Title: A&E Services for Renovations at the Law Enforcement Complex

Deadline: 9/4/2020 2:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: RFQ 2021-07

Description: Dorchester County is soliciting Requests for Qualifications (RFQ) to qualify firms for a contract for the complete architectural and engineering services for the renovations needed at the Law Enforcement Complex, located at 212 Deming Way, Summerville, SC.


Pre-Bid Meeting Date: 8/14/2020 1:00 PM

Pre-Bid Meeting Details: A mandatory site visit will be held at 1:00 PM on August 14, 2020. Interested offerors are required to have a representative present that day and are asked to meet in front of the Sheriff’s Office, located at 212 Deming Way, Summerville, SC 29483. Face masks will be required, and participants are asked to practice social distancing.


Documents:

Documents as of 8/31/2020
Login to view documents
Login to view documents
Addition 1

Posted: 8/28/2020

Type of Addition: Addendum

Overview: Addendum to answer questions.

Documents:

Addition 2

Posted: 9/4/2020

Type of Addition: In Review

Addition 3

Posted: 11/6/2020

Type of Addition: Award Information

Overview: This contract has been awarded to Rosenblum Coe Architects, Inc.

Question 1

Posted: 8/5/2020

Question: In reference to Section D.C.c Proposed ideas and proposed timeline for site selection, design, and construction. Are there any previous studies, master plan, or existing facilities drawings (i.e. floor plans) that can be made available for reference?

Response: Please see Addendum 1.

Question 2

Posted: 8/19/2020

Question: Can you please clarify the function of the current crime scene lab in the facility? What is anticipated future function in phase II renovation?

Response: Please see Addendum 1.

Posted: 8/28/2020

Type of Addition: Addendum

Overview: Addendum to answer questions.

Documents:

Posted: 9/4/2020

Type of Addition: In Review

Posted: 11/6/2020

Type of Addition: Award Information

Overview: This contract has been awarded to Rosenblum Coe Architects, Inc.

Posted: 8/5/2020

Question: In reference to Section D.C.c Proposed ideas and proposed timeline for site selection, design, and construction. Are there any previous studies, master plan, or existing facilities drawings (i.e. floor plans) that can be made available for reference?

Response: Please see Addendum 1.

Posted: 8/19/2020

Question: Can you please clarify the function of the current crime scene lab in the facility? What is anticipated future function in phase II renovation?

Response: Please see Addendum 1.