Florence County Open Until Resolved RFP

Title: Design/Build-New Lake City Multipurpose Hall

Deadline: 2/9/2023 10:00 AM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: 19-22/23

Description: Florence County (County) is seeking a qualified firm to provide design/build services for the design and construction of a new Multi-purpose Hall to be located at 318 Charles Street, Lake City, SC (TMP#80015-02-016).   


Documents:

Documents as of 2/1/2023
Login to view documents
Login to view documents

PLANHOLDERS:

Date Company Name
2/1/2023 12:13:23 PM Davis Builders, LLC
2/1/2023 12:22:57 PM SSOE
2/1/2023 12:32:07 PM GMK Associates, Inc.
2/1/2023 12:38:54 PM Ace Construction Co., Inc.
2/1/2023 12:52:14 PM Moseley Architects
2/1/2023 1:10:50 PM M B Kahn Construction Co., Inc.
2/1/2023 1:13:13 PM Madco Contracting & Consulting Services
2/1/2023 2:13:34 PM Boomerang Design
2/1/2023 2:40:25 PM Reeves Young
2/1/2023 4:27:11 PM Contract Construction, Inc.
2/1/2023 4:47:52 PM Ace Construction Co., Inc.
2/1/2023 5:25:04 PM Collins and Almers Architecture
2/2/2023 2:00:42 AM IMS
2/2/2023 2:19:15 AM IMS
2/2/2023 7:08:03 AM ADW Architects
2/2/2023 8:24:28 AM FBi Construction Inc.
2/2/2023 9:05:18 AM Davis & Floyd, Inc.
2/2/2023 9:11:30 AM JF Contractors LLC
2/2/2023 9:55:16 AM envirobidnet
2/2/2023 10:50:18 AM Thompson Turner Construction
2/2/2023 11:59:42 AM Gilbert Construction
2/2/2023 2:53:50 PM Deltek
2/2/2023 5:24:03 PM TShayEnterprise
2/3/2023 5:50:52 AM Alliance Consulting Engineers, Inc.
2/3/2023 10:10:11 AM Ajax Building Company, LLC
2/3/2023 1:29:41 PM Caplea Coe Architects, Inc.
2/3/2023 2:41:50 PM McMillan Pazdan Smith Architecture
2/6/2023 8:56:56 AM Creech & Associates
2/6/2023 1:13:21 PM Mashburn Construction
2/7/2023 8:54:48 AM MRB Group
2/8/2023 10:43:18 PM AG Ltd
2/9/2023 9:54:57 AM JF Contractors
3/2/2023 10:47:36 AM Georgia Stone Products
3/9/2023 8:39:28 AM Dodge Data & Analytics
3/9/2023 6:58:42 PM All Quality Construction Company LLC
3/10/2023 3:39:23 AM Dodge Data
3/13/2023 9:50:41 AM None
3/16/2023 4:49:49 PM ConstructConnect
8/25/2023 11:26:24 AM Davis & Floyd, Inc.
9/22/2023 2:10:01 PM Pee Dee Environmental
Addition 1

Posted: 2/3/2023

Type of Addition: Addendum No. 1

Overview: The following has been added to the general information portion of the RFP.   Include this addition in your proposal.


* Add to the building details the inclusion of an extensive outdoor patio area with amenities such as fireplaces or fire pits, benches, swings, and a small stage for music.  

Addition 2

Posted: 2/9/2023

Type of Addition: In Review

Addition 3

Posted: 2/17/2023

Type of Addition: Award Information

Overview: Thompson Turner Construction of Sumter, SC on February 16, 2023.

Documents:

Question 1

Posted: 2/1/2023

Question: The RFQ mentions that a proposed floor plan is included in the solicitation, but I am unable to find it. Thank you.

Response: A floor plan will not be included in this proposal request. The County is asking that you provide your own floor plan based on the scope of services of the RFP. The type of building the County is looking for is based on the following link: https://southcarolinaparks.com/founders-hall/galleries

Question 2

Posted: 2/3/2023

Question: Based on the Answer to an earlier Question - is the County expecting proposers to submit a proposed floor plan with the submittal due on February 9 or is the floor plan to be developed merely to allow proposers to develop the requested cost proposal?

Response: You should submit a minimum of one proposed floor plan. More than one floor plan will be accepted as well.

Question 3

Posted: 2/3/2023

Question: Re: Evaluation Criteria and Selection Procedure, Criteria E. Cost of Each Project - Please provide separately. For proposers intending to submit electronically through Vendor Registry, will uploading the Cost Proposal as a separate .pdf document meet this requirement?

Response: Yes, you may upload the cost proposal as a separate proposal document on Vendor Registry.

Question 4

Posted: 2/3/2023

Question: Re: Proposal Submittal Requirements. Item 7 requires "A method to demonstrate the firm's ability to work within the County's proposed project budget." Has the County established a project budget for this project that can be shared with potential proposers?

Response: No budget set. Considering any price options that allow construction of a facility that meets the requirement of the RFP.

Question 5

Posted: 2/3/2023

Question: An earlier Answer notes the type of building the County is looking for is based on Founders Hall - this building is a gold-level LEED-Certified green building. Is LEED certification (or other levels of environmental certification) desired for this Multi-purpose Hall?

Response: No, the building is not required to be LEED certified.

Posted: 2/3/2023

Type of Addition: Addendum No. 1

Overview: The following has been added to the general information portion of the RFP.   Include this addition in your proposal.


* Add to the building details the inclusion of an extensive outdoor patio area with amenities such as fireplaces or fire pits, benches, swings, and a small stage for music.  

Posted: 2/9/2023

Type of Addition: In Review

Posted: 2/17/2023

Type of Addition: Award Information

Overview: Thompson Turner Construction of Sumter, SC on February 16, 2023.

Documents:

Posted: 2/1/2023

Question: The RFQ mentions that a proposed floor plan is included in the solicitation, but I am unable to find it. Thank you.

Response: A floor plan will not be included in this proposal request. The County is asking that you provide your own floor plan based on the scope of services of the RFP. The type of building the County is looking for is based on the following link: https://southcarolinaparks.com/founders-hall/galleries

Posted: 2/3/2023

Question: Based on the Answer to an earlier Question - is the County expecting proposers to submit a proposed floor plan with the submittal due on February 9 or is the floor plan to be developed merely to allow proposers to develop the requested cost proposal?

Response: You should submit a minimum of one proposed floor plan. More than one floor plan will be accepted as well.

Posted: 2/3/2023

Question: Re: Evaluation Criteria and Selection Procedure, Criteria E. Cost of Each Project - Please provide separately. For proposers intending to submit electronically through Vendor Registry, will uploading the Cost Proposal as a separate .pdf document meet this requirement?

Response: Yes, you may upload the cost proposal as a separate proposal document on Vendor Registry.

Posted: 2/3/2023

Question: Re: Proposal Submittal Requirements. Item 7 requires "A method to demonstrate the firm's ability to work within the County's proposed project budget." Has the County established a project budget for this project that can be shared with potential proposers?

Response: No budget set. Considering any price options that allow construction of a facility that meets the requirement of the RFP.

Posted: 2/3/2023

Question: An earlier Answer notes the type of building the County is looking for is based on Founders Hall - this building is a gold-level LEED-Certified green building. Is LEED certification (or other levels of environmental certification) desired for this Multi-purpose Hall?

Response: No, the building is not required to be LEED certified.