Peralta Community College District Sealed Solicitation
Title: Bid No. 20-21/07 Laney Perimeter Paving Rehabilitation
Deadline: 3/2/2021 2:00 PM (UTC-08:00) Pacific Time (US & Canada)
Status: Awarded
Solicitation Number: Bid No. 20-21/07
Description: The Laney Perimeter Paving Rehabilitation Project includes: - Asphalt Concrete (AC) pavement rehabilitation inclusive of grind and inlay, spot reconstruction, and/or slurry seal along perimeter of Laney College with slurry seal application and restriping at North Parking Lot and Southwest Parking Lot; removal of parking striping, wheel stops, and parking signs from Southeast Parking Lot; curb repainting, lettering and miscellaneous restriping as indicated; removal and replacement of bollards; removal of portion of storm drain pipe and installation of new catch basin; and installation of concrete caps above shallow trenches as necessary.
Pre-Bid Meeting Date: 2/16/2021 10:00 AM
Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-bid meeting.Hi there, SERAPHINE NZOMO is inviting you to a scheduled Zoom meeting. Topic: Laney Perimeter Paving Rehabilitation Time: Feb 9, 2021 10:00 AM Pacific Time (US and Canada) Join from PC, Mac, Linux, iOS or Android: https://cccconfer.zoom.us/j/94539605307 Or iPhone one-tap (US Toll): +16699006833,94539605307# or +13462487799,94539605307# Or Telephone: Dial: +1 669 900 6833 (US Toll) +1 346 248 7799 (US Toll) +1 253 215 8782 (US Toll) +1 301 715 8592 (US Toll) +1 312 626 6799 (US Toll) +1 646 876 9923 (US Toll) Meeting ID: 945 3960 5307 International numbers available: https://cccconfer.zoom.us/u/a9txZmuOC Or Skype for Business (Lync): SIP:94539605307@lync.zoom.us
Documents:
Addition 1
Posted: 3/3/2021
Type of Addition: In Review
Overview: PM and Purchasing reviewing bids received.
Addition 2
Posted: 3/3/2021
Type of Addition: Bid Results
Overview: There were five bids received for this project. See the Bid Tabulation sheet attached.
Documents:
Addition 3
Posted: 8/27/2021
Type of Addition: Bid # 20-21/07 awarded to Tri Valley Excavating Company, Inc.
Amount: $230,277.00
Documents:
Addition 4
Posted: 8/27/2021
Type of Addition: Award Information
Question 1
Posted: 2/17/2021
Question: Plan sheet C2.2 shows installation of 18" DI on 18" Storm Drain Line. Is this supposed to a 36" DI? Additionally, can you give us the depth of the existing storm drain line?
Response: The drain inlet noted on sheet C2.2 is deleted. Detail 2 on sheet C4.1 is no longer applicable.
Posted: 3/3/2021
Type of Addition: In Review
Overview: PM and Purchasing reviewing bids received.
Posted: 3/3/2021
Type of Addition: Bid Results
Overview: There were five bids received for this project. See the Bid Tabulation sheet attached.
Documents:
Posted: 8/27/2021
Type of Addition: Bid # 20-21/07 awarded to Tri Valley Excavating Company, Inc.
Amount: $230,277.00
Documents:
Posted: 8/27/2021
Type of Addition: Award Information
Posted: 2/17/2021
Question: Plan sheet C2.2 shows installation of 18" DI on 18" Storm Drain Line. Is this supposed to a 36" DI? Additionally, can you give us the depth of the existing storm drain line?
Response: The drain inlet noted on sheet C2.2 is deleted. Detail 2 on sheet C4.1 is no longer applicable.