deadline: 6/1/2021 2:00 PM
Solicitation #: 22-20/21
Documents:
Addition 3
Posted: 5/25/2021
Type of Addition: Addendum No. 2
Overview:
The Jack & Bore was added as an additive alternate to the bid. A revised bid form and an exhibit plan is also attached for clarity.
Addition 4
Posted: 5/25/2021
Type of Addition: Addendum No. 2
Overview:
The Jack & Bore was added as an additive alternate to the bid. A revised bid form and an exhibit plan is also attached for clarity.
Documents:
Addition 5
Posted: 5/27/2021
Type of Addition: Notice of Bid Opening Extension
Overview: Please note that the bid opening date for this solicitation has been extended.
Deadline: 6/22/2021 2:00 PM
Solicitation #: 22-20/21
Addition 6
Posted: 6/8/2021
Type of Addition: Addendum No. 3
Overview: Included with this addendum is a revised bid form and bid plans.
Documents:
Addition 8
Posted: 7/20/2021
Type of Addition: Award Information
Overview: Awarded to Digging Deep Construction, LLC of Gable, SC on 7-16-21
Amount: $2,248,631.00
Question 1
Posted: 5/24/2021
Question: It looks like the proposed 12" sewer line at Station 3+00 is approximately 14 feet deep and installs between an existing billboard and an existing power pole. Is there any information on the billboard footing? Should the sewer line be bored in this area so that the billboard is not disturbed?
Response: This question will be answered via Addendum No. 3
Posted: 5/10/2021
Type of Addition: CAD File Release Form
Overview: Please fill the release form and submit to pfletcher@florenceco.org to request the CAD file.
Documents:
Posted: 5/12/2021
Type of Addition: Addendum No. 1
Overview:
This addendum revises the bid form (adds divisionalsubtotals and add alternate 1 for stone) This addendum also addresses questions concerning earthwork/Geotech and indexing materials.
Deadline: 6/1/2021 2:00 PM
Solicitation #: 22-20/21
Documents:
Posted: 5/25/2021
Type of Addition: Addendum No. 2
Overview:
The Jack & Bore was added as an additive alternate to the bid. A revised bid form and an exhibit plan is also attached for clarity.
Posted: 5/25/2021
Type of Addition: Addendum No. 2
Overview:
The Jack & Bore was added as an additive alternate to the bid. A revised bid form and an exhibit plan is also attached for clarity.
Documents:
Posted: 5/27/2021
Type of Addition: Notice of Bid Opening Extension
Overview: Please note that the bid opening date for this solicitation has been extended.
Deadline: 6/22/2021 2:00 PM
Solicitation #: 22-20/21
Posted: 6/8/2021
Type of Addition: Addendum No. 3
Overview: Included with this addendum is a revised bid form and bid plans.
Documents:
Posted: 7/20/2021
Type of Addition: Award Information
Overview: Awarded to Digging Deep Construction, LLC of Gable, SC on 7-16-21
Amount: $2,248,631.00
Posted: 5/24/2021
Question: It looks like the proposed 12" sewer line at Station 3+00 is approximately 14 feet deep and installs between an existing billboard and an existing power pole. Is there any information on the billboard footing? Should the sewer line be bored in this area so that the billboard is not disturbed?
Response: This question will be answered via Addendum No. 3