City of Quincy Sealed Solicitation
Title: NOTICE TO CONTRACTORS - BROADWAY EMERGENCY SEWER REPLACEMENT PROJECT
Deadline: 11/8/2023 11:00 AM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Description: Sealed bids for the BROADWAY EMERGENCY SEWER REPLACEMENT Project in the City of Quincy, Adams County, Illinois, described herein will be received at the office of the City Clerk, 730 Maine Street, Quincy, Illinois 62301 until 11:00 AM local time, Wednesday, November 8, 2023 and at that time publicly opened and read aloud in the City Hall Council Chamber.
The project consists of removal of a brick manhole and installation of a precast concrete manhole in its place; removal of approximately fifty-eight (58) lineal feet of collapsed sewer pipe and installation of 8” PVC sewer pipe in its place; furnishing and installing a precast concrete manhole to connect to an existing 8” service lateral; removal of existing pavement and restoration with Portland cement concrete (PCC) patches; removal of PCC sidewalk, curb & gutter; construction of PCC sidewalk, curb & gutter and curb ramp; traffic control; and related improvements.
Plans and specifications are available online at www.quincyil.gov/bids and may be examined at the office of the Department of Utilities & Engineering, City Hall, 730 Maine Street, Quincy, Illinois 62301.
All bids shall be accompanied by either a bid bond on the “Proposal Bid” form contained in the proposal, executed by a corporate surety company satisfactory to the city of Quincy, or a bank cashier’s check, an irrevocable letter of credit or a properly certified check for not less than 5 percent of the amount bid, or for the amount listed in the specifications.
The City Council of Quincy reserves the right to reject any or all bids and to waive technicalities.
No bid may be withdrawn after the time for opening of the bids is past.
The City of Quincy is an Equal Opportunity-Affirmative Action Employer and encourages minority group participation in the bidding and construction process.
Bidders are notified that not less than the prevailing wage rate as determined by the Illinois Department of Labor shall be paid to all workers performing work under this contract.
BY ORDER OF:
Jeffrey Conte
Director of Public Works
Documents:
Documents as of 10/27/2023 |
---|
Login to view documents |
PLANHOLDERS:
Date | Company Name |
---|---|
10/27/2023 4:24:21 PM | Southern Illinois Builders Association |
10/28/2023 1:49:09 AM | AG Ltd |
10/29/2023 10:39:42 PM | North America Procurement Council, Inc. PBC |
10/30/2023 9:47:19 AM | Architechnics, Inc |
10/30/2023 12:57:29 PM | G G CONSTRUCTION SERVICES INC dba Proline Fence |
11/5/2023 6:12:41 AM | Green Plumbing |
11/7/2023 2:39:27 PM | Laverdiere Construction, Inc |
11/15/2023 3:09:26 AM | Dodge Data |
11/15/2023 7:28:31 AM | ConstructConnect |
11/15/2023 11:47:53 AM | County Contractors Inc |
11/15/2023 1:27:51 PM | ePlan |
11/27/2023 5:59:46 PM | MILLION CONSTRUCTION |
11/29/2023 12:13:07 PM | Zanger Excavating LLC |
11/30/2023 3:36:02 PM | D&L EXCAVATING INC. |
12/4/2023 1:20:52 AM | Dodge Data & Analytics |
12/15/2023 12:04:23 AM | Deltek |
1/4/2024 9:45:17 AM | Hood Construction Group Midwest, LLC |
1/31/2024 9:05:12 PM | Emrick Bros. LLC |
2/7/2024 7:31:04 AM | COULTER ASPHALT SERVICES, INC. |
2/10/2024 12:11:09 AM | PWXPress |
4/15/2024 11:17:12 AM | Rees Construction Co |
7/3/2024 9:08:38 AM | Argabright Electric |
12/17/2024 10:24:02 AM | Petty Construction Co |
Addition 1
Posted: 11/8/2023
Type of Addition: In Review
Addition 2
Posted: 11/14/2023
Type of Addition: Bid Tab
Overview:
Documents:
Addition 3
Posted: 11/14/2023
Type of Addition: Award Information
Overview: On Monday, November 13, 2023 the Quincy City Council approved the low bid from Rees Construction in the amount of $140,735.00 for sewer replacement near 24th & Broadway.
Amount: $140,735.00
Posted: 11/8/2023
Type of Addition: In Review
Posted: 11/14/2023
Type of Addition: Award Information
Overview: On Monday, November 13, 2023 the Quincy City Council approved the low bid from Rees Construction in the amount of $140,735.00 for sewer replacement near 24th & Broadway.
Amount: $140,735.00