Fort Mill School District Sealed Solicitation

Title: District Door Replacements

Deadline: 5/15/2019 11:00 AM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: 18-076

Description: Fort Mill School District is in need of contractors to replace various exterior doors throughout the Fort Mill School District.  Removal of old doors/door frames will take place during the summer of 2019 and into the fall/winter of 2019 when students are NOT present.  There will be a MANDATORY site visit.  This will be the only opportunity to view the projects.  Award will be made to one or more contractors, awarded by location.


Pre-Bid Meeting Date: 5/6/2019 9:00 AM

Pre-Bid Meeting Details: There will be a MANDATORY site visit on Monday, May 6, 2019 from 9 am - 2 pm. We will begin at Springfield Elementary School, 1691 Springfield Parkway, Fort Mill, SC 29715,


Documents:

Documents as of 4/24/2019
18-076 District Door Replacements.pdf
school calendars.pdf
Addition 1

Posted: 5/10/2019

Type of Addition: Addendum #1

Overview: Fort Mill School District is issuing Addendum #1 to clarify the scope of work/specifications as reviewed during our MANDATORY site visit on May 6, 2019.

Documents:

Addition 2

Posted: 5/15/2019

Type of Addition: Award Information

Overview: Fort Mill School District intends to award the contract for District Door Replacements to Rock Hill Industrial Piping & Fabrication, Inc. Please see the attached documents.

Amount: $259,731.00

Documents:

Posted: 5/10/2019

Type of Addition: Addendum #1

Overview: Fort Mill School District is issuing Addendum #1 to clarify the scope of work/specifications as reviewed during our MANDATORY site visit on May 6, 2019.

Documents:

Posted: 5/15/2019

Type of Addition: Award Information

Overview: Fort Mill School District intends to award the contract for District Door Replacements to Rock Hill Industrial Piping & Fabrication, Inc. Please see the attached documents.

Amount: $259,731.00

Documents: