County of Beaufort Sealed Solicitation
Title: Charles Lind Brown Drainage
Deadline: 5/18/2023 3:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status:
Solicitation Number: IFB 051823
Description: Beaufort County desires to remove and replace a trench drain system along the back side (east) of the existing Charles Lind Brown Recreation Center.
Pre-Bid Meeting Date: 5/1/2023 2:00 PM
Pre-Bid Meeting Details: This is a virtual meeting. Email victoria.moyer@bcgov.net to receive your invite
Documents:
Documents as of 4/17/2023 |
---|
Login to view documents |
Login to view documents |
PLANHOLDERS:
Date | Company Name |
---|---|
4/17/2023 2:46:10 PM | MRB Group |
4/17/2023 2:46:28 PM | J.R. Wilson Construction Company, Inc. |
4/17/2023 3:04:37 PM | Dorseyco, llc |
4/17/2023 3:06:48 PM | Seacoast Supply |
4/17/2023 3:20:07 PM | Kiewit Infrastructure South Co. |
4/17/2023 3:39:29 PM | Parrish and Partners, LLC |
4/17/2023 11:53:25 PM | Hoft Environmental Service |
4/18/2023 5:33:09 AM | AG Ltd |
4/18/2023 7:11:45 AM | First Construction Management |
4/18/2023 7:19:19 AM | Online Data Services, LLC |
4/18/2023 9:13:52 AM | Integrity Contracting Solutions |
4/18/2023 9:29:06 AM | Soil Consultants Inc. |
4/18/2023 5:40:46 PM | Deltek |
4/19/2023 2:09:26 AM | Dodge Data & Analytics |
4/19/2023 4:46:11 PM | Dragonfly Pond Works |
4/20/2023 9:16:11 AM | Martin & Son Contracting, Inc. |
4/20/2023 3:36:09 PM | Mitchell Brothers, Inc. |
4/21/2023 5:26:51 PM | Wildwood Contractors, Inc. |
4/25/2023 7:05:17 AM | J S Construction Services, Inc. |
4/25/2023 3:34:23 PM | HB&C LTD LLC |
5/1/2023 7:52:05 PM | Sandhill ALS Construction Inc |
5/8/2023 3:10:13 AM | ConstructConnect |
5/10/2023 3:55:31 PM | Sea Island Land Development |
5/12/2023 3:37:45 AM | PWXPress |
5/15/2023 3:40:42 PM | Southeastern Pipe and Drain |
5/25/2023 2:55:28 PM | Dodge Data & Analytics |
6/9/2023 2:10:16 PM | Dodge Data & Analytics |
8/22/2023 8:54:47 AM | FCCI Insurance Group |
Addition 1
Posted: 5/18/2023
Type of Addition: No Submissions
Question 1
Posted: 5/2/2023
Question: Question - is there any restrictions as far as visiting the site? We are working on our proposal and would like to visit sometime this week to see the site in person, if possible. Thanks
Response: There is no restriction. All work is outside and accessible.
Posted: 5/18/2023
Type of Addition: No Submissions
Posted: 5/2/2023
Question: Question - is there any restrictions as far as visiting the site? We are working on our proposal and would like to visit sometime this week to see the site in person, if possible. Thanks
Response: There is no restriction. All work is outside and accessible.