City of Woodstock Sealed Solicitation
Title: RFB 2023 - 13 - Wellington Manor Service Line Replacement
Deadline: 4/4/2023 10:00 AM (UTC-05:00) Eastern Time (US & Canada)
Status: In Review
Solicitation Number: 2023 - 13
Description: The City of Woodstock, Georgia, herein referred to as the City, is accepting bids from qualified contractors for the purpose of replacing the aging poly water service line with new copper tubing in the Wellington Manor neighborhood, hereinafter referred to as the “PROJECT”. Material for the new water service line will be provided. The water service line will connect to existing meters with a total of 129 services: 127 homes, one pool house, and one irrigation line. In addition to the water service line, seven driveway panels will need to be replaced and the landscaped areas surrounding the driveways and sidewalk will need to be brought back to like conditions.
Documents:
Documents as of 2/24/2023 |
---|
Login to view documents |
PLANHOLDERS:
Date | Company Name |
---|---|
3/2/2023 6:13:05 PM | MAC and Son Plumbing Inc |
3/3/2023 1:37:44 AM | AG Ltd |
3/7/2023 3:17:23 PM | RDJE, Inc |
3/8/2023 10:53:13 AM | Sol Construction LLC |
4/4/2023 8:53:31 AM | S.H. Creel Contracting |
4/12/2023 2:01:42 PM | dodge data and analytics |
4/14/2023 5:54:13 AM | Dodge Data & Analytics |
4/19/2023 7:50:03 AM | Dodge Data |
5/9/2023 1:24:24 PM | ConstructConnect |
Addition 1
Posted: 4/3/2023
Type of Addition: Addendum 1 - Bid Opening Zoom Link
Deadline: 4/4/2023 10:00 AM
Solicitation #: 2023 - 13
Documents:
Addition 2
Posted: 4/18/2023
Type of Addition: In Review - Bid Tabulation as Read
Documents:
Question 1
Posted: 3/24/2023
Question: 1. Is there existing casing on the existing long side services? 2. Will casing be required on long side services? 3. Will a new tap be required? 4. How will qty overages be addressed on the driveway and sidewalk demo and replace?
Response: In our experience from replacing long side services in Wellington Manor, all long side services have had casings. The new service lines will be connected to the existing taps, new taps will not be required. The contractor will be responsible for ordering and paying for any concrete overages that occur during the project. We do have a contingency already for an extra concrete driveway apron if necessary.
Posted: 4/3/2023
Type of Addition: Addendum 1 - Bid Opening Zoom Link
Deadline: 4/4/2023 10:00 AM
Solicitation #: 2023 - 13
Documents:
Posted: 4/18/2023
Type of Addition: In Review - Bid Tabulation as Read
Documents:
Posted: 3/24/2023
Question: 1. Is there existing casing on the existing long side services? 2. Will casing be required on long side services? 3. Will a new tap be required? 4. How will qty overages be addressed on the driveway and sidewalk demo and replace?
Response: In our experience from replacing long side services in Wellington Manor, all long side services have had casings. The new service lines will be connected to the existing taps, new taps will not be required. The contractor will be responsible for ordering and paying for any concrete overages that occur during the project. We do have a contingency already for an extra concrete driveway apron if necessary.