Peralta Community College District Sealed Solicitation

Title: RFP 23 24 07 Geotech Engineer of Record Services, Laney College Library & Learning Resources Center

Deadline: 11/2/2023 2:00 PM   (UTC-08:00) Pacific Time (US & Canada)

Status: Deadline Expired

Solicitation Number: 23 24 07

Description: The project includes the selective site demolition and construction necessary for a new academic library and learning resource center on the Laney College campus. The project is a 75,622 square foot, three (3) story concrete and steel structure, Type IIA construction and consists of Type A-3 and B occupancies. Work includes site utilities and landscaping at 900 Fallon Street, Oakland, CA 94607.


Pre-Bid Meeting Date: 10/12/2023 11:00 AM

Pre-Bid Meeting Details: A non-mandatory Pre-proposal video conference meeting will be held on October 12, 2023 at 11:00A.M. via Zoom: Conference Meeting ID 869 1952 7712 https://peralta-edu.zoom.us/j/86919527712


Documents:

Documents as of 10/12/2023
Notice to Proposers - RFP 23 24 07 LC L+LRC Geotech Engineer Services.pdf
RFP 23 24 07 Laney L+LRC GEOR Services.pdf
Exhibit 2 - SLBE Program & Affidavit.pdf
Exhibit 2.1 - SLBE Participation Template.pdf
Exhibit 3 - Team Experience_LC L+LRC IOR.pdf
Exhibit 4 - Sample Staffing Proposal Worksheet.xlsx
Exhibit 5.1 Laney LRC 01-119215 Drawings.pdf
Exhibit 5.2 Laney LRC 01-119215 Specifications.pdf
Exhibit 5.3 Laney LRC 01-119215 DSA Form 103.pdf
Exhibit 6 - Independent Consultant Agreement.pdf
Exhibit 5.4 Laney LRC Geotech Investigation & Haz Evaluation.pdf
RFP 23 24 07 Pre-Proposal Video Meeting Chat Sign-in.pdf
Addition 1

Posted: 10/13/2023

Type of Addition: Addendum

Overview: Addendum One

Deadline: 11/2/2023 11:00 AM

Documents:

Question 1

Posted: 10/19/2023

Question: Were there DSA comments on the geotechnical investigation report that is available in the document portal? Where is the document that provides response to DSA comments or DSA approval of the geotechnical report?

Response: The response to this question can be found in Addendum Two.

Question 2

Posted: 10/19/2023

Question:

Response: This question was apparently submitted prior to the content being provided. No response needed.

Posted: 10/13/2023

Type of Addition: Addendum

Overview: Addendum One

Deadline: 11/2/2023 11:00 AM

Documents:

Posted: 10/19/2023

Question: Were there DSA comments on the geotechnical investigation report that is available in the document portal? Where is the document that provides response to DSA comments or DSA approval of the geotechnical report?

Response: The response to this question can be found in Addendum Two.

Posted: 10/19/2023

Question:

Response: This question was apparently submitted prior to the content being provided. No response needed.