Wentzville R-IV School District Sealed Solicitation

Title: “Elementary & Middle School Kitchen Equipment” Bid Number RFB-CN-261

Deadline: 4/22/2022 1:00 PM   (UTC-06:00) Central Time (US & Canada)

Status: Awarded

Solicitation Number: RFB-CN-261

Description: SPEC-1 General Scope
1. The purpose of this Request for Bid (RFB) is to establish purchasing for twenty-four (24) pieces of
kitchen equipment.


Documents:

Documents as of 4/5/2022
Login to view documents
Login to view documents
Addition 1

Posted: 4/25/2022

Type of Addition: In Review

Addition 2

Posted: 6/22/2022

Type of Addition: Award Information

Documents:

Question 1

Posted: 4/6/2022

Question: Good Morning, Do you need an ice bin for your ice maker?

Response: Yes

Question 2

Posted: 4/12/2022

Question: Is there a specific Model # Ice Bin you are looking for? Would Model# D320 be sufficient ?

Response: Yes, that would be sufficient

Question 3

Posted: 4/13/2022

Question: Are all of the items to shipped and set in place after uncrating, or only shipped to the address listed?

Response: Shipped only to the address listed.

Question 4

Posted: 4/13/2022

Question: Good Afternoon, When does the District need these delivered by? Respectfully, Matt

Response: By August 1st

Question 5

Posted: 4/13/2022

Question: Is there an estimated Award Date ?

Response: May 19th

Question 6

Posted: 4/14/2022

Question: Good Afternoon, After speaking with the manufacturer. Most of these units are build to order and may take 20 weeks to build. If these are needed by August 1st. We would ideally need need to know by the 1st week of May. Would there be any leeway on the delivery date? Respectfully, Matt

Response: All purchases must go to our BOE for approval - the earliest I could order would be May 20th.

Posted: 4/25/2022

Type of Addition: In Review

Posted: 6/22/2022

Type of Addition: Award Information

Documents:

Posted: 4/6/2022

Question: Good Morning, Do you need an ice bin for your ice maker?

Response: Yes

Posted: 4/12/2022

Question: Is there a specific Model # Ice Bin you are looking for? Would Model# D320 be sufficient ?

Response: Yes, that would be sufficient

Posted: 4/13/2022

Question: Are all of the items to shipped and set in place after uncrating, or only shipped to the address listed?

Response: Shipped only to the address listed.

Posted: 4/13/2022

Question: Good Afternoon, When does the District need these delivered by? Respectfully, Matt

Response: By August 1st

Posted: 4/13/2022

Question: Is there an estimated Award Date ?

Response: May 19th

Posted: 4/14/2022

Question: Good Afternoon, After speaking with the manufacturer. Most of these units are build to order and may take 20 weeks to build. If these are needed by August 1st. We would ideally need need to know by the 1st week of May. Would there be any leeway on the delivery date? Respectfully, Matt

Response: All purchases must go to our BOE for approval - the earliest I could order would be May 20th.