City of Conroe Sealed Solicitation

Title: Fire Department Metal Building

Deadline: 7/30/2020 2:00 PM   (UTC-06:00) Central Time (US & Canada)

Status: In Review

Solicitation Number: Bid # 0716-2020

Description: Fire Department Metal Building


Pre-Bid Meeting Date: 7/2/2020 8:00 AM

Pre-Bid Meeting Details: Pre-Bid will be at 2357 Mike Meador Parkway (FM 1484) Conroe Texas 77303


Documents:

Documents as of 6/29/2020
BID 0716-2020 COMPLETE.pdf
Addition 1

Posted: 7/7/2020

Type of Addition: Addendum #1 - Geotechnical Report

Overview: Geotechnical soil report for the location

Documents:

Addition 2

Posted: 7/9/2020

Type of Addition: Addendum 2

Overview: Clarification of plans, extended bid due date

Deadline: 7/30/2020 2:00 PM

Solicitation #: 0716-2020

Documents:

Addition 3

Posted: 7/30/2020

Type of Addition: BID TABULATION

Overview: BID TABULATION

Documents:

Addition 4

Posted: 7/30/2020

Type of Addition: In Review

Documents:

Question 1

Posted: 7/2/2020

Question: At the prebid this morning, it was brought up that the GC needs to cover the civil drawings. Can the Owner provide an allowance to the GC for stamped civil drawings. Prices will very for each GC based on the civil engineer they chose, this will help keep it apples to apples.

Response: The Owner will prepare the Civil Drawings and include in an addendum to follow.

Question 2

Posted: 7/3/2020

Question: Is there a soils report? What is the slab elevation in regard to ground elevation? Will soils need to be replaced? Will this project be permitted through the City of Conroe? Who will be responsible for permitting.

Response: The report is in Addendum 1

Posted: 7/7/2020

Type of Addition: Addendum #1 - Geotechnical Report

Overview: Geotechnical soil report for the location

Documents:

Posted: 7/9/2020

Type of Addition: Addendum 2

Overview: Clarification of plans, extended bid due date

Deadline: 7/30/2020 2:00 PM

Solicitation #: 0716-2020

Documents:

Posted: 7/30/2020

Type of Addition: BID TABULATION

Overview: BID TABULATION

Documents:

Posted: 7/30/2020

Type of Addition: In Review

Documents:

Posted: 7/2/2020

Question: At the prebid this morning, it was brought up that the GC needs to cover the civil drawings. Can the Owner provide an allowance to the GC for stamped civil drawings. Prices will very for each GC based on the civil engineer they chose, this will help keep it apples to apples.

Response: The Owner will prepare the Civil Drawings and include in an addendum to follow.

Posted: 7/3/2020

Question: Is there a soils report? What is the slab elevation in regard to ground elevation? Will soils need to be replaced? Will this project be permitted through the City of Conroe? Who will be responsible for permitting.

Response: The report is in Addendum 1