Buffalo Grove Sealed Solicitation
Title: 2021 Cracksealing Project
Deadline: 3/4/2021 9:00 AM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Solicitation Number: VoBG-2021-07
Description:
This project includes,
but is not limited to, the following major work items: crack routing (pavement)
and filling; and other appurtenant work on various street segments throughout
the Village limits. Any and all questions about the bid document should be submitted to: Gewalt Hamilton Associates, Inc.
Attn: Brian Wesolowski, PE
625 Forest Edge Drive
Vernon Hills, Illinois 60061
(847) 821-6235. bwesolowski@gha-engineers.com no later than 9:00 A.M. on 2/26/2021.
Line Item |
Item # | Description | Purchase Quantity |
Unit Of Measurement |
Units Per UOM |
Total Units | Allow Alt Item Purchase Quantity? | Allow Alt. item? |
Allow Alt. UOM? |
Attachments |
---|---|---|---|---|---|---|---|---|---|---|
1 | - | Crack Routing (Pavement) and Filling in LBS | 35530 | Each | 1 | 35530 |
|
Documents:
Documents as of 2/3/2021 |
---|
Login to view documents |
PLANHOLDERS:
Date | Company Name |
---|---|
2/18/2021 9:47:46 AM | Denler, Inc |
2/18/2021 2:48:20 PM | Rhino Seal Coat |
2/19/2021 7:10:32 AM | SKC Construction.net |
2/22/2021 10:14:36 AM | Crafco, Inc. |
3/4/2021 11:52:03 AM | Denler, Inc |
3/4/2021 1:34:22 PM | DataBid |
3/5/2021 2:10:05 PM | Dodge Data & Analytics |
3/11/2021 2:20:27 PM | ePlan |
3/12/2021 3:17:49 PM | chicagolandconstruction.com |
3/19/2021 2:27:48 PM | ConstructConnect |
4/1/2021 7:50:04 AM | Construction Journal |
10/9/2021 5:25:58 PM | RFx Analyst, Inc. |
1/26/2023 7:57:39 AM | patriot pavement maintenance |
1/31/2023 9:57:49 AM | Freehill Asphalt inc. |
2/22/2024 11:30:34 PM | PWXPress |
Addition 1
Posted: 3/4/2021
Type of Addition: In Review
Overview: Bid Tab attached
Documents:
Addition 2
Posted: 4/7/2021
Type of Addition: Denler Inc
Overview: Due to the scope of the project a contingency of $4505.20 (10% of the project cost) has been authorized.
Amount: $45,052.04
Posted: 3/4/2021
Type of Addition: In Review
Overview: Bid Tab attached
Documents:
Posted: 4/7/2021
Type of Addition: Denler Inc
Overview: Due to the scope of the project a contingency of $4505.20 (10% of the project cost) has been authorized.
Amount: $45,052.04