Myrtle Beach Sealed Solicitation

Title: Parallel Water Transmission Line Phase I

Deadline: 12/12/2023 2:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: 24-B0019

Description: The City of Myrtle Beach will be receiving Invitation for Bid (IFB) 24-B0019, Parallel Water Transmission Line Phase I. This project is being funded in whole or in part by the South Carolina Infrastructure Investment Program (SCIIP), which is administered by the South Carolina Rural Infrastructure Authority (RIA) and funded by federal State and Local Fiscal Recovery Funds (SLFRF) through the American Rescue Plan Act (ARPA). All federal SLFRF requirements and SCIIP requirements will apply to the contract. All contractors and subcontractors are required to be registered in the federal System for Award Management (SAM) and may not be debarred from doing business with the federal government. Respondents on this work will be required to comply with all applicable federal regulations. Electronic IFB forms and requirements may be obtained at the City of Myrtle Beach Procurement Office located at 3231 Mr. Joe White Avenue, Myrtle Beach, SC for $50.00 (non-refundable). 


Pre-Bid Meeting Date: 11/21/2023 10:00 AM

Pre-Bid Meeting Details: Mandatory Pre-Bid Meeting will be held at 10:00a.m. (local time) at the Myrtle Beach Public Works Administration Building located at 3210 Mr. Joe White Avenue, Myrtle Beach, SC. On-time attendance and sign-in are required for bid consideration. No late attendees will be admitted. No remote attendance options are available.


Addition 1

Posted: 11/22/2023

Type of Addition: Addendum 01

Documents:

Addition 2

Posted: 12/5/2023

Type of Addition: Addendum 02

Documents:

Addition 3

Posted: 12/5/2023

Type of Addition: Addendum 03

Documents:

Addition 4

Posted: 12/13/2023

Type of Addition: In Review

Documents:

Addition 5

Posted: 3/5/2024

Type of Addition: Award Information

Overview: Garney Construction

Posted: 11/22/2023

Type of Addition: Addendum 01

Documents:

Posted: 12/5/2023

Type of Addition: Addendum 02

Documents:

Posted: 12/5/2023

Type of Addition: Addendum 03

Documents:

Posted: 12/13/2023

Type of Addition: In Review

Documents:

Posted: 3/5/2024

Type of Addition: Award Information

Overview: Garney Construction