Peralta Community College District Sealed Solicitation

Title: RFP 19-20/12 - LANEY COLLEGE CAMPUS CENTRAL UTILITY PLANT UPGRADE PROJECT DESIGN-BUILD SERVICES

Deadline: 10/12/2020 2:00 PM   (UTC-05:00) Indiana (East)

Status: Deadline Expired

Solicitation Number: RFP 19-20/12

Description: This posting is for the three pre-qualified Design-Build Entities resulting from RFQ 19-20/12 and their subcontractors. No other submissions will be accepted. 


Pre-Bid Meeting Date: 9/15/2020 2:00 PM

Pre-Bid Meeting Details: Laney College 900 Fallon Street, Oakland, CA 94607. Meet at the existing Central Utility Plant with masks on and mainting COVID-19 safe distancing.


Documents:

Documents as of 10/23/2020
RFP 19 20 12 LC CUP Pre-Qualified DBE.pdf
RFP 19 20 12 LC CUP.pdf
Appendix B - PCCD LANEY CUP RFP SPECS.pdf
Appendix B - PCCD LANEY CUP RFP DRAWINGS.pdf
Appendix B - 05-26-98 Central Plant Retrofit.pdf
Appendix C - Design-Build Agreement.pdf
Appendix E - Stipend Agreement.pdf
Appendix F - Proposal Form.pdf
Appendix H - LC Central Utility Plant Study Taylor 2020 0305.pdf
Reference Document - Laney CUP Geotech Report.pdf
Appendix B - 10-08-71 LC Consolidated Mechanical Set - First half.pdf
Appendix B - 10-08-71 LC Consolidated Mechanical Set - Second half.pdf
RFP 19 20 12 LC CUP Mandatory Pre-Proposal Meeting Sign-In.pdf
RFP 19 20 12 Addendum One.pdf
RFP 19 20 12 Checklist.pdf
RFP 19 20 12 RFI Log.pdf
00 50 00 Design-Build Agreement Appendix C Rev. 00 2020 0923.pdf
Noll & Tam Citeria Documents Addm.01.pdf
Noll & Tam LANEY CUP Addm.01 - CAD WAIVER.pdf
Laney CUP Div 00 01 Specifications.pdf
Laney LRC 50 CD - SPEC Vol 1.pdf
Laney LRC 50 CD - SPEC Vol 2.pdf
Laney-LLRC_CD50_FULL_DWG-SET.pdf
RFQ 19 20 12 Addendum Two.pdf
RFP 19 20 12 Laney CUP Notice of Intent to Award.pdf
Question 1

Posted: 9/30/2020

Question: 1. Sheet E2.01 shows Distribution Panel EP, this is not labeled as existing, but it does show as existing on E1.01. Please confirm this is existing. 2. Existing MCC-2 (Future Distribution Panel EP2A) is fed from EP with a feeder labeled 6003. Please provide feeder size for EP2A 6003. 3. New chillers are fed from a 600/3 circuit breaker but have a 100A disconnect (Type C) for shutoff. Please confirm that these should be 600A (Type F). 4. Please provide feeder sizes for feeder notes 4000 and 6000. 5. Conduits that are not shown in the site trenching details C4.00, C4.01 a. Emergency conduit from ERC2 to new panel ERZC13 up to new utility building b. Feeder conduit from EPCUP to net utility building for EP213 c. 12 KV feeder from “E” Primary switchgear to new utility building for future transformer 6. Bridging documents do not have information for Data, Security, or other Low Voltage systems at the new utility building. Are these to be included? If so, please provide: a. Information and manufacturer of security system b. Locations where these may be fed from 7. There are 4 – 1.25” and 2 – 2” spare conduits shown on Note 1 on both C4.00 and C4.01. Please provide future use for these conduits.

Response: Answered in Addendum Two, posted today 10-6-20.

Question 2

Posted: 9/30/2020

Question: 1. Can the district provide a campus Path of Travel plan from prior projects? 2. During the site meeting it was mentioned meetings have occurred with PG&E regarding the 115kv facilities and associated easement. Are meeting minutes available and what are the requirements for work within the easement? Concerns include minimum clearances to maintain, review process with PG&E, oversight/interaction during construction that will impact schedule, etc. 3. Potholes #2 and #5 document the depth of the 115kv duct bank. What is the width of the duct bank? 4. Sheet C4.00 notes the relocation of a 12kv duct bank between manhole A and the existing switchgear. Is there a single line diagram or other information available to explain what this branch serves and the associated shut down required?

Response: Answered in Addendum Two, posted today 10-6-20.

Question 3

Posted: 9/30/2020

Question: 5. Can the district provide the LRC building plans for reference? 6. The criteria documents call for the relocation of the domestic water backflow preventor. Has there been any correspondence with EBMUD regarding the proposed location? 7. What is the timing of the relocation of the 36-inch EBMUD watermain shown on sheet C4.01? Will it be relocated prior to the construction of this project? If not what are the criteria/requirements for construction within the easement and for crossing the water main? 8. It was mentioned on the informational meeting that the District plans to procure the equipment for this project. Please advise if the equipment should be planned to be included in the NTE cost of $12m or outside. Also, please advise if the equipment are planned to be procured on or before the DSA approval?

Response: Answered in Addendum Two, posted today 10-6-20.

Question 4

Posted: 10/1/2020

Question: RFI Q1: Reference Sheet C4.01: Information needed for general note to Relocate panel: • Please provide new location for disconnect, Transformer, and panel. • Please provide single line showing where panel is fed from and feeder size • Please provide panel schedule or loads that will need to be reconfigured to new location. RFI Q2: Who is the preferred Fire Life Safety Alarm vendor for the campus? Please provide contact info. Thank you!

Response: Answered in Addendum Two, posted today 10-6-20.

Posted: 9/30/2020

Question: 1. Sheet E2.01 shows Distribution Panel EP, this is not labeled as existing, but it does show as existing on E1.01. Please confirm this is existing. 2. Existing MCC-2 (Future Distribution Panel EP2A) is fed from EP with a feeder labeled 6003. Please provide feeder size for EP2A 6003. 3. New chillers are fed from a 600/3 circuit breaker but have a 100A disconnect (Type C) for shutoff. Please confirm that these should be 600A (Type F). 4. Please provide feeder sizes for feeder notes 4000 and 6000. 5. Conduits that are not shown in the site trenching details C4.00, C4.01 a. Emergency conduit from ERC2 to new panel ERZC13 up to new utility building b. Feeder conduit from EPCUP to net utility building for EP213 c. 12 KV feeder from “E” Primary switchgear to new utility building for future transformer 6. Bridging documents do not have information for Data, Security, or other Low Voltage systems at the new utility building. Are these to be included? If so, please provide: a. Information and manufacturer of security system b. Locations where these may be fed from 7. There are 4 – 1.25” and 2 – 2” spare conduits shown on Note 1 on both C4.00 and C4.01. Please provide future use for these conduits.

Response: Answered in Addendum Two, posted today 10-6-20.

Posted: 9/30/2020

Question: 1. Can the district provide a campus Path of Travel plan from prior projects? 2. During the site meeting it was mentioned meetings have occurred with PG&E regarding the 115kv facilities and associated easement. Are meeting minutes available and what are the requirements for work within the easement? Concerns include minimum clearances to maintain, review process with PG&E, oversight/interaction during construction that will impact schedule, etc. 3. Potholes #2 and #5 document the depth of the 115kv duct bank. What is the width of the duct bank? 4. Sheet C4.00 notes the relocation of a 12kv duct bank between manhole A and the existing switchgear. Is there a single line diagram or other information available to explain what this branch serves and the associated shut down required?

Response: Answered in Addendum Two, posted today 10-6-20.

Posted: 9/30/2020

Question: 5. Can the district provide the LRC building plans for reference? 6. The criteria documents call for the relocation of the domestic water backflow preventor. Has there been any correspondence with EBMUD regarding the proposed location? 7. What is the timing of the relocation of the 36-inch EBMUD watermain shown on sheet C4.01? Will it be relocated prior to the construction of this project? If not what are the criteria/requirements for construction within the easement and for crossing the water main? 8. It was mentioned on the informational meeting that the District plans to procure the equipment for this project. Please advise if the equipment should be planned to be included in the NTE cost of $12m or outside. Also, please advise if the equipment are planned to be procured on or before the DSA approval?

Response: Answered in Addendum Two, posted today 10-6-20.

Posted: 10/1/2020

Question: RFI Q1: Reference Sheet C4.01: Information needed for general note to Relocate panel: • Please provide new location for disconnect, Transformer, and panel. • Please provide single line showing where panel is fed from and feeder size • Please provide panel schedule or loads that will need to be reconfigured to new location. RFI Q2: Who is the preferred Fire Life Safety Alarm vendor for the campus? Please provide contact info. Thank you!

Response: Answered in Addendum Two, posted today 10-6-20.