Title: DEMOGRAPHIC & ENROLLMENT PROJECT STUDY RFP-AS-292
Deadline: 11/4/2022 10:00 AM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Solicitation Number: RFP-AS-292
Description: The purpose of this Request for Proposal (RFP) is to solicit vendors that can provide a Demographic Study to help the Wentzville RIV School District, herein referred to as the District, with long-range student projections which will aid the District in planning for the future.
This RFP will allow the District to review and select the most qualified and economical vendor to perform the studies outlined in the RFP. Work not explicitly covered herein, is not required unless it is reasonably inferable there from as being necessary to produce the intended results. The vendors are requested to respond to each RFP Requirement.
Documents:
Documents as of 10/21/2022 |
---|
Login to view documents |
Addition 1
Posted: 11/4/2022
Type of Addition: In Review
Addition 2
Posted: 12/12/2022
Type of Addition: Award Information
Documents:
Question 1
Posted: 10/24/2022
Question: What is the expected timeline for the study?
Response: As soon as possible
Question 2
Posted: 10/24/2022
Question: Can the vendor work remotely?
Response: If onsite walkthroughs to discuss programming and space are completed then this would require the company to be on site. Other situations may require the company to be on site with additional work being completed remotely.
Question 3
Posted: 10/27/2022
Question: Hello Dr. Mueller, Would it be possible for this project to start in 2023 Q1 and finish in Q2 or is there a different timeline that you had in mind? Thank you!
Response: We need this study to be done as soon as possible. We can not wait until 2023.
Posted: 11/4/2022
Type of Addition: In Review
Posted: 10/24/2022
Question: What is the expected timeline for the study?
Response: As soon as possible
Posted: 10/24/2022
Question: Can the vendor work remotely?
Response: If onsite walkthroughs to discuss programming and space are completed then this would require the company to be on site. Other situations may require the company to be on site with additional work being completed remotely.
Posted: 10/27/2022
Question: Hello Dr. Mueller, Would it be possible for this project to start in 2023 Q1 and finish in Q2 or is there a different timeline that you had in mind? Thank you!
Response: We need this study to be done as soon as possible. We can not wait until 2023.