Dorchester County Sealed Solicitation

Title: Lower Dorchester Wastewater Treatment Plant Improvements Project

Deadline: 8/17/2018 2:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: In Review

Solicitation Number: 2018-3282-7306-02

Description: Dorchester County is requesting sealed bids from qualified firms for the construction and installation of a new clarifier mechanism, RAS pump, tertiary filter, sludge feed pump, polymer feed system, sludge grinder, decanter centrifuge, fine bubble diffused air system, and positive displacement blowers at the Lower Dorchester Wastewater Treatment Plant.  This project includes construction of related electrical, control and information systems components, and all piping, valves and associated work necessary to render the facilities complete and operational.  All work shall be as described or implied in the Specifications and indicated on Contract Drawings. This project is being funded by a loan from the State Revolving Fund and bidders must comply with all applicable state and federal requirements identified in the bid documents – including Davis-Bacon and “American Iron and Steel” Provisions.


Pre-Bid Meeting Date: 7/18/2018 2:00 PM

Pre-Bid Meeting Details: A mandatory pre-bid meeting will be held Wednesday, July 18, 2018, at 2:00 PM at the Lower Dorchester Wastewater Treatment Plant, located at 2900 Landing Parkway, North Charleston, SC 29420.


Documents:

Documents as of 7/9/2018
Login to view documents
Login to view documents
Addition 1

Posted: 7/26/2018

Type of Addition: Addendum No. 1

Overview: Please see attached addendum.

Documents:

Addition 2

Posted: 8/2/2018

Type of Addition: Addendum No. 2

Overview: Please see attached addendum.

Documents:

Addition 3

Posted: 8/6/2018

Type of Addition: Addendum No. 3

Overview: Please see attached Addendum #3. Bid opening has been rescheduled and will now take place August 17, 2018 at 2:00 PM. Question/comment deadline has been extended to August 10, 2018 at 2:00 PM.

Deadline: 8/17/2018 2:00 PM

Documents:

Addition 4

Posted: 8/8/2018

Type of Addition: Addendum No. 4

Overview: Please see attached Addendum No. 4.

Documents:

Addition 5

Posted: 8/13/2018

Type of Addition: Addendum No. 5

Overview: Please see attached Addendum Number 5.

Documents:

Addition 6

Posted: 8/21/2018

Type of Addition: In Review

Question 1

Posted: 7/10/2018

Question: Is a cost estimate/ budget available for the project?

Response: There is no formal cost estimate or budget available.

Question 2

Posted: 7/10/2018

Question: When do you expect construction to begin?

Response: Within 60 days of the bid award.

Question 3

Posted: 7/10/2018

Question: Is there an engineers estimate or budget for this project?

Response: There is no formal cost estimate or budget available.

Question 4

Posted: 7/11/2018

Question: REF: Section 00100, par 3.1.6 says the contractors need to schedule a site visit. Will the contractors be able to inspect the site after the mandatory pre-bid meeting?

Response: Yes

Posted: 7/26/2018

Type of Addition: Addendum No. 1

Overview: Please see attached addendum.

Documents:

Posted: 8/2/2018

Type of Addition: Addendum No. 2

Overview: Please see attached addendum.

Documents:

Posted: 8/6/2018

Type of Addition: Addendum No. 3

Overview: Please see attached Addendum #3. Bid opening has been rescheduled and will now take place August 17, 2018 at 2:00 PM. Question/comment deadline has been extended to August 10, 2018 at 2:00 PM.

Deadline: 8/17/2018 2:00 PM

Documents:

Posted: 8/8/2018

Type of Addition: Addendum No. 4

Overview: Please see attached Addendum No. 4.

Documents:

Posted: 8/13/2018

Type of Addition: Addendum No. 5

Overview: Please see attached Addendum Number 5.

Documents:

Posted: 8/21/2018

Type of Addition: In Review

Posted: 7/10/2018

Question: Is a cost estimate/ budget available for the project?

Response: There is no formal cost estimate or budget available.

Posted: 7/10/2018

Question: When do you expect construction to begin?

Response: Within 60 days of the bid award.

Posted: 7/10/2018

Question: Is there an engineers estimate or budget for this project?

Response: There is no formal cost estimate or budget available.

Posted: 7/11/2018

Question: REF: Section 00100, par 3.1.6 says the contractors need to schedule a site visit. Will the contractors be able to inspect the site after the mandatory pre-bid meeting?

Response: Yes