Dorchester County Sealed Solicitation
Title: Stratton Capers New 6" Water Line
Deadline: 3/23/2018 2:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status: Cancelled
Description: Sealed Bids for the construction of the Stratton Capers New 6” Water Line will be received by the Dorchester County Purchasing Department in the Kenneth F. Waggoner Services Center, 201 Johnston Street, St. George, SC 29477, until 2:00 p.m. on March 23, 2018, at which time the Bids received will be publicly opened and read.
Pre-Bid Meeting Date: 3/9/2018 10:00 AM
Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-solicitation meeting
Documents:
Documents as of 2/22/2018 |
---|
Login to view documents |
Login to view documents |
Addition 3
Posted: 3/16/2018
Type of Addition: Addendum
Overview: Please see the attached Addendum.
Documents:
Addition 4
Posted: 3/21/2018
Type of Addition: Addendum 2
Overview: Addendum 2: Per project engineer, the fire hydrants are to have a Storz connection as indicated in the detail drawing.
Documents:
Addition 5
Posted: 3/23/2018
Type of Addition: In Review
Overview: Bids are currently under review by the project engineer.
Documents:
Addition 6
Posted: 4/13/2018
Type of Addition: Cancellation Information
Overview: Green Construction withdrew bid due to significant omission of calculations. Due to large variance between engineer's cost estimate and bids submitted, a rebid with adjusted specifications will be necessary.
Question 1
Posted: 3/2/2018
Question: Has a cost estimate/ budget been established for the project?
Response: There is no formal cost estimate.
Question 2
Posted: 3/2/2018
Question: When do you expect work to begin?
Response: Within 60 days after bid opening
Question 3
Posted: 3/14/2018
Question: Have you sent out the addendum that was to come out on March 14, 2018 yet?
Response: The addendum was just posted.
Posted: 3/16/2018
Type of Addition: Addendum
Overview: Please see the attached Addendum.
Documents:
Posted: 3/21/2018
Type of Addition: Addendum 2
Overview: Addendum 2: Per project engineer, the fire hydrants are to have a Storz connection as indicated in the detail drawing.
Documents:
Posted: 3/23/2018
Type of Addition: In Review
Overview: Bids are currently under review by the project engineer.
Documents:
Posted: 4/13/2018
Type of Addition: Cancellation Information
Overview: Green Construction withdrew bid due to significant omission of calculations. Due to large variance between engineer's cost estimate and bids submitted, a rebid with adjusted specifications will be necessary.
Posted: 3/2/2018
Question: Has a cost estimate/ budget been established for the project?
Response: There is no formal cost estimate.
Posted: 3/2/2018
Question: When do you expect work to begin?
Response: Within 60 days after bid opening
Posted: 3/14/2018
Question: Have you sent out the addendum that was to come out on March 14, 2018 yet?
Response: The addendum was just posted.