NOTIFICATION REQUEST FOR FORMAL PROPOSAL

Proposal Number: B002628

RESPONSE DUE BY:   08/07/2019

Knee Mill with MillPWR 2-axis B002628

 

THE UNIVERSITY OF ALABAMA IN HUNTSVILLE REQUESTS PROPOSAL FOR ITEMS/SERVICES AS PER THE POSTED SPECIFICATIONS ATTACHED FROM THE PROCUREMENT SERVICES below.

 

To register go to WEBSITE: http://www.uah.edu/business-services/vendors/bid-opportunities Vendor Registration

 

The vendor bid opening day will be August 07th at 1:30pm. I will need an automated bid loaded to UAH Vendor Registry. 

 


Documents:

Documents as of 7/23/2019
Login to view documents
Addition 1

Posted: 8/12/2019

Type of Addition: Sierra Victor Industries is the apparent lowest responsible bidder

Overview: The bid is awarded by total low to Sierra Victor Industries as the apparent lowest responsible bidder, meeting specifications.

Amount: $26,495.00

Documents:

Question 1

Posted: 7/27/2019

Question: This is an online bid or sealed?

Response: This is a online sealed bid.

Question 2

Posted: 7/30/2019

Question: Kindly advise will you offload? Multiple proposal are acceptable? How soon the University need this or equivalent Mill? What documents are required with our proposal? Vendor Disclosure Statement required after an award?

Response: Not sure what you are asking about offload. If you are asking about delivery we have forklifts. Yes multiple is acceptable. Need this after the Po is issued. The bid fill out complete and if you have the item you are information would help. Vendor disclosure Statement is required with the bid package at time of UAH opening.

Question 3

Posted: 8/5/2019

Question: We need atleast 2-3 week for shipping? We can't deliver the machine after the PO# issued.

Response: Sound good.

Question 4

Posted: 8/6/2019

Question: I know after the award a PO will be sent to awarded vendor but I'm talking about the delivery as you told me delivery needed after receipt of PO. We need atleast 3 weeks for delivery after PO.

Response: Sound good.

Posted: 8/12/2019

Type of Addition: Sierra Victor Industries is the apparent lowest responsible bidder

Overview: The bid is awarded by total low to Sierra Victor Industries as the apparent lowest responsible bidder, meeting specifications.

Amount: $26,495.00

Documents:

Posted: 7/27/2019

Question: This is an online bid or sealed?

Response: This is a online sealed bid.

Posted: 7/30/2019

Question: Kindly advise will you offload? Multiple proposal are acceptable? How soon the University need this or equivalent Mill? What documents are required with our proposal? Vendor Disclosure Statement required after an award?

Response: Not sure what you are asking about offload. If you are asking about delivery we have forklifts. Yes multiple is acceptable. Need this after the Po is issued. The bid fill out complete and if you have the item you are information would help. Vendor disclosure Statement is required with the bid package at time of UAH opening.

Posted: 8/5/2019

Question: We need atleast 2-3 week for shipping? We can't deliver the machine after the PO# issued.

Response: Sound good.

Posted: 8/6/2019

Question: I know after the award a PO will be sent to awarded vendor but I'm talking about the delivery as you told me delivery needed after receipt of PO. We need atleast 3 weeks for delivery after PO.

Response: Sound good.