Lindbergh Schools Sealed Solicitation
Title: District School Zone Flashers
Deadline: 10/18/2021 1:00 PM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Description:
Documents:
Documents as of 9/23/2021 |
---|
Login to view documents |
Login to view documents |
Addition 1
Posted: 10/26/2021
Type of Addition: Award Information
Question 1
Posted: 10/1/2021
Question: What is the desired term of cellular service for the flashing beacons?
Response: Cellular service shall be included through 7/31/2029.
Question 2
Posted: 10/1/2021
Question: How long each day is the flashing beacon planned to be on for?
Response: The contractors/vendors should assume 1 hour each of flashing operation in the AM and PM peak periods on weekdays.
Question 3
Posted: 10/11/2021
Question: Is the cost of cellular service through 7/31/2029 to be included in our proposal? Also, is there a bid form you would liike us to use in submitting our proposal?
Response: The cost of cellular service through 7/31/2029 should be included in the bid, included with the per each price for Solar Powered School Speed Limit Flasher. The bid form can be an extended version of a Summary of Quantities table to show the price for each line item.
Question 4
Posted: 10/11/2021
Question: Will Subcontracting be allowed on this project?
Response: Yes, please see the General Terms and Conditions included in the original posting for more information about subcontractors.
Posted: 10/26/2021
Type of Addition: Award Information
Posted: 10/1/2021
Question: What is the desired term of cellular service for the flashing beacons?
Response: Cellular service shall be included through 7/31/2029.
Posted: 10/1/2021
Question: How long each day is the flashing beacon planned to be on for?
Response: The contractors/vendors should assume 1 hour each of flashing operation in the AM and PM peak periods on weekdays.
Posted: 10/11/2021
Question: Is the cost of cellular service through 7/31/2029 to be included in our proposal? Also, is there a bid form you would liike us to use in submitting our proposal?
Response: The cost of cellular service through 7/31/2029 should be included in the bid, included with the per each price for Solar Powered School Speed Limit Flasher. The bid form can be an extended version of a Summary of Quantities table to show the price for each line item.
Posted: 10/11/2021
Question: Will Subcontracting be allowed on this project?
Response: Yes, please see the General Terms and Conditions included in the original posting for more information about subcontractors.