Description: SCOPE OF WORK
RFP TDD 25-23
DECORATIVE RAILING AT DFWBCC MAIN ENTRANCE
GENERAL REQUIREMENTS
The Destin-Fort Walton Beach Convention Center (DFWBCC) is a multi-purpose facility with approximately 33,000 square feet of indoor meeting space and 38,000 square feet of open-air, fully-equipped outdoor space. Conventions, trade shows, entertainment events, regional sporting events, association events and civic functions are held here on a year-round basis. Visit us at: https://www.destinfwbconventioncenter.com/.
The exterior area around the main entrance features a variety of half-walls that may pose a safety hazard if used for sitting, walking and/or climbing. This is a Request for Proposals (RFP) for the design and installation of decorative railings along the half-walls at the main entrance to the DFWBCC, generally denoted in yellow (upper walls) in the images below.
More detailed images provided within the scope of services.
Upper Entrance Patio Walls Facing Left
Top surface width for all locations: thirteen inches (13”)
Total length for left wall:12’-2”
Total length for center wall: 13’
Total length for right wall: 7’-1”
Upper Entrance Patio Walls Facing Right
Top surface width for all locations: thirteen inches (13”)
Total length for left wall: 7’-1”
Total length for center wall: 23’5
Total length for right wall: 25’-7”
Decorative Railing: The approximate length is 95’, vendor to verify. Bolted to wall cap. Installation included. Railing design shall prevent sitting, walking and/or climbing on top of the walls. Railing shall incorporate the destination’s
Little Adventures Fish Design shown below, but ultimate design, material, finish and construction methodology to be proposed by vendor.
The vendor shall be responsible for the following:
1. Perform all services and furnish all supplies, materials, and equipment as necessary for the design, execution, fabrication, and installation of the railings at the site in accordance with Florida Building Code as applicable.
2. Vendor will be required to obtain and pay for all required permits.
3. Provide a maintenance manual to the County for the Decorative Railings.
The County shall be responsible for the following:
1. Provide the fish design in electronic format for vendor’s use in Decorative Railings.
2. Review and approve the final design.
3. Access to the site for installation purposes.
Reproduction rights shall be afforded to the County for appropriate safety, promotional and educational purposes.
PROPOSAL FORMAT / SELECTION CRITERIA
Proposals MUST be submitted in the following format and criteria will be utilized in the evaluation of proposals:
A. Executive Summary (10 points): Summarize the firm’s background, qualifications and work experience applicable to this solicitation; confirm the firm will comply with the requirements, provisions, terms, and conditions specified in this solicitation; include the firm’s years in business, complete name and address, permit, and contact information for the person authorized to negotiate terms and render binding decisions on contract matters; signed by an authorized representative of the firm.
B. Project Experience (20 points): Demonstrate experience in projects of similar size and scope, preferably for government entities. Provide at least five (5) recently completed projects similar to that described in this RFP, preferably completed by individuals to be assigned to this project. Include the client name, project location, services provided, design material and product, dates services were provided, and budget.
C. Pricing (30 points): Include a total cost of services and any up-front payment requirements for the project. This amount is to be inclusive of all costs associated with labor, supplies, materials, and equipment as necessary for the design, execution, fabrication, and installation of the railings at the site. The most competitive price submitted will be awarded the maximum points. Remaining proposals will receive points on a pro-rated basis. Pricing must be provided in the prescribed format.
D. Decorative Railing Design (40 points): Describe proposed design, material, finish and construction methodology. Provide both narrative and images. Include any required or suggested maintenance practices.
TERM OF CONTRACT
The contract term is anticipated to be no more than one (1) year from Notice to Proceed, but the County wishes the work to be completed sooner.
Note: Failure to provide all the required information, in the required format, may disqualify the vendor from further consideration.
PROCUREMENT SCHEDULE (ANTICIPATED)
RFP Advertised & Posted on Website 01/09/2023
Deadline for Questions 01/23/2023 @ 3:00 P.M.
RFP Response Due Date 02/01/2023 @ 3:00 P.M.
Selection Review Committee Meeting 02/07/2023
Oral Presentations *if needed* Week of February 13, 2023
Recommend Award Via ITA 02/17/2023
Contract Negotiations 02/20/2023 – 02/24/2023
Finalize/Execute Agreement 03/07/2023


Documents:

Documents as of 1/5/2023
Login to view documents
Addition 1

Posted: 1/24/2023

Type of Addition: Addendum 1

Overview:

ADDENDUM 1
January 23, 2023
RFP TDD 25-23 - Decorative Railing Destin-Fort Walton Beach Convention Center (DFWBCC) Main Entrance
Please find the attached document and information below, for the above referenced Addendum 1. This Addendum is hereby made a part of the Contract Documents and Specifications of the above referenced project. All other requirements of the original Contract Documents and Specifications shall remain effective in their respective order.
I. Utilize the Updated “Request for Proposals (RFP) & Respondent’s Acknowledgement” when your company submits its response.
II. Questions/Answers
Question: Is there a proposed railing height from top of the mounting surface to top of the railing?
Answer: The proposed height should be no more than 12” above the finished concrete of the wall, and no lower than 6” above the finished concrete of the wall.
Question: Does the Owner require engineered shop drawings for this railing?
Answer: Yes, the owner will require shop drawings.
See Next Page Attached
The solicitation opening date remains February 1, 2023 at 3:00 p.m. (CST).

Deadline: 2/1/2023 3:00 PM

Solicitation #: RFP TDD 25-23

Documents:

Addition 2

Posted: 2/13/2023

Type of Addition: Cancellation Information

Overview: The only proposer was deemed non-responsive.

Question 1

Posted: 1/16/2023

Question: Does the Owner require engineered shop drawings for this railing?

Response: See Addendum 1.

Question 2

Posted: 1/16/2023

Question: Is there a proposed railing height from top of the mounting surface to top of the railing?

Response: See Addendum 1.

Posted: 1/24/2023

Type of Addition: Addendum 1

Overview:

ADDENDUM 1
January 23, 2023
RFP TDD 25-23 - Decorative Railing Destin-Fort Walton Beach Convention Center (DFWBCC) Main Entrance
Please find the attached document and information below, for the above referenced Addendum 1. This Addendum is hereby made a part of the Contract Documents and Specifications of the above referenced project. All other requirements of the original Contract Documents and Specifications shall remain effective in their respective order.
I. Utilize the Updated “Request for Proposals (RFP) & Respondent’s Acknowledgement” when your company submits its response.
II. Questions/Answers
Question: Is there a proposed railing height from top of the mounting surface to top of the railing?
Answer: The proposed height should be no more than 12” above the finished concrete of the wall, and no lower than 6” above the finished concrete of the wall.
Question: Does the Owner require engineered shop drawings for this railing?
Answer: Yes, the owner will require shop drawings.
See Next Page Attached
The solicitation opening date remains February 1, 2023 at 3:00 p.m. (CST).

Deadline: 2/1/2023 3:00 PM

Solicitation #: RFP TDD 25-23

Documents:

Posted: 2/13/2023

Type of Addition: Cancellation Information

Overview: The only proposer was deemed non-responsive.

Posted: 1/16/2023

Question: Does the Owner require engineered shop drawings for this railing?

Response: See Addendum 1.

Posted: 1/16/2023

Question: Is there a proposed railing height from top of the mounting surface to top of the railing?

Response: See Addendum 1.