Florence County Sealed Solicitation

Title: 43-23/24 Concrete Work for South Lynches Fire Station in Lake City

Deadline: 2/27/2024 10:00 AM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: 43-23/24

Description: Florence County, South Carolina (Owner) is accepting bids from licensed and qualified Contractors to perform concrete work for the South Lynches Fire Station located at 345 S. Ron McNair Blvd., Lake City, SC 29560.


Pre-Bid Meeting Date: 2/20/2024 9:00 AM

Pre-Bid Meeting Details: Please sign up if you plan to attend the pre-bid meeting.A mandatory pre-bid meeting will be conducted on February 20, 2024 at 9:00 a.m. The purpose of this meeting is to discuss the scope of work, timeframe of completion of the project and scheduling/coordinating of work to be done.


Documents:

Documents as of 2/14/2024
Login to view documents

PLANHOLDERS:

Date Company Name
2/14/2024 11:57:37 AM Industrial Contractors inc.
2/14/2024 12:13:43 PM Sun Construction
2/14/2024 1:44:58 PM Thompson Turner Construction
2/14/2024 2:57:50 PM W E Martin Contracting LLC
2/14/2024 8:05:46 PM Osborne concrete inc
2/16/2024 10:03:35 AM PWXPress
2/16/2024 10:45:00 AM Meric Builders
2/20/2024 12:56:46 PM Davis & Floyd, Inc.
2/20/2024 2:59:19 PM Deltek
2/20/2024 8:52:10 PM J&M Sitework
2/21/2024 11:53:52 AM MNB Construction Inc.
2/21/2024 3:50:12 PM Ben Cox Company, LLC
2/21/2024 6:39:19 PM C. R. Jackson, Inc
2/22/2024 2:48:22 AM Pee Dee Earthworks
2/22/2024 3:26:10 PM Willie Keitt and sons LLC
2/23/2024 5:55:25 AM Dodge Data & Analytics
2/23/2024 8:23:11 AM Gilbert Construction
2/23/2024 9:41:32 AM Palmetto Corp of Conway
2/23/2024 5:01:23 PM Davis Builders, LLC
2/26/2024 11:39:23 AM Gaster's Grading Co., Inc
2/26/2024 11:44:25 AM First Construction Management
2/26/2024 1:03:35 PM dodge data and analytics
2/26/2024 1:20:14 PM North America Procurement Council Inc., PBC
2/26/2024 2:59:59 PM S&ME, Inc.
2/27/2024 7:25:24 AM Chipley Company, Inc
2/27/2024 8:14:55 AM Palmetto Corp of Conway
3/21/2024 2:21:01 PM ConstructConnect
3/22/2024 11:12:01 AM Freedom Contractors of SC
4/4/2024 11:44:21 AM Dodge Data & Analytics
4/5/2024 1:36:52 PM Carolina Gold Construction
4/18/2024 10:33:23 AM None
Addition 1

Posted: 2/20/2024

Type of Addition: Pre-Bid Attendance Sheet

Documents:

Addition 2

Posted: 2/22/2024

Type of Addition: Addendum

Overview: Addendum to address questions that came in.

Documents:

Addition 3

Posted: 2/26/2024

Type of Addition: Addendum

Overview: Second Addendum to address the changing of calendar completion days from 30 (thirty) to 90 (ninety) days.

Documents:

Addition 4

Posted: 2/27/2024

Type of Addition: In Review

Addition 5

Posted: 3/22/2024

Type of Addition: Award Information

Overview: Awarded to Palmetto Corp. of Florence, SC.

Amount: $295,665.75

Question 1

Posted: 2/20/2024

Question: On page 13, Item 4 says the time limit for the project is 5 calendar days. Should this be 30 calendar days?

Response: That is correct; the completion time allowed for this project is 30 calendar days and not 5. This was an over sight and is an error. (see page 20 for extra clarity).

Question 2

Posted: 2/20/2024

Question: For the trench drain specified, is it supposed to be Zurn Z886-FGF

Response: The Dept. is allowing for whatever the vendor deems suitable to accommodate the weight the fire trucks.

Question 3

Posted: 2/20/2024

Question: Is the slab rebar just to support the drainage trench or is it for the whole slab?

Response: The rebar should support the whole slab.

Question 4

Posted: 2/21/2024

Question: Will the county obtain the encroachment permit to work on SCDOT Rights-of-way?

Response: The Dept. is asking that the contractor obtain the permit.

Posted: 2/20/2024

Type of Addition: Pre-Bid Attendance Sheet

Documents:

Posted: 2/22/2024

Type of Addition: Addendum

Overview: Addendum to address questions that came in.

Documents:

Posted: 2/26/2024

Type of Addition: Addendum

Overview: Second Addendum to address the changing of calendar completion days from 30 (thirty) to 90 (ninety) days.

Documents:

Posted: 2/27/2024

Type of Addition: In Review

Posted: 3/22/2024

Type of Addition: Award Information

Overview: Awarded to Palmetto Corp. of Florence, SC.

Amount: $295,665.75

Posted: 2/20/2024

Question: On page 13, Item 4 says the time limit for the project is 5 calendar days. Should this be 30 calendar days?

Response: That is correct; the completion time allowed for this project is 30 calendar days and not 5. This was an over sight and is an error. (see page 20 for extra clarity).

Posted: 2/20/2024

Question: For the trench drain specified, is it supposed to be Zurn Z886-FGF

Response: The Dept. is allowing for whatever the vendor deems suitable to accommodate the weight the fire trucks.

Posted: 2/20/2024

Question: Is the slab rebar just to support the drainage trench or is it for the whole slab?

Response: The rebar should support the whole slab.

Posted: 2/21/2024

Question: Will the county obtain the encroachment permit to work on SCDOT Rights-of-way?

Response: The Dept. is asking that the contractor obtain the permit.