Rio Rancho Public Schools Sealed Solicitation

Title: Category 2 E-rate-Cabling and Infrastructure

Deadline: 12/7/2021 2:00 PM   (UTC-07:00) Mountain Time (US & Canada)

Status: Deadline Expired

Solicitation Number: RFP No. 2022-007-IT

Description:



Rio Rancho Public Schools (RRPS) is seeking to establish a District “Price Agreement” for the purchase of Category 2 Eligible Services for a two (2) year period.  RRPS also has some cabling upgrades as part of the proposal.

RRPS will evaluate Proposals for E-Rate eligible Category 2 Services and equipment. Several Schools (Item#1) need infrastructure copper refreshed from older Cat5 and below.  The current and much larger project is the Districtwide switch refresh. RRPS IT has implemented an HP standardization strategy for minimizing IT costs within the District organization to keep hardware and software as consistent as possible and reducing the number of tools we have to address the same basic needs to overall to help reduce expenditures.   Moreover, RRPS has adopted the philosophy and applied it the other technologies and power infrastructure. 

 

However, in compliance with FCC rules and as stated earlier in the RFP, the district is willing to consider equivalent equipment.  Vendors bidding a non-HP solution MUST provide documentation to demonstrate the equivalency of the proposed solution.   The district will be the arbiter responsible for determining compatibility with existing infrastructure.   






Pre-Bid Meeting Date: 9/30/2021 10:00 AM

Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-bid meeting.Non Mandatory Pre-Proposal: A non-mandatory virtual pre-proposal meeting is scheduled on September 30, 2021, @ 10:00 a.m. use the following meeting link. Meeting ID meet.google.com/yjx-wmht-jqt  Phone Numbers (‪US‬)‪+1 475-441-4593‬‬‬‬‬‬‬ PIN: ‪882 273 528#‬‬‬‬


Documents:

Documents as of 11/30/2021
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Login to view documents
Question 1

Posted: 10/8/2021

Question: During walk thru it was discussed to remove existing cabling and coil above ceiling in each space, in doing so the existing pathways and J hooks may not be viable options. Are we all to include new J hooks and pathways for all new cables in our proposals?

Response: See Addenda 2

Question 2

Posted: 10/8/2021

Question: In MDF/IDF's that do not have enough available space in sleeves for new cables, are we to include new penetrations and sleeves?

Response: See Addenda 2

Question 3

Posted: 10/11/2021

Question: The excel workbook provided has a total footage of Category 6 and 6A as one line item, would it be possible for RRPS to provide the cable lengths desired for each cable type in order for all parties to provide pricing to the same cable length requirements?

Response: See Addenda 2

Question 4

Posted: 10/11/2021

Question: Tab 2 on the Cat 2 RFP 2022-007 IT Pricing WB contains schools not walked or information provided, was this tab included in error or do we need to include pricing for each of these sites as well?

Response: See Addenda 2

Question 5

Posted: 11/16/2021

Question: Our questions were not answered yet, so I am resubmitting: 1. At the site walk though it was discussed to remove the installation of 4 post racks at some IDF locations due to space and or clearance restraints. Please list which IDF rooms the 4 post racks were de-scoped from. 2. Will any drops be required in MDFs/IDFs? 3. Can we get the telecommunications as-built drawings of each school?

Response: This question was received after the submittal deadline.

Posted: 10/8/2021

Question: During walk thru it was discussed to remove existing cabling and coil above ceiling in each space, in doing so the existing pathways and J hooks may not be viable options. Are we all to include new J hooks and pathways for all new cables in our proposals?

Response: See Addenda 2

Posted: 10/8/2021

Question: In MDF/IDF's that do not have enough available space in sleeves for new cables, are we to include new penetrations and sleeves?

Response: See Addenda 2

Posted: 10/11/2021

Question: The excel workbook provided has a total footage of Category 6 and 6A as one line item, would it be possible for RRPS to provide the cable lengths desired for each cable type in order for all parties to provide pricing to the same cable length requirements?

Response: See Addenda 2

Posted: 10/11/2021

Question: Tab 2 on the Cat 2 RFP 2022-007 IT Pricing WB contains schools not walked or information provided, was this tab included in error or do we need to include pricing for each of these sites as well?

Response: See Addenda 2

Posted: 11/16/2021

Question: Our questions were not answered yet, so I am resubmitting: 1. At the site walk though it was discussed to remove the installation of 4 post racks at some IDF locations due to space and or clearance restraints. Please list which IDF rooms the 4 post racks were de-scoped from. 2. Will any drops be required in MDFs/IDFs? 3. Can we get the telecommunications as-built drawings of each school?

Response: This question was received after the submittal deadline.