Wentzville R-IV School District Sealed Solicitation
Title: “Elementary & Middle School Kitchen Equipment” Bid Number RFB-CN-261
Deadline: 4/22/2022 1:00 PM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Solicitation Number: RFB-CN-261
Description: SPEC-1 General Scope
1. The purpose of this Request for Bid (RFB) is to establish purchasing for twenty-four (24) pieces of
kitchen equipment.
Documents:
Documents as of 4/5/2022 |
---|
Login to view documents |
Login to view documents |
Addition 1
Posted: 4/25/2022
Type of Addition: In Review
Question 1
Posted: 4/6/2022
Question: Good Morning, Do you need an ice bin for your ice maker?
Response: Yes
Question 2
Posted: 4/12/2022
Question: Is there a specific Model # Ice Bin you are looking for? Would Model# D320 be sufficient ?
Response: Yes, that would be sufficient
Question 3
Posted: 4/13/2022
Question: Are all of the items to shipped and set in place after uncrating, or only shipped to the address listed?
Response: Shipped only to the address listed.
Question 4
Posted: 4/13/2022
Question: Good Afternoon, When does the District need these delivered by? Respectfully, Matt
Response: By August 1st
Question 5
Posted: 4/13/2022
Question: Is there an estimated Award Date ?
Response: May 19th
Question 6
Posted: 4/14/2022
Question: Good Afternoon, After speaking with the manufacturer. Most of these units are build to order and may take 20 weeks to build. If these are needed by August 1st. We would ideally need need to know by the 1st week of May. Would there be any leeway on the delivery date? Respectfully, Matt
Response: All purchases must go to our BOE for approval - the earliest I could order would be May 20th.
Posted: 4/25/2022
Type of Addition: In Review
Posted: 4/6/2022
Question: Good Morning, Do you need an ice bin for your ice maker?
Response: Yes
Posted: 4/12/2022
Question: Is there a specific Model # Ice Bin you are looking for? Would Model# D320 be sufficient ?
Response: Yes, that would be sufficient
Posted: 4/13/2022
Question: Are all of the items to shipped and set in place after uncrating, or only shipped to the address listed?
Response: Shipped only to the address listed.
Posted: 4/13/2022
Question: Good Afternoon, When does the District need these delivered by? Respectfully, Matt
Response: By August 1st
Posted: 4/13/2022
Question: Is there an estimated Award Date ?
Response: May 19th
Posted: 4/14/2022
Question: Good Afternoon, After speaking with the manufacturer. Most of these units are build to order and may take 20 weeks to build. If these are needed by August 1st. We would ideally need need to know by the 1st week of May. Would there be any leeway on the delivery date? Respectfully, Matt
Response: All purchases must go to our BOE for approval - the earliest I could order would be May 20th.