City of Woodstock Sealed Solicitation
Title: RFB 2023 - 01 - Revere Production Well and Treatment Building
Deadline: 3/16/2023 10:00 AM (UTC-05:00) Eastern Time (US & Canada)
Status: Deadline Expired
Solicitation Number: 2023 - 01
Description: The City of Woodstock, Georgia (City) is soliciting bids from contractors for the purpose of furnishing all materials, labor, tools, equipment, and any other miscellaneous items necessary for the construction of the Project# 2023-01, The Revere Production Well and Treatment Building project.
This project includes, but is not limited to, the installation of a well pump and construction of a treatment building off Revere Drive. The scope of work will include the installation of a well pump, treatment building, water main piping and valves, electrical/controls, chemical feed systems, SCADA system, erosion control, fenced enclosure, grassing and related appurtenances.
Pre-Bid Meeting Date: 2/16/2023 10:30 AM
Documents:
Documents as of 1/26/2023 |
---|
Login to view documents |
PLANHOLDERS:
Date | Company Name |
---|---|
1/26/2023 12:09:03 PM | Morgan Contracting, Inc. |
1/26/2023 12:40:47 PM | Astra Group, Inc. |
1/26/2023 5:42:31 PM | PWXPress |
1/27/2023 8:35:46 AM | ECS Southeast LLP |
1/27/2023 8:45:08 PM | Accrete Construction Company |
1/30/2023 3:29:51 AM | Dodge Data & Analytics |
1/30/2023 11:33:28 AM | Complete Site llc |
2/3/2023 11:38:17 AM | Civil Ace Engineering |
2/3/2023 5:39:58 PM | Proshot Concrete, Inc. |
2/16/2023 10:04:51 AM | Reeves Young |
2/16/2023 11:08:24 AM | Szoch Holdings, LLC |
2/16/2023 11:56:10 AM | Construct Connect |
2/28/2023 11:35:32 AM | Revere Control Systems, Inc. |
2/28/2023 12:03:13 PM | Astra Group Inc. |
2/28/2023 4:35:39 PM | MAC and Son Plumbing Inc |
2/28/2023 8:21:02 PM | dodge data and analytics |
3/7/2023 5:25:39 PM | Haren Construction Company, Inc. |
3/8/2023 8:11:27 AM | IHC Construction Companies, LLC |
3/9/2023 10:21:10 AM | AC Schultes of Florida Inc |
3/11/2023 5:53:29 AM | AG Ltd |
3/11/2023 8:00:33 AM | iSqFt |
3/16/2023 9:45:05 AM | TADO Construction, LLC |
3/17/2023 6:44:46 PM | Dexter Fortson Associates, Inc. |
3/24/2023 5:53:05 AM | Dodge Data |
3/28/2023 12:10:43 PM | Dodge Data & Analytics |
3/29/2023 10:43:55 AM | ConstructConnect |
1/25/2024 2:28:35 PM | Sol Construction LLC |
Addition 1
Posted: 1/26/2023
Type of Addition: Addendum 1 - Pre-Proposal Zoom Link
Deadline: 3/1/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Addition 2
Posted: 2/16/2023
Type of Addition: Addendum 1 - Pre-Bid Zoom Link
Solicitation #: 2023 - 01
Documents:
Addition 3
Posted: 2/16/2023
Type of Addition: Addendum 2 - Pre Bid Meeting
Overview: Attendees and Questions
Deadline: 3/1/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Addition 4
Posted: 2/28/2023
Type of Addition: Addendum 2 - Bid Opening Delayed
Deadline: 3/9/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Addition 5
Posted: 3/7/2023
Type of Addition: Addendum 3 - Bid Opening Delay 2
Deadline: 3/16/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Addition 6
Posted: 3/7/2023
Type of Addition: Addendum 4 - Questions Answered
Deadline: 3/16/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Addition 7
Posted: 3/16/2023
Type of Addition: Bid Opening Zoom Link
Deadline: 3/16/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Question 1
Posted: 2/20/2023
Question: Is the well house to be constructed following the CMU Wall Construction detail shown on page 13 and the roofing detail shown on page 14?
Response: See Addendum 4 for Answers to Questions
Question 2
Posted: 2/20/2023
Question: Please provide a detail and specifications for the 10’ wide roll up door shown on page 6.
Response: See Addendum 4 for Answers to Questions
Question 3
Posted: 2/20/2023
Question: The well shed detail on page 13 says “Cover by city.” Please confirm if the city will provide all components including electrical, HVAC, CMU, etc. of this building. Or provide drawings and specifications if contractor to provide.
Response: See Addendum 4 for Answers to Questions
Question 4
Posted: 2/20/2023
Question: Please provide specifications on the roofing
Response: See Addendum 4 for Answers to Questions
Question 5
Posted: 2/20/2023
Question: Please provide specifications on the door shown on page 6.
Response: See Addendum 4 for Answers to Questions
Question 6
Posted: 2/20/2023
Question: Plan sheet 13, well shed detail, calls out 3” steel pipe connecting to the top of the well head. Is the steel pipe black or galvanized. Schedule 40?
Response: See Addendum 4 for Answers to Questions
Question 7
Posted: 2/20/2023
Question: Plan sheet 13 calls out a ½” tap on the 3” pipe connecting to the well pump. Does anything connect to this tap?
Response: See Addendum 4 for Answers to Questions
Question 8
Posted: 2/20/2023
Question: Plan sheet 13 states that the well shed cover is by the city. No concrete or gravel is shown to support this “Cover”, please clarify.
Response: See Addendum 4 for Answers to Questions
Question 9
Posted: 2/20/2023
Question: Plan sheet 3 – what is the size of the water main we are connecting the 4” pipe to? How do we connect to this line, cut in a reducing tee or is a tapping sleeve & tapping valve?
Response: See Addendum 4 for Answers to Questions
Question 10
Posted: 2/20/2023
Question: Plan, site piping notes, item #1 “all 16” dip to be reinforced with (2) ½” rods”. Can gripper gaskets be substituted for restraining rods? Is this requirement pertinent to the 4” from the well shed to the well house also?
Response: See Addendum 4 for Answers to Questions
Question 11
Posted: 2/20/2023
Question: Plan sheet 6 calls out the blow off pipe as 6”, plan sheet 3 calls out this same pipe as 4”, please clarify.
Response: See Addendum 4 for Answers to Questions
Question 12
Posted: 2/20/2023
Question: Plan sheet 3 shows the 4” blow off piping & the 6” pvc drain pipe terminating in rip rap. Is anything suppose to go over the end of each pipe?
Response: See Addendum 4 for Answers to Questions
Question 13
Posted: 2/20/2023
Question: Plan sheet 3 references “4” x 16” mj reducer (typ) see detail page 10. I do not see any detail on a reducer shown on plan sheet 10, please clarify.
Response: See Addendum 4 for Answers to Questions
Question 14
Posted: 2/20/2023
Question: The request for bids states “This project includes, but is not limited to, the installation of a well pump”. Has the city purchased the well pump and the riser pipe? If not does the city want the contactor to provide?
Response: See Addendum 4 for Answers to Questions
Question 15
Posted: 2/20/2023
Question: Please provide davis-bacon wage rates for this project....since this is a GEFA funded project.
Response: See Addendum 4 for Answers to Questions
Question 16
Posted: 2/20/2023
Question: Plan sheet 3 calls out “2” dip blow off to daylight”. I am not aware of 2” dip, please specify an alternate material.
Response: See Addendum 4 for Answers to Questions
Question 17
Posted: 2/20/2023
Question: Note 6 on plan sheet 3 states “contractor shall coordinate with conflicting utilities and pay for any relocation expenses as part of this contract.” Please advise of any conflicting utilities, otherwise the contractor cannot address something that is unknown.
Response: See Addendum 4 for Answers to Questions
Question 18
Posted: 2/20/2023
Question: Plan sheet 6 calls out 6” hdpe for the drain line & 2” dip for the chlorine analyzer, plan sheet 3 calls out the 6” drain line as pvc. Please advise if pvc sch 40 pipe is acceptable for both lines.
Response: See Addendum 4 for Answers to Questions
Question 19
Posted: 2/20/2023
Question: Is there any charge to bring power to the site? Or has the city coordinated power with others for load requirements?
Response: See Addendum 4 for Answers to Questions
Question 20
Posted: 2/20/2023
Question: Is on site testing of concrete & soil compaction required and if so, who pays for the testing?
Response: See Addendum 4 for Answers to Questions
Question 21
Posted: 2/20/2023
Question: Specification section 01025 basis of payment under well pump and treatment building telemetry is listed under each item. Please clarify the meaning of telemetry and where in the specifications or on the plans is it shown.
Response: See Addendum 4 for Answers to Questions
Question 22
Posted: 2/20/2023
Question: Specification section 01025 mentions a fixed generator with an automatic transfer switch, where is the generator shown on the plans & what size is required? If this is temporary system (mobile) please provide data sheet for this unit.
Response: See Addendum 4 for Answers to Questions
Question 23
Posted: 2/20/2023
Question: Will the owner/engineer accept submittals electronically?
Response: See Addendum 4 for Answers to Questions
Question 24
Posted: 2/20/2023
Question: Plan sheet 16 calls out a “VFD” please provide details on the required VFD.
Response: See Addendum 4 for Answers to Questions
Question 25
Posted: 2/20/2023
Question: Specification section 01730 requires the contractor to “Allocate two (2) periods of 8-hours to provide necessary instruction to owner’s designated personnel.” What areas of the project are we to provide instruction on, who is acceptable to give this instruction – please clarify.
Response: See Addendum 4 for Answers to Questions
Question 26
Posted: 2/20/2023
Question: 150 calendar work days due to market conditions for certain components is not reasonable – a minimum of 270 days is probably more reasonable depending on numerous questions and information requested.
Response: See Addendum 4 for Answers to Questions
Question 27
Posted: 2/20/2023
Question: When is anticipated award date?
Response: See Addendum 4 for Answers to Questions
Question 28
Posted: 2/20/2023
Question: Page 13 Article 24 “Construction Clearing” – If the property owner wishes to keep the timber contractor shall cut and stack. After site review the site has heavy timber in excess of the few trees shown on drawing 2. Please advise city’s intention for timber that can be harvested.
Response: See Addendum 4 for Answers to Questions
Question 29
Posted: 2/20/2023
Question: Bid form indicates SCADA (Item #7). Is SCADA to be provided please provide specifications. If the city has a current SCADA contractor, please provide name and contact information
Response: See Addendum 4 for Answers to Questions
Question 30
Posted: 2/20/2023
Question: Bid form (Item #10) request breakout of access drive. There is nothing shown on drawings – please provide detail for drive (traffic loading/curb & gutter/asphalt or concrete).
Response: See Addendum 4 for Answers to Questions
Question 31
Posted: 2/20/2023
Question: Section 00461 “Non-Collusion Affidavit of Subcontractor” – is typical not provided by subcontractor(s) – if awarded can this be provided after bid.
Response: See Addendum 4 for Answers to Questions
Question 32
Posted: 2/20/2023
Question: Is any building permits or fees required?
Response: See Addendum 4 for Answers to Questions
Question 33
Posted: 2/20/2023
Question: Is underground electrical required to be encased?
Response: See Addendum 4 for Answers to Questions
Question 34
Posted: 2/20/2023
Question: Section 01025 Part 3 – 3.02 Well Pump Installation details extensive description of work included – please revise to reflect drawings and specification. See question above that pump house building was by the city.
Response: See Addendum 4 for Answers to Questions
Question 35
Posted: 2/20/2023
Question: Section 01025 Part 3 – 3.03 There is extensive detail such as including generator & transfer switch which requires clarification what is and not included in this project.
Response: See Addendum 4 for Answers to Questions
Question 36
Posted: 2/20/2023
Question: Section 01025-Part 3 – 3.04 details measurement of pipe to be paid in linear feet vs LS pay item
Response: See Addendum 4 for Answers to Questions
Question 37
Posted: 2/20/2023
Question: Section 01025-Part 3 – 3.04 (D) states pay items for valves and sizes vs LS pay item
Response: See Addendum 4 for Answers to Questions
Question 38
Posted: 2/20/2023
Question: Section 01050 Is there 2 control points adjacent work area for surveyor reference.
Response: See Addendum 4 for Answers to Questions
Question 39
Posted: 2/20/2023
Question: Does owner have any available earth for required backfill – or does contractor need to find a source?
Response: See Addendum 4 for Answers to Questions
Question 40
Posted: 2/20/2023
Question: Has new well by owner been pretested for performance – can city provide those results?
Response: See Addendum 4 for Answers to Questions
Question 41
Posted: 2/20/2023
Question: Are there any geo-technical reports available to contractor?
Response: See Addendum 4 for Answers to Questions
Question 42
Posted: 2/20/2023
Question: Is there any work or day restriction times for contractor?
Response: See Addendum 4 for Answers to Questions
Question 43
Posted: 2/20/2023
Question: Section 02660 1.04 Please provide “Current City of Woodstock Standard Development Regulations”
Response: See Addendum 4 for Answers to Questions
Question 44
Posted: 2/20/2023
Question: Section 02660 1.07 Is there an existing tap at current location or will water needed to be hauled for construction and startup.
Response: See Addendum 4 for Answers to Questions
Question 45
Posted: 2/20/2023
Question: Can you provide the current water rate?
Response: See Addendum 4 for Answers to Questions
Question 46
Posted: 2/20/2023
Question: What is the estimated NTP?
Response: See Addendum 4 for Answers to Questions
Question 47
Posted: 2/20/2023
Question: Has there been a budget established for this project to allow the contractor to determine ample funding availability via the GEFA funding before expending cost and time to quote the project?
Response: See Addendum 4 for Answers to Questions
Question 48
Posted: 2/20/2023
Question: Due to the number of questions – can one week be added to bid date?
Response: See Addendum 4 for Answers to Questions
Question 49
Posted: 2/20/2023
Question: Typically if bid is over 25% with GEFA funding they will not allow negotiation to occur between owner and city – or does the owner have other funding available.
Response: See Addendum 4 for Answers to Questions
Posted: 1/26/2023
Type of Addition: Addendum 1 - Pre-Proposal Zoom Link
Deadline: 3/1/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Posted: 2/16/2023
Type of Addition: Addendum 1 - Pre-Bid Zoom Link
Solicitation #: 2023 - 01
Documents:
Posted: 2/16/2023
Type of Addition: Addendum 2 - Pre Bid Meeting
Overview: Attendees and Questions
Deadline: 3/1/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Posted: 2/28/2023
Type of Addition: Addendum 2 - Bid Opening Delayed
Deadline: 3/9/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Posted: 3/7/2023
Type of Addition: Addendum 3 - Bid Opening Delay 2
Deadline: 3/16/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Posted: 3/7/2023
Type of Addition: Addendum 4 - Questions Answered
Deadline: 3/16/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Posted: 3/16/2023
Type of Addition: Bid Opening Zoom Link
Deadline: 3/16/2023 10:00 AM
Solicitation #: 2023 - 01
Documents:
Posted: 2/20/2023
Question: Is the well house to be constructed following the CMU Wall Construction detail shown on page 13 and the roofing detail shown on page 14?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Please provide a detail and specifications for the 10’ wide roll up door shown on page 6.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: The well shed detail on page 13 says “Cover by city.” Please confirm if the city will provide all components including electrical, HVAC, CMU, etc. of this building. Or provide drawings and specifications if contractor to provide.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Please provide specifications on the roofing
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Please provide specifications on the door shown on page 6.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Plan sheet 13, well shed detail, calls out 3” steel pipe connecting to the top of the well head. Is the steel pipe black or galvanized. Schedule 40?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Plan sheet 13 calls out a ½” tap on the 3” pipe connecting to the well pump. Does anything connect to this tap?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Plan sheet 13 states that the well shed cover is by the city. No concrete or gravel is shown to support this “Cover”, please clarify.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Plan sheet 3 – what is the size of the water main we are connecting the 4” pipe to? How do we connect to this line, cut in a reducing tee or is a tapping sleeve & tapping valve?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Plan, site piping notes, item #1 “all 16” dip to be reinforced with (2) ½” rods”. Can gripper gaskets be substituted for restraining rods? Is this requirement pertinent to the 4” from the well shed to the well house also?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Plan sheet 6 calls out the blow off pipe as 6”, plan sheet 3 calls out this same pipe as 4”, please clarify.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Plan sheet 3 shows the 4” blow off piping & the 6” pvc drain pipe terminating in rip rap. Is anything suppose to go over the end of each pipe?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Plan sheet 3 references “4” x 16” mj reducer (typ) see detail page 10. I do not see any detail on a reducer shown on plan sheet 10, please clarify.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: The request for bids states “This project includes, but is not limited to, the installation of a well pump”. Has the city purchased the well pump and the riser pipe? If not does the city want the contactor to provide?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Please provide davis-bacon wage rates for this project....since this is a GEFA funded project.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Plan sheet 3 calls out “2” dip blow off to daylight”. I am not aware of 2” dip, please specify an alternate material.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Note 6 on plan sheet 3 states “contractor shall coordinate with conflicting utilities and pay for any relocation expenses as part of this contract.” Please advise of any conflicting utilities, otherwise the contractor cannot address something that is unknown.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Plan sheet 6 calls out 6” hdpe for the drain line & 2” dip for the chlorine analyzer, plan sheet 3 calls out the 6” drain line as pvc. Please advise if pvc sch 40 pipe is acceptable for both lines.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Is there any charge to bring power to the site? Or has the city coordinated power with others for load requirements?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Is on site testing of concrete & soil compaction required and if so, who pays for the testing?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Specification section 01025 basis of payment under well pump and treatment building telemetry is listed under each item. Please clarify the meaning of telemetry and where in the specifications or on the plans is it shown.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Specification section 01025 mentions a fixed generator with an automatic transfer switch, where is the generator shown on the plans & what size is required? If this is temporary system (mobile) please provide data sheet for this unit.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Will the owner/engineer accept submittals electronically?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Plan sheet 16 calls out a “VFD” please provide details on the required VFD.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Specification section 01730 requires the contractor to “Allocate two (2) periods of 8-hours to provide necessary instruction to owner’s designated personnel.” What areas of the project are we to provide instruction on, who is acceptable to give this instruction – please clarify.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: 150 calendar work days due to market conditions for certain components is not reasonable – a minimum of 270 days is probably more reasonable depending on numerous questions and information requested.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: When is anticipated award date?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Page 13 Article 24 “Construction Clearing” – If the property owner wishes to keep the timber contractor shall cut and stack. After site review the site has heavy timber in excess of the few trees shown on drawing 2. Please advise city’s intention for timber that can be harvested.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Bid form indicates SCADA (Item #7). Is SCADA to be provided please provide specifications. If the city has a current SCADA contractor, please provide name and contact information
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Bid form (Item #10) request breakout of access drive. There is nothing shown on drawings – please provide detail for drive (traffic loading/curb & gutter/asphalt or concrete).
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Section 00461 “Non-Collusion Affidavit of Subcontractor” – is typical not provided by subcontractor(s) – if awarded can this be provided after bid.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Is any building permits or fees required?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Is underground electrical required to be encased?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Section 01025 Part 3 – 3.02 Well Pump Installation details extensive description of work included – please revise to reflect drawings and specification. See question above that pump house building was by the city.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Section 01025 Part 3 – 3.03 There is extensive detail such as including generator & transfer switch which requires clarification what is and not included in this project.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Section 01025-Part 3 – 3.04 details measurement of pipe to be paid in linear feet vs LS pay item
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Section 01025-Part 3 – 3.04 (D) states pay items for valves and sizes vs LS pay item
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Section 01050 Is there 2 control points adjacent work area for surveyor reference.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Does owner have any available earth for required backfill – or does contractor need to find a source?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Has new well by owner been pretested for performance – can city provide those results?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Are there any geo-technical reports available to contractor?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Is there any work or day restriction times for contractor?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Section 02660 1.04 Please provide “Current City of Woodstock Standard Development Regulations”
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Section 02660 1.07 Is there an existing tap at current location or will water needed to be hauled for construction and startup.
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Can you provide the current water rate?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: What is the estimated NTP?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Has there been a budget established for this project to allow the contractor to determine ample funding availability via the GEFA funding before expending cost and time to quote the project?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Due to the number of questions – can one week be added to bid date?
Response: See Addendum 4 for Answers to Questions
Posted: 2/20/2023
Question: Typically if bid is over 25% with GEFA funding they will not allow negotiation to occur between owner and city – or does the owner have other funding available.
Response: See Addendum 4 for Answers to Questions