Florence County Sealed Solicitation
Title: 16-21/22 CPSTIII Resurfacing Project District 7
Deadline: 1/27/2022 10:15 AM (UTC-05:00) Eastern Time (US & Canada)
Status: Awarded
Solicitation Number: 16-21/22
Description: Florence County, South Carolina (Owner) is accepting bids from licensed and qualified Contractors for the 2022 CPSTIII Resurfacing Project - District 7.
Documents:
Documents as of 1/19/2022 |
---|
Login to view documents |
Addition 1
Posted: 1/20/2022
Type of Addition: Addendum
Overview: Updated Bid Document to include Unit Price Bid Form.
Documents:
Addition 2
Posted: 1/27/2022
Type of Addition: In Review
Addition 4
Posted: 2/17/2022
Type of Addition: Award Information
Amount: $519,827.05
Documents:
Question 1
Posted: 1/20/2022
Question: The unit price bid form was omitted in this bid package.
Response: Please see addendum updating bid document to include unit price form on page 59.
Question 2
Posted: 1/20/2022
Question: Can the quantities be provided for each individual road?
Response: The answer to this question is provided in the addendum update.
Question 3
Posted: 1/20/2022
Question: There is no quantity for pavement markings on this project. Could we be provided with this quantity?
Response: There are no pavement markings that currently exist on the roads and new pavement markings will not be required for the project.
Posted: 1/20/2022
Type of Addition: Addendum
Overview: Updated Bid Document to include Unit Price Bid Form.
Documents:
Posted: 1/27/2022
Type of Addition: In Review
Posted: 2/17/2022
Type of Addition: Award Information
Amount: $519,827.05
Documents:
Posted: 1/20/2022
Question: The unit price bid form was omitted in this bid package.
Response: Please see addendum updating bid document to include unit price form on page 59.
Posted: 1/20/2022
Question: Can the quantities be provided for each individual road?
Response: The answer to this question is provided in the addendum update.
Posted: 1/20/2022
Question: There is no quantity for pavement markings on this project. Could we be provided with this quantity?
Response: There are no pavement markings that currently exist on the roads and new pavement markings will not be required for the project.