Kaufman County Sealed Solicitation
Title: Construction Manager Agent Services - Kaufman County Master Plan Facility Projects
Deadline: 8/6/2021 2:00 PM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Solicitation Number: 21-21
Description:
OBJECTIVES OF THIS
REQUEST FOR QUALIFICATIONS – Kaufman County leadership is interested in
soliciting SOQ in response to this Request for Qualifications 21-21 (“RFQ”)
from contractors, hereafter referred to collectively as “Proposers”, to provide
Construction Manager-Agent Services as more particularly described in Section 4
(Scope of Work) of this RFQ.DESCRIPTION OF
KAUFMAN COUNTY – At
808 square miles and more than an estimated 120,000 residents, U.S. Census
Bureau estimates now rank Kaufman County as the 3rd in the nation
for the greatest percentage growth between 2017 and 2018, among counties of
20,000 people or more and continues to grow.
PROJECT BACKGROUND – Kaufman County
leadership is engaged in the programming, design, and/or construction of a wide
variety of both new and renovation projects.
These projects include, but are not limited to, historical Courthouse
renovations, court facilities, office space, and other public buildings. Specific projects are not known at this time.
Documents:
Documents as of 6/29/2021 |
---|
21-21 RFQ.pdf |
Addition 2
Posted: 8/6/2021
Type of Addition: Responses Received 08.06.2021
Overview:
Documents:
Addition 3
Posted: 9/14/2021
Type of Addition: BID TABULATION
Overview:
Documents:
Question 1
Posted: 7/6/2021
Question: Could you please clarify if a response must include the Legal Notice in its entirety (RFQ page 4-7 with a signature on page 7) as well as the Execution of Offer (Section 5)? Para 3.2 Preparation and Submittal Instructions does not mention pages 4-7 of the RFQ but on RFQ page 7 there is a statement that this original must be included in its entirety with the response. Also while Form CIQ was included in the RFQ, Para 3.2 Preparation and Submittal Instructions does not mention if or where it is to be included. Does it need to be in Tab H?
Response: RFQ pages 4-7, Execution of Offer, and Form CIQ, with signatures should be submitted with your response. These pages will NOT count against the total page-count for your response.
Posted: 8/6/2021
Type of Addition: Responses Received 08.06.2021
Overview:
Documents:
Posted: 7/6/2021
Question: Could you please clarify if a response must include the Legal Notice in its entirety (RFQ page 4-7 with a signature on page 7) as well as the Execution of Offer (Section 5)? Para 3.2 Preparation and Submittal Instructions does not mention pages 4-7 of the RFQ but on RFQ page 7 there is a statement that this original must be included in its entirety with the response. Also while Form CIQ was included in the RFQ, Para 3.2 Preparation and Submittal Instructions does not mention if or where it is to be included. Does it need to be in Tab H?
Response: RFQ pages 4-7, Execution of Offer, and Form CIQ, with signatures should be submitted with your response. These pages will NOT count against the total page-count for your response.