City of Milton Sealed Solicitation
Title: RFP - Submersible Wet Pit Sewage Pumps & Special Accessories (Equipment Only)
Deadline: 3/13/2017 2:00 PM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Solicitation Number: RFP #2017.02.004
Description: The City of Milton is soliciting bids for the purchase of the two (2) Submersible Wet Pit Sewage Pumps & Special Accessories. It is the intent of this notice to seek costs for purchase of the equipment and special accessories only and the City of Milton will perform installation of the new pumps.
Documents:
Documents as of 2/23/2017 |
---|
RFP MunsonHwyLS Pumps FINAL.pdf |
Bid tab sheet only.docx |
Addition 1
Posted: 2/28/2017
Type of Addition: Addendum 1 - Q&A thru 2/28/2017
Overview: Questions and responses on specifications.
Documents:
Addition 2
Posted: 3/15/2017
Type of Addition: In Review
Overview: One (1) company submitted a bid on the equipment. The bid was received from Pump & Process Equipment, 3820 Hopkins St., Pens., FL 32505 in the amount of $61,334.29Staff recommends awarding the bid to Pump & Process Equipment in the amount listed in the bid, subject to staff confirmation that all requirements and specifications have been met.
Addition 3
Posted: 4/14/2017
Type of Addition: Award Information
Overview: Awarded to Pump & Process by Council on March 14, 2017. Negotiated bid amount and equipment; reducing actual cost of effort to $50,534.00
Amount: $61,334.29
Posted: 2/28/2017
Type of Addition: Addendum 1 - Q&A thru 2/28/2017
Overview: Questions and responses on specifications.
Documents:
Posted: 3/15/2017
Type of Addition: In Review
Overview: One (1) company submitted a bid on the equipment. The bid was received from Pump & Process Equipment, 3820 Hopkins St., Pens., FL 32505 in the amount of $61,334.29Staff recommends awarding the bid to Pump & Process Equipment in the amount listed in the bid, subject to staff confirmation that all requirements and specifications have been met.
Posted: 4/14/2017
Type of Addition: Award Information
Overview: Awarded to Pump & Process by Council on March 14, 2017. Negotiated bid amount and equipment; reducing actual cost of effort to $50,534.00
Amount: $61,334.29