City of Aztec Sealed Solicitation

Title: RFP 2022-783 FIRE ALARM SYSTEM INSTALLATION

Deadline: 7/29/2021 2:00 PM   (UTC-07:00) Mountain Time (US & Canada)

Status: Awarded

Solicitation Number: RFP 2022-783

Description:

The City of Aztec, New Mexico (City) is requesting proposes to remove and install brand new fire alarm system in the Boys and Girls Club facility.

 

A pre-bid site visit (not mandatory) is scheduled for Thursday, July 22, 2021, 2:00 PM, at Aztec Boys and Girls club, Aztec NM 87410.  Last day for questions is Monday, July 22, 2021, 2:00 PM.

 

Proposal documents, including instructions to Bidders and Bid Forms are available online by accessing the City’s purchasing webpage through http://www.aztecnm.gov/purchasing.html or Vendor Registry or by contacting Eduard Vodovoz at (505) 334-7656 or evodovoz@aztecnm.gov

Sealed proposals, clearly marked as RFP 2022-783 Fire Alarm System Installation will be received by the Purchasing Office at 201 W. Chaco, Aztec, New Mexico 87410, until the hour of 2:00 p.m. on Wednesday, July 29, 2021. Proposals received after that date and time will be considered non-responsive and returned unopened.

 

Any proposal received after stated due date and time will be returned unopened. If proposals are sent by mail to the City of Aztec, the Offeror shall be responsible for actual delivery of the proposal to the Purchasing Office before the advertised date and hour for the opening. Please note that the City of Aztec, NM is NOT a guaranteed delivery point for any of the various delivery services.  Proposals which are delayed will not be considered and will be returned unopened.

Offerors are responsible for monitoring the website referenced above for notifications of changes and addenda related to this solicitation.


Pre-Bid Meeting Date: 7/22/2021 2:00 PM

Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-bid meeting.Boys and Girls club Aztec NM


Documents:

Documents as of 7/20/2021
RFP 2022-783 fire alarm system installation.pdf
00-00000-20-00094_00-00000-20-00094 GSA, Facilities Maint & Mgmt 0125.pdf (1).PDF
30-00000-13-00085_30-000-13-00085 Fire Alarm & Suppression Services 0623.pdf.PDF
Aztec Family Center - Boys & Girls Club (1998) .pdf
Addition 1

Posted: 8/9/2021

Type of Addition: Awardee Network Cabling INC

Amount: $38,916.46

Documents:

Addition 2

Posted: 8/9/2021

Type of Addition: Award Information

Question 1

Posted: 7/19/2021

Question: Can we get a copy of the as-builts for the Boys and Girls facility?

Response: A copy has been uploaded to the documents section. Please let me know if you're able to view.

Question 2

Posted: 7/19/2021

Question: Does the city of Aztec have CAD drawing for the building?

Response: There are no CAD drawings available

Question 3

Posted: 7/19/2021

Question: On Preliminary Schedule I have Deadline for Questions and Pre-Bid site visit on the same day. What if questions arise after Pre-Bid site visit. Will we be able to get the questions answered?

Response: I understand that last minute questions may/will arise. However, to reduce lead time for questions and answers, we would like for vendors to look at the site and ask all necessary questions with the project manager on day of the site visit. We are available for questions afterwards if necessary.

Question 4

Posted: 7/19/2021

Question: Is the new fire alarm system a stand alone system or will it need to be tied into another system?

Response: It is a stand alone system.

Posted: 8/9/2021

Type of Addition: Awardee Network Cabling INC

Amount: $38,916.46

Documents:

Posted: 8/9/2021

Type of Addition: Award Information

Posted: 7/19/2021

Question: Can we get a copy of the as-builts for the Boys and Girls facility?

Response: A copy has been uploaded to the documents section. Please let me know if you're able to view.

Posted: 7/19/2021

Question: Does the city of Aztec have CAD drawing for the building?

Response: There are no CAD drawings available

Posted: 7/19/2021

Question: On Preliminary Schedule I have Deadline for Questions and Pre-Bid site visit on the same day. What if questions arise after Pre-Bid site visit. Will we be able to get the questions answered?

Response: I understand that last minute questions may/will arise. However, to reduce lead time for questions and answers, we would like for vendors to look at the site and ask all necessary questions with the project manager on day of the site visit. We are available for questions afterwards if necessary.

Posted: 7/19/2021

Question: Is the new fire alarm system a stand alone system or will it need to be tied into another system?

Response: It is a stand alone system.