Jasper County Sealed Solicitation

Title: Church Road Area Drainage Improvement Project (Project No. CDBG #4-CI-20-010-SCIIP#A-23-C104)

Deadline: 10/30/2023 11:00 AM   (UTC-05:00) Eastern Time (US & Canada)

Status: Deadline Expired

Solicitation Number: IVTB #2024-6

Description: Jasper County is seeking sealed bids for the Church Road Area Drainage Improvement Project (Project No. CDBG #4-CI-20-010-SCIIP#A-23-C104) until WEDNESDAY OCTOBER 25, 2023, at 11:00 A.M. Information may be found under “What’s New”, “Bids & Solicitations”, on the County’s website at www.jaspercountysc.gov.


Documents:

Documents as of 8/24/2023
Login to view documents
Login to view documents
Login to view documents
Addition 1

Posted: 9/21/2023

Type of Addition: Addendum #1

Overview: The information contained in this addendum should be considered by prospective bidders in preparation of their proposals and are hereby incorporated into the Proposal Documents. Bidders shall be responsible for acknowledging receipt of this addendum in the Bid Form, Document 00 41 43. Failure to do so will result in the proposal being considered nonresponsive. 

Deadline: 10/25/2023 11:00 AM

Solicitation #: IVTB #2024-6

Documents:

Addition 2

Posted: 9/27/2023

Type of Addition: Addendum #2

Overview: Section 00 11 16 – Invitation to Bid has been revised to extend the bid due date to Monday, October 30, 2023, at 11:00 AM,  and includes the deadline for questions, addenda dates and additional contact information.   All questions shall be submitted to the engineer in writing by October 13th, 2023, at 5:00 PM. An addendum addressing all plan holders by end of business on October 18th, 2023.

Deadline: 10/30/2023 11:00 AM

Solicitation #: IVTB #2024-6

Documents:

Addition 3

Posted: 10/17/2023

Type of Addition: Addendum #3

Overview: PART I – QUESTIONS AND CLARIFICATIONS:   Q. Would you consider increasing the Project Duration?  A. The project duration has been changed. The work is to be substantially completed in 180 days and ready for final payment 240 days after the commencement of contract times.
PART II – CONTRACT DOCUMENTS
The following enclosed Proposal Documents have been changed in the following respects:  Section 00 52 43 Agreement Form was revised to show project duration has been changed. The work is to be substantially completed in 180 days and ready for final payment 240 days after the commencement of contract times.  Section 00 80 00 – Special Conditions project duration has been changed. The work is to
be substantially completed in 180 days and ready for final payment 240 days after the commencement of contract times. 

Deadline: 10/30/2023 11:00 AM

Solicitation #: IVTB #2024-6

Documents:

Posted: 9/21/2023

Type of Addition: Addendum #1

Overview: The information contained in this addendum should be considered by prospective bidders in preparation of their proposals and are hereby incorporated into the Proposal Documents. Bidders shall be responsible for acknowledging receipt of this addendum in the Bid Form, Document 00 41 43. Failure to do so will result in the proposal being considered nonresponsive. 

Deadline: 10/25/2023 11:00 AM

Solicitation #: IVTB #2024-6

Documents:

Posted: 9/27/2023

Type of Addition: Addendum #2

Overview: Section 00 11 16 – Invitation to Bid has been revised to extend the bid due date to Monday, October 30, 2023, at 11:00 AM,  and includes the deadline for questions, addenda dates and additional contact information.   All questions shall be submitted to the engineer in writing by October 13th, 2023, at 5:00 PM. An addendum addressing all plan holders by end of business on October 18th, 2023.

Deadline: 10/30/2023 11:00 AM

Solicitation #: IVTB #2024-6

Documents:

Posted: 10/17/2023

Type of Addition: Addendum #3

Overview: PART I – QUESTIONS AND CLARIFICATIONS:   Q. Would you consider increasing the Project Duration?  A. The project duration has been changed. The work is to be substantially completed in 180 days and ready for final payment 240 days after the commencement of contract times.
PART II – CONTRACT DOCUMENTS
The following enclosed Proposal Documents have been changed in the following respects:  Section 00 52 43 Agreement Form was revised to show project duration has been changed. The work is to be substantially completed in 180 days and ready for final payment 240 days after the commencement of contract times.  Section 00 80 00 – Special Conditions project duration has been changed. The work is to
be substantially completed in 180 days and ready for final payment 240 days after the commencement of contract times. 

Deadline: 10/30/2023 11:00 AM

Solicitation #: IVTB #2024-6

Documents: