City of Daytona Beach Sealed Solicitation
Title: FIRST STEP SHELTER CONSTRUCTION
Deadline: 9/7/2018 2:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status: Awarded
Solicitation Number: 0318-2360
Description:
The work generally consists of supplying all necessary labor, equipment and materials for the completion of a concrete “tilt-wall” structure and accessory structures as indicated on the plans and specifications of HALL & OGLE ARCHITECTS, INC. and Parker Mynchenberg & Associates, Inc. This structure will be 15,820 square feet located in Volusia County Florida.
Pre-Bid Meeting Date: 8/8/2018 2:00 PM
Pre-Bid Meeting Details: A NON-MANDATORY PRE-PROPOSAL CONFERENCE will be held at the Daytona Beach City Hall, 301 S. Ridgewood Ave., Room 149B, Daytona Beach, Florida 32114, on August 8, 2018 at 2:00 PM. Interested contractors are urged to attend
Documents:
Addition 1
Posted: 8/3/2018
Type of Addition: Addendum
Overview: Provides responses to bidders' written questions
Pre-Bid Meeting Date: 8/3/2018 11:30 AM
Solicitation #: 0318-2360
Documents:
Addition 2
Posted: 8/3/2018
Type of Addition: Addendum
Overview: Estimate of Probable Cost
Pre-Bid Meeting Date: 8/3/2018 4:55 PM
Solicitation #: 0318-2360
Documents:
Addition 3
Posted: 8/10/2018
Type of Addition: Addendum
Overview: Answering questions from Pre Bid Conference and written questions submitted by Bidders
Deadline: 8/24/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Addition 4
Posted: 8/14/2018
Type of Addition: Addendum
Overview: Site Visit scheduled for Friday, Aug. 17, 2018 at 8:00 am at 3889 W. International Speedway Blvd, Daytona Beach, FL
Deadline: 8/24/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Addition 5
Posted: 8/15/2018
Type of Addition: Addendum
Overview: ANSWERS TO QUESTIONS AND SOME REVISIONS TO PLANS
Deadline: 8/24/2018 2:00 PM
Solicitation #: 0318-0360
Documents:
Addition 6
Posted: 8/16/2018
Type of Addition: Addendum
Overview: Extending Bid Opening Date one week to August 31, 2018
Deadline: 8/31/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Addition 7
Posted: 8/21/2018
Type of Addition: Addendum
Overview: Answering bidders' questions
Deadline: 8/31/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Addition 8
Posted: 8/23/2018
Type of Addition: Addendum
Overview:
Extends opening to 9/7/18
Answers questions, provides drawing revisions
Extends completion time to 240 days to Substantial Completion
Deadline: 9/7/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Addition 9
Posted: 8/31/2018
Type of Addition: Addendum
Overview: Answers Bidder's questions
Deadline: 9/7/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Addition 10
Posted: 9/11/2018
Type of Addition: BID TABULATION
Overview:
Documents:
Addition 11
Posted: 9/14/2018
Type of Addition: BID TABULATION
Overview:
Documents:
Addition 12
Posted: 10/9/2018
Type of Addition: In Review
Addition 13
Posted: 12/3/2018
Type of Addition: Awarded Construction Contract to APM Construction Corp. on 11/7/18
Overview: Base bid with deductive alternate 1 applied
Amount: $4,336,300.00
Documents:
Posted: 8/3/2018
Type of Addition: Addendum
Overview: Provides responses to bidders' written questions
Pre-Bid Meeting Date: 8/3/2018 11:30 AM
Solicitation #: 0318-2360
Documents:
Posted: 8/3/2018
Type of Addition: Addendum
Overview: Estimate of Probable Cost
Pre-Bid Meeting Date: 8/3/2018 4:55 PM
Solicitation #: 0318-2360
Documents:
Posted: 8/10/2018
Type of Addition: Addendum
Overview: Answering questions from Pre Bid Conference and written questions submitted by Bidders
Deadline: 8/24/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Posted: 8/14/2018
Type of Addition: Addendum
Overview: Site Visit scheduled for Friday, Aug. 17, 2018 at 8:00 am at 3889 W. International Speedway Blvd, Daytona Beach, FL
Deadline: 8/24/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Posted: 8/15/2018
Type of Addition: Addendum
Overview: ANSWERS TO QUESTIONS AND SOME REVISIONS TO PLANS
Deadline: 8/24/2018 2:00 PM
Solicitation #: 0318-0360
Documents:
Posted: 8/16/2018
Type of Addition: Addendum
Overview: Extending Bid Opening Date one week to August 31, 2018
Deadline: 8/31/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Posted: 8/21/2018
Type of Addition: Addendum
Overview: Answering bidders' questions
Deadline: 8/31/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Posted: 8/23/2018
Type of Addition: Addendum
Overview:
Extends opening to 9/7/18
Answers questions, provides drawing revisions
Extends completion time to 240 days to Substantial Completion
Deadline: 9/7/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Posted: 8/31/2018
Type of Addition: Addendum
Overview: Answers Bidder's questions
Deadline: 9/7/2018 2:00 PM
Solicitation #: 0318-2360
Documents:
Posted: 10/9/2018
Type of Addition: In Review
Posted: 12/3/2018
Type of Addition: Awarded Construction Contract to APM Construction Corp. on 11/7/18
Overview: Base bid with deductive alternate 1 applied
Amount: $4,336,300.00
Documents: