Wentzville R-IV School District Sealed Solicitation

Title: NORTH POINT HIGH SCHOOL VISITOR STADIUM BLEACHERS RFB-M-279

Deadline: 5/25/2022 10:30 AM   (UTC-06:00) Central Time (US & Canada)

Status: Awarded

Solicitation Number: RFB-M-279

Description: The purpose of this Request for Bid (RFB) is to install one (1) 10 row x 91’6” elevated, aluminum angle frame bleacher to North Point High School located at 2255 West Meyer, Wentzville, MO 63385.


Documents:

Documents as of 5/6/2022
Login to view documents
Login to view documents
Addition 1

Posted: 5/25/2022

Type of Addition: In Review

Addition 2

Posted: 7/12/2022

Type of Addition: Award Information

Documents:

Question 1

Posted: 5/17/2022

Question: 1) What is the required completion date for the project? 2) Is the concrete pad that is required for the bleacher installation to be included in our pricing?

Response: The completion date is May 2023. The concrete will not be in the bid it is supplied by the district.

Question 2

Posted: 5/19/2022

Question: How long are we to hold our bid pricing for?

Response: The winning bid is expected to purchase and install the bleachers based on their bid amount.

Question 3

Posted: 5/19/2022

Question: Is a 5% bid bond required with this bid?

Response: yes

Posted: 5/25/2022

Type of Addition: In Review

Posted: 7/12/2022

Type of Addition: Award Information

Documents:

Posted: 5/17/2022

Question: 1) What is the required completion date for the project? 2) Is the concrete pad that is required for the bleacher installation to be included in our pricing?

Response: The completion date is May 2023. The concrete will not be in the bid it is supplied by the district.

Posted: 5/19/2022

Question: How long are we to hold our bid pricing for?

Response: The winning bid is expected to purchase and install the bleachers based on their bid amount.

Posted: 5/19/2022

Question: Is a 5% bid bond required with this bid?

Response: yes