Knoxville's Community Development Corporation Sealed Solicitation
Title: Roofing Services for North Ridge Crossing C25018.1
Deadline: 10/11/2024 2:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status: Awarded
Solicitation Number: C25018.1
Description: KCDC will received UPLOADED bids for roofing services for North Ridge Crossing, as detailed in the solicitation document, through this portal. Note that bids are to be uploaded as ONE document.
Pre-Bid Meeting Details: Bidders may visit the buildings on September 24-26 from 8:00 to 4:00. See the solicitation document for details.
Line Item |
Item # | Description | Purchase Quantity |
Unit Of Measurement |
Units Per UOM |
Total Units | Allow Alt Item Purchase Quantity? | Allow Alt. item? |
Allow Alt. UOM? |
Attachments |
---|---|---|---|---|---|---|---|---|---|---|
1 | 1 | Project Total Cost | 1 | Each | 1 | 1 |
|
|||
2 | 2 | Decking Cost (per 4 x 8) | 1 | Each | 1 | 1 |
|
Documents:
Documents as of 9/17/2024 |
---|
Roofing_Services_for_North_Ridge_Crossing_C25018.1.pdf |
Addition 1
Posted: 10/11/2024
Type of Addition: In Review
Overview: KCDC received five responsive bids-see the attached tabulation. The review is underway.
Documents:
Addition 2
Posted: 10/16/2024
Type of Addition: Award Information
Overview: KCDC awarded to the low bidder, Iron Horse Demolition.
Amount: $72,727.97
Question 1
Posted: 10/1/2024
Question: 1. Are we able to be approved to work from 7 am to 7 pm Monday through Friday? 2. Do you want us to replace all Counter Flashing for Roof to Wall Junctions on 3801-3808 Titus Way or only if the existing pieces compromise during installation of the new step flashing? 3. On 3900 Titus/401 Pertinax there is a dead valley section that is heavily tarred currently, do you want us to add Rolled Roofing in that section for longevity or just install standard Ice and Water Shield.
Response: 1. Are we able to be approved to work from 7 am to 7 pm Monday through Friday? No unless you are authorized by the property manager. KCDC's normal business hours are 7:30 am to 4:00 pm Monday through Friday. 2. Do you want us to replace all Counter Flashing for Roof to Wall Junctions on 3801-3808 Titus Way or only if the existing pieces compromise during installation of the new step flashing? Only if the existing pieces compromise during installation of the new step flashing. 3. On 3900 Titus/401 Pertinax there is a dead valley section that is heavily tarred currently, do you want us to add Rolled Roofing in that section for longevity or just install standard Ice and Water Shield. Install standard Ice and Water Shield per manufacturer's specifications.
Posted: 10/11/2024
Type of Addition: In Review
Overview: KCDC received five responsive bids-see the attached tabulation. The review is underway.
Documents:
Posted: 10/16/2024
Type of Addition: Award Information
Overview: KCDC awarded to the low bidder, Iron Horse Demolition.
Amount: $72,727.97
Posted: 10/1/2024
Question: 1. Are we able to be approved to work from 7 am to 7 pm Monday through Friday? 2. Do you want us to replace all Counter Flashing for Roof to Wall Junctions on 3801-3808 Titus Way or only if the existing pieces compromise during installation of the new step flashing? 3. On 3900 Titus/401 Pertinax there is a dead valley section that is heavily tarred currently, do you want us to add Rolled Roofing in that section for longevity or just install standard Ice and Water Shield.
Response: 1. Are we able to be approved to work from 7 am to 7 pm Monday through Friday? No unless you are authorized by the property manager. KCDC's normal business hours are 7:30 am to 4:00 pm Monday through Friday. 2. Do you want us to replace all Counter Flashing for Roof to Wall Junctions on 3801-3808 Titus Way or only if the existing pieces compromise during installation of the new step flashing? Only if the existing pieces compromise during installation of the new step flashing. 3. On 3900 Titus/401 Pertinax there is a dead valley section that is heavily tarred currently, do you want us to add Rolled Roofing in that section for longevity or just install standard Ice and Water Shield. Install standard Ice and Water Shield per manufacturer's specifications.