City of Framingham Sealed Solicitation
Title: IFB# 7126 BROPHY LOCKER ROOM PROJECT GENERAL BID OPENING
Deadline: 8/19/2021 1:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status: In Review
Solicitation Number: 7126
Description:
The City of Framingham, through the Mayor of Framingham Massachusetts, the Awarding Authority invites sealed bids for BROPHY LOCKER ROOM PROJECT Bid No 7126 Plans and Specifications will be accepted electronically through the City of Framingham’s Vendor Registry portal https://vrapp.vendorregistry.com/Vendor/Register/Index/city-of-framingham-ma-vendor-registration in accordance with Contract Documents prepared by Haynes, Lieneck, and Smith, Inc. Bids must be submitted electronically through the City’s Vendor Registry system. Bids submitted through any other means, such as mail, email or hand delivery, will not be accepted and will be rejected by the City as non-responsive.
Pre-Bid Meeting Date: 8/3/2021 10:00 AM
Pre-Bid Meeting Details: A pre-bid meeting will be held on Tuesday August 3, 2021 at 10:00 AM in the morning; meet in the main entrance lobby at the Brophy Elementary School, 575 Pleasant Street in Framingham.
Documents:
Documents as of 7/28/2021 |
---|
Login to view documents |
PLANHOLDERS:
Date | Company Name |
---|---|
7/29/2021 2:36:12 AM | IMS |
7/29/2021 7:04:38 AM | Paul J. Rogan Co., Inc, |
7/29/2021 8:38:55 AM | Stutman Contracting Inc |
7/29/2021 9:04:23 AM | Wayne J. Griffin Electric, Inc. |
7/29/2021 1:42:20 PM | Prime Vendor |
7/29/2021 3:53:23 PM | iSqFt |
7/29/2021 8:20:05 PM | Elm Electrical |
7/30/2021 3:32:53 AM | North America Procurement Council Inc., PBC |
7/30/2021 9:37:02 AM | Projectdog |
7/30/2021 10:06:47 AM | Maron Construction Co., Inc. |
7/30/2021 10:44:58 AM | J. J. Cardosi, Inc. |
8/1/2021 5:10:38 PM | Encore Contracting Services, Inc. |
8/1/2021 6:36:25 PM | vintage properties inc |
8/5/2021 12:27:02 PM | Northern Contracting Corp |
8/5/2021 4:54:55 PM | Premier Abatement & Labor Services, Inc. |
8/9/2021 10:50:09 AM | Robert W. Irvine & Sons, Inc. |
8/9/2021 7:51:50 PM | dodge data and analytics |
8/9/2021 9:31:17 PM | Galway Electrical Co Inc |
8/10/2021 9:03:06 AM | Pavilion Floors, Inc. |
8/10/2021 9:41:37 AM | Casby Bros., Inc. |
8/11/2021 8:25:16 AM | Hub Electric Inc. |
8/11/2021 8:43:57 AM | V & G Iron Works, Inc |
8/16/2021 8:44:00 AM | Poulin Construction Inc. |
8/16/2021 9:02:30 AM | Brothers Electrical Corp |
8/16/2021 11:36:17 AM | general mechanical contractors |
8/16/2021 1:01:48 PM | Dodge Data |
8/16/2021 4:43:30 PM | North America Procurement Council, Inc. PBC |
8/17/2021 9:37:55 AM | Menemsha Solutions, Inc. |
8/18/2021 9:01:32 AM | APC Development Group, Inc |
8/18/2021 2:18:58 PM | Cornerstone Building Services |
8/18/2021 3:27:03 PM | Cornerstone Building Services |
8/18/2021 3:34:11 PM | Santangelo Flooring |
8/19/2021 1:49:06 PM | Compass Restoration Services |
8/19/2021 2:30:02 PM | Page Building Construction Co., Inc. |
8/19/2021 3:22:34 PM | Tower Construction Corporation |
8/19/2021 9:16:36 PM | vintage properties, inc |
9/28/2021 9:52:01 AM | Bluebook Network Building & Construction |
9/29/2021 3:38:36 PM | ConstructConnect |
10/9/2021 5:18:56 PM | RFx Analyst, Inc. |
Addition 1
Posted: 7/30/2021
Type of Addition: Addendum NO.1
Overview: Responses to questions
Solicitation #: 7126
Documents:
Addition 2
Posted: 8/9/2021
Type of Addition: Addendum No.2
Overview: Modification of the contract Documents
Documents:
Addition 3
Posted: 8/10/2021
Type of Addition: Pre-bid sign in sheet
Documents:
Addition 4
Posted: 8/16/2021
Type of Addition: Addendum no.3
Overview: Responses to questions, filed sub bid results
Documents:
Addition 5
Posted: 8/19/2021
Type of Addition: General bid opening results
Overview:
Documents:
Addition 6
Posted: 8/19/2021
Type of Addition: In Review
Question 1
Posted: 7/29/2021
Question: Is there an estimated value for this project?
Response: This project is estimated at 200K
Posted: 7/30/2021
Type of Addition: Addendum NO.1
Overview: Responses to questions
Solicitation #: 7126
Documents:
Posted: 8/9/2021
Type of Addition: Addendum No.2
Overview: Modification of the contract Documents
Documents:
Posted: 8/16/2021
Type of Addition: Addendum no.3
Overview: Responses to questions, filed sub bid results
Documents:
Posted: 8/19/2021
Type of Addition: General bid opening results
Overview:
Documents:
Posted: 8/19/2021
Type of Addition: In Review
Posted: 7/29/2021
Question: Is there an estimated value for this project?
Response: This project is estimated at 200K