Florence County Sealed Solicitation

Title: PAMPLICO HIGH SCHOOL TENNIS COURT PARKING LOT PAVING

Deadline: 10/17/2019 10:00 AM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: 04-19/20

Description:

Florence County, South Carolina (Owner) is accepting bids from licensed and qualified Contractors to perform paving of the Pamplico High School Tennis Court Parking Lot located at 2131 S. Pamplico Highway, Pamplico, SC  29503.   


Documents:

Documents as of 10/3/2019
04-18-19 Resurfacing of Parking Lot - Pamplico School Bid Document.pdf
04-18-19 Site Map.pdf
Addition 1

Posted: 10/17/2019

Type of Addition: In Review

Documents:

Addition 2

Posted: 11/21/2019

Type of Addition: Award Information

Overview: Awarded to Palmetto Corp. on 11-21-19.

Amount: $59,390.00

Question 1

Posted: 10/9/2019

Question: Will any milling be required?

Response: Not sure at this point. Do not include this with your bid. If milling will be needed, it will be handled by means of a change order to the purchase order.

Question 2

Posted: 10/9/2019

Question: Will the contractor be required to re-stripe the parking spaces?

Response: Yes, the contractor will be required to re-stripe the parking spaces. Include this with your bid.

Question 3

Posted: 10/9/2019

Question: Will the contractor be required to rebuild the speed bump within the provided tonnage quantity? If so, will the speed bump need to be painted?

Response: There are no speed bumps in this project. Contractors should view and inspect the site before submitting a bid.

Question 4

Posted: 10/9/2019

Question: Will any parking bumpers need to be placed?

Response: If bumpers are placed there already, then bumpers will need to be placed back. Include this in the price of the bid.

Posted: 10/17/2019

Type of Addition: In Review

Documents:

Posted: 11/21/2019

Type of Addition: Award Information

Overview: Awarded to Palmetto Corp. on 11-21-19.

Amount: $59,390.00

Posted: 10/9/2019

Question: Will any milling be required?

Response: Not sure at this point. Do not include this with your bid. If milling will be needed, it will be handled by means of a change order to the purchase order.

Posted: 10/9/2019

Question: Will the contractor be required to re-stripe the parking spaces?

Response: Yes, the contractor will be required to re-stripe the parking spaces. Include this with your bid.

Posted: 10/9/2019

Question: Will the contractor be required to rebuild the speed bump within the provided tonnage quantity? If so, will the speed bump need to be painted?

Response: There are no speed bumps in this project. Contractors should view and inspect the site before submitting a bid.

Posted: 10/9/2019

Question: Will any parking bumpers need to be placed?

Response: If bumpers are placed there already, then bumpers will need to be placed back. Include this in the price of the bid.