Florence County Sealed Solicitation
Title: 12-23/24 6" MBC Stone for District 2 & 5 Roads
Deadline: 8/31/2023 11:00 AM (UTC-05:00) Eastern Time (US & Canada)
Status: Awarded
Solicitation Number: 12-23/24
Description: Florence County, South Carolina is accepting bids from qualified vendors to furnish and deliver 23,314 Tons of MBC Stone to various roads in Florence County.
Documents:
Documents as of 8/18/2023 |
---|
Login to view documents |
PLANHOLDERS:
Date | Company Name |
---|---|
8/18/2023 2:25:31 PM | carver companies |
8/18/2023 3:52:54 PM | Palmetto Corp of Conway |
8/21/2023 1:58:28 AM | Dodge Data |
8/21/2023 8:06:11 PM | tgtrucking2@gmail.com |
8/22/2023 1:22:57 PM | Luck Stone |
8/30/2023 9:55:49 AM | N. W. White & Company |
8/31/2023 12:30:13 AM | AG Ltd |
8/31/2023 10:14:26 AM | HERITAGE HAULING INC |
8/31/2023 11:52:33 AM | D&L Sitework Inc |
8/31/2023 12:10:03 PM | Boggs Paving, Inc. |
8/31/2023 12:28:18 PM | Thompson Turner Construction |
8/31/2023 12:29:43 PM | Georgia Stone Products |
8/31/2023 1:01:32 PM | Chipley Company, Inc |
8/31/2023 1:50:04 PM | C. R. Jackson, Inc |
8/31/2023 1:53:35 PM | Heritage Hauling Inc. |
8/31/2023 2:22:30 PM | ConstructConnect |
8/31/2023 2:56:59 PM | Soil Consultants Inc. |
8/31/2023 7:58:24 PM | D & L Sitework Inc |
8/31/2023 9:07:11 PM | Palmetto Mining Company |
9/1/2023 1:19:05 PM | GA Stone |
9/4/2023 2:08:33 AM | Dodge Data & Analytics |
9/4/2023 4:10:49 AM | Deltek |
9/6/2023 12:34:49 AM | Dodge Data & Analytics |
9/7/2023 1:42:05 AM | Dodge Data & Analytics |
9/23/2023 11:35:48 PM | Granger Landscapes, Inc. |
10/13/2023 12:23:33 PM | Kirven Construction, Inc. |
12/4/2023 10:02:16 AM | R.E. Goodson Construction Co., Inc. |
12/25/2023 1:03:08 AM | PWXPress |
4/22/2024 10:25:50 PM | CLC Construction Inc |
Addition 1
Posted: 8/28/2023
Type of Addition: Addendum No. 1
Overview: There was an error in the total rock quantity for this bid. An addendum is need to re-issue the bid form so it will be corrected. This bid form is to be used in submitting your bid.
Documents:
Addition 2
Posted: 8/31/2023
Type of Addition: In Review
Overview: Bid Tab Attached.
Documents:
Addition 3
Posted: 10/19/2023
Type of Addition: Award Information
Overview: Awarded to Palmetto Mining Co., LLC out of Florence, SC.
Amount: $714,056.04
Question 1
Posted: 8/18/2023
Question: Good afternoon . Is there an option that material could be railed to and then trucked to locations. Tommy Neville Carver Companies
Response: Contractor shall be responsible for determining most feasible and economical options for acquiring materials and hauling to specific sites. The county does not have a specific site for stockpiling materials from rail.
Posted: 8/28/2023
Type of Addition: Addendum No. 1
Overview: There was an error in the total rock quantity for this bid. An addendum is need to re-issue the bid form so it will be corrected. This bid form is to be used in submitting your bid.
Documents:
Posted: 8/31/2023
Type of Addition: In Review
Overview: Bid Tab Attached.
Documents:
Posted: 10/19/2023
Type of Addition: Award Information
Overview: Awarded to Palmetto Mining Co., LLC out of Florence, SC.
Amount: $714,056.04
Posted: 8/18/2023
Question: Good afternoon . Is there an option that material could be railed to and then trucked to locations. Tommy Neville Carver Companies
Response: Contractor shall be responsible for determining most feasible and economical options for acquiring materials and hauling to specific sites. The county does not have a specific site for stockpiling materials from rail.