Rio Rancho Public Schools Sealed Solicitation
Title: Synthetic Grass Field Replacement @ V. Sue Cleveland High School - Volume 1 (Pricing)
Deadline: 11/11/2021 2:00 PM (UTC-07:00) Mountain Time (US & Canada)
Status: Deadline Expired
Solicitation Number: RFP No. 2022-009-FAC
Description: Refer to Specification Section 01 1000 - Summary in the Project Manual
Pre-Bid Meeting Date: 10/14/2021 10:00 AM
Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-bid meeting.Mandatory Pre-Proposal Conference – Followed by a Site Visit RRPS Board Rooms 1&2, 500 Laser Road NW Rio Rancho, NM 87124
Documents:
Documents as of 11/5/2021 |
---|
Login to view documents |
Login to view documents |
Login to view documents |
Login to view documents |
Login to view documents |
Question 1
Posted: 10/19/2021
Question: If available, will you please upload the pre-bid sign in sheet from the meeting on the 14th? Thanks.
Response: See Addenda No. 1
Question 2
Posted: 10/20/2021
Question: Page 80 is missing the signature on the price proposal page.
Response: See Addenda No. 1
Question 3
Posted: 10/27/2021
Question: Cleveland 1. Is there a wage decision for this project? 2. Section 01 2100 for allowances includes 2 allowances. 1 For converting the as-builts to CAD but there is no bid item for this. Will one be added? The allowance for underdrain does not include an amount. What amount should be included for this? 3. GRT is not on the bid form. Will this be added to the bid form or should the contractor include this on each bid item?
Response: See Addenda No. 1
Question 4
Posted: 11/3/2021
Question: Although the addendum states the $20,000 allowance for conversion of s-built drawings to CAD file was removed, the allowance is still present on sheet 00 119 73. Please clarify.
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Question 5
Posted: 11/3/2021
Question: Page C-102, Demolition Plan, keyed note 1 calls for removal and disposal of turf field. Is aggregate base to be removed with turf field or is aggregate base to remain? If entire existing aggregate base is not removed, please update quantity of Bid Proposal Form, page 00 1119-80 Base Bid item 7.
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Question 6
Posted: 11/3/2021
Question: Keyed note 4 on page C-104 calls for a 40” high CMU wall. Please locate the beginning and end of the wall, exact location, and specify type of CMU (color, etc.)
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Question 7
Posted: 11/3/2021
Question: Page C-104 Grading & Drainage, keyed note 3 for base bid item 5 - header curb, please indicate the exact location, beginning and end of the header curb. Also, verify the quantity on the Bid Proposal Form.
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Question 8
Posted: 11/3/2021
Question: The Statement of Qualifications for Subcontractors, Section 3a states “Provide copies of Performance Evaluation Reports prepared in connection with projects described in Para. 3.a.above.” Can you please clarify what information you are looking for?
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Question 9
Posted: 11/3/2021
Question: Base bid form, add alt 1, item 5 specifies a 4’ dia MH type C. Please indicate where on the plan this item is to be installed.
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Question 10
Posted: 11/3/2021
Question: Please indicate location of excavation for Bid item number 1 for additive alternate 2 – Unclassified Excavation and confirm quantity.
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Question 11
Posted: 11/3/2021
Question: Where is Add. Alt. 1 - Field Underdrain System shown on the plans? What are quantities shown on Add. Alt. 1 based on?
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Question 12
Posted: 11/3/2021
Question: Demolition note #8 on C-102 – states “remove and dispose of chain link fence”. Are these costs are to be carried under the base bid, or which alternate?
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Question 13
Posted: 11/3/2021
Question: Base Bid Item #4 on bid form “liner, base rock section, leveling course, nailer board” is for 11,791 SY. Please confirm this is only for the area where the high jump is to be demolished and the synthetic turf base section is to be installed (approximately 565 SY).
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Question 14
Posted: 11/3/2021
Question: Base Bid Item #7 on bid form states that the subgrade preparation of 12” at 95% compaction is for 11,791 SY. Please confirm this is only for the area where the high jump is to be demolished and the synthetic turf base section is to be installed (approximately 565 SY).
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Posted: 10/19/2021
Question: If available, will you please upload the pre-bid sign in sheet from the meeting on the 14th? Thanks.
Response: See Addenda No. 1
Posted: 10/20/2021
Question: Page 80 is missing the signature on the price proposal page.
Response: See Addenda No. 1
Posted: 10/27/2021
Question: Cleveland 1. Is there a wage decision for this project? 2. Section 01 2100 for allowances includes 2 allowances. 1 For converting the as-builts to CAD but there is no bid item for this. Will one be added? The allowance for underdrain does not include an amount. What amount should be included for this? 3. GRT is not on the bid form. Will this be added to the bid form or should the contractor include this on each bid item?
Response: See Addenda No. 1
Posted: 11/3/2021
Question: Although the addendum states the $20,000 allowance for conversion of s-built drawings to CAD file was removed, the allowance is still present on sheet 00 119 73. Please clarify.
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Posted: 11/3/2021
Question: Page C-102, Demolition Plan, keyed note 1 calls for removal and disposal of turf field. Is aggregate base to be removed with turf field or is aggregate base to remain? If entire existing aggregate base is not removed, please update quantity of Bid Proposal Form, page 00 1119-80 Base Bid item 7.
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Posted: 11/3/2021
Question: Keyed note 4 on page C-104 calls for a 40” high CMU wall. Please locate the beginning and end of the wall, exact location, and specify type of CMU (color, etc.)
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Posted: 11/3/2021
Question: Page C-104 Grading & Drainage, keyed note 3 for base bid item 5 - header curb, please indicate the exact location, beginning and end of the header curb. Also, verify the quantity on the Bid Proposal Form.
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Posted: 11/3/2021
Question: The Statement of Qualifications for Subcontractors, Section 3a states “Provide copies of Performance Evaluation Reports prepared in connection with projects described in Para. 3.a.above.” Can you please clarify what information you are looking for?
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Posted: 11/3/2021
Question: Base bid form, add alt 1, item 5 specifies a 4’ dia MH type C. Please indicate where on the plan this item is to be installed.
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Posted: 11/3/2021
Question: Please indicate location of excavation for Bid item number 1 for additive alternate 2 – Unclassified Excavation and confirm quantity.
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Posted: 11/3/2021
Question: Where is Add. Alt. 1 - Field Underdrain System shown on the plans? What are quantities shown on Add. Alt. 1 based on?
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Posted: 11/3/2021
Question: Demolition note #8 on C-102 – states “remove and dispose of chain link fence”. Are these costs are to be carried under the base bid, or which alternate?
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Posted: 11/3/2021
Question: Base Bid Item #4 on bid form “liner, base rock section, leveling course, nailer board” is for 11,791 SY. Please confirm this is only for the area where the high jump is to be demolished and the synthetic turf base section is to be installed (approximately 565 SY).
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)
Posted: 11/3/2021
Question: Base Bid Item #7 on bid form states that the subgrade preparation of 12” at 95% compaction is for 11,791 SY. Please confirm this is only for the area where the high jump is to be demolished and the synthetic turf base section is to be installed (approximately 565 SY).
Response: Pending Review and Response (Answer will be provided in Addenda No. 2)