Central Florida Expressway Authority Sealed Solicitation
Title: SR 417 WIDENING FROM BOGGY CREEK ROAD TO NARCOOSSEE ROAD; PROJECT 417-151
Deadline: 7/21/2021 1:30 PM (UTC-05:00) Eastern Time (US & Canada)
Status: Awarded
Solicitation Number: ITB-001802
Description:
The work consists
of providing all labor, materials, equipment and incidentals necessary to
widened SR 417 from Boggy Creek Road to Narcoossee Road (SR 15) from four (4)
general use lanes to six (6) general use lanes. Specifically, the project
consists of widening to the inside (median) to accommodate an additional
general use travel lane in each direction with full depth shoulders for a
portion of the remainder of median areas to facilitate hard shoulder running in
the future. All mainline bridges within the project limits, SR 15, will also be
widened to accommodate the appropriate shoulder widths, additional general use
lane or ramp modifications as per the concept. The work also includes, but is
not limited to, construction of sound barriers, overhead sign structures and
intelligent transportation systems infrastructure.
Pre-Bid Meeting Date: 6/15/2021 10:00 AM
Pre-Bid Meeting Details: The purpose of the meeting will be to discuss requirements of the project in an open forum. Although not mandatory, attendance at the pre-bid meeting is highly recommended.
Documents:
PLANHOLDERS:
Date | Company Name |
---|---|
6/1/2021 10:23:36 AM | Central Florida Transport, LLC |
6/1/2021 10:33:42 AM | ZEP CONSTRUCTION INC |
6/1/2021 11:09:55 AM | Structural Group, Inc. |
6/1/2021 11:44:39 AM | Construction Bid Source |
6/1/2021 12:20:07 PM | Scalar Consulting Group, Inc. |
6/1/2021 4:00:10 PM | ASSOCIATED COST ENGINEERS, INC. OF DELAWARE |
6/2/2021 1:01:34 PM | CDM Smith |
6/3/2021 5:48:39 AM | Gregori Construction Inc. |
6/4/2021 11:48:46 AM | Steel Dynamics Inc |
6/8/2021 8:13:19 AM | Concrete Cutting & Breaking Co. |
6/8/2021 4:09:47 PM | MC Squared, Inc. |
6/9/2021 12:29:18 AM | Top Star Construction, LLC |
6/9/2021 7:50:50 AM | GLF Construction |
6/9/2021 2:41:58 PM | Vecellio & Grogan, Inc |
6/9/2021 2:56:43 PM | T2ues, inc |
6/9/2021 4:50:36 PM | MIMS Construction Company |
6/10/2021 7:29:19 AM | Burgess & Niple, Inc. |
6/10/2021 8:57:36 AM | Statewide Materials |
6/10/2021 4:20:39 PM | MIMS Construction |
6/10/2021 4:31:08 PM | cdr environmental |
6/11/2021 9:13:57 AM | GLF Construction Corporation |
6/11/2021 10:31:37 AM | Kisinger Campo and Associates, Inc. |
6/14/2021 10:17:30 AM | SICE INC |
6/14/2021 12:21:57 PM | TAG-DOT INC |
6/14/2021 2:04:07 PM | RK&K (Rummel, Klepper & Kahl, LLP) |
6/15/2021 11:15:56 AM | Horizon Engineering Group |
6/15/2021 11:41:57 AM | DS Brown Co |
6/15/2021 11:55:35 AM | BCC Engineering |
6/15/2021 1:14:27 PM | Moffatt & Nichol, Inc. |
6/15/2021 1:44:29 PM | Roadway Construction Products |
6/15/2021 2:29:36 PM | RS&H Inc |
6/16/2021 1:37:01 PM | Earth Wall Products |
6/17/2021 8:36:24 AM | Skanska USA Civil Southeast |
6/17/2021 12:28:46 PM | Tiffany & Associates |
6/18/2021 9:46:48 AM | VALENCIA CONSTRUCTION GROUP, INC. |
6/18/2021 3:33:20 PM | CONTI LLC |
6/22/2021 7:00:22 PM | Control Technologies |
6/23/2021 12:48:57 PM | SICE, Inc. |
6/25/2021 2:16:56 PM | Archer Western Construction, LLC |
6/25/2021 2:18:32 PM | KBC CONSTRUCTION LLC |
6/25/2021 2:31:35 PM | The Lane Construction Corporation |
6/25/2021 3:52:19 PM | SEMA Construction, Inc. |
6/25/2021 4:09:03 PM | DRMP, Inc |
6/27/2021 7:39:06 AM | THE ARNOLD GROUP OF FLORIDA, INC. |
6/28/2021 11:23:10 AM | Trail's Clearing Service, LLC |
6/30/2021 12:30:13 PM | Transportation Systems Inc. |
7/1/2021 7:05:26 AM | J McKinnon Development |
7/2/2021 11:00:50 AM | A2 Group, Inc. |
7/6/2021 9:28:03 AM | Tensor Engineering |
7/6/2021 10:35:10 AM | Nadic Engineering Services, Inc. |
7/6/2021 11:13:07 AM | Traffic Engineering and Management |
7/7/2021 8:38:57 AM | temple inc |
7/7/2021 11:35:48 AM | PAW Materials, Inc |
7/7/2021 1:34:40 PM | Wayne Atkinson Inc |
7/7/2021 4:11:38 PM | Ion Electric, LLC |
7/7/2021 4:36:48 PM | CFX |
7/8/2021 9:14:32 AM | Watson Bowman Acme Corp |
7/8/2021 2:00:27 PM | Dane Construction and Company, Inc. |
7/9/2021 10:23:12 AM | Arrive Alive Traffic Control LLC |
7/9/2021 2:53:32 PM | Universal Signs & Accessories |
7/9/2021 3:36:57 PM | Maschmeyer |
7/12/2021 7:33:52 AM | TCB Trucking |
7/13/2021 11:31:04 AM | McShea contracting |
7/13/2021 1:28:57 PM | LB Foster CO |
7/14/2021 10:02:25 AM | Earth Tech, LLC |
7/14/2021 4:43:27 PM | Traffic Control Devices, LLC |
7/14/2021 5:09:33 PM | Parsons |
7/14/2021 10:53:53 PM | AG Ltd |
7/15/2021 3:17:30 AM | Link Systems, LLC |
7/15/2021 6:43:44 AM | SEMA Construction, Inc. |
7/15/2021 9:13:19 AM | Ranger Construction |
7/15/2021 9:59:57 AM | Dewberry Engineers Inc. |
7/15/2021 11:52:40 AM | CON-SERV, INC |
7/15/2021 1:38:00 PM | Traffic Control Products of Fl, Inc |
7/15/2021 2:24:56 PM | JOMAR Constructors LLC |
7/15/2021 2:37:39 PM | Surface preparation technologies llc |
7/15/2021 2:47:19 PM | Condotte America, Inc. |
7/15/2021 4:10:26 PM | Bent Metal Works Inc. |
7/15/2021 6:14:54 PM | Straight Edge COncrete LLC |
7/16/2021 11:36:31 AM | Bluebook Network Building & Construction |
7/19/2021 9:42:43 AM | SEMA Construction |
7/20/2021 4:29:03 PM | EAGLE GRINDING AND GROOVING LLC |
7/20/2021 6:27:00 PM | The Reinforced Earth Company |
7/21/2021 9:35:41 AM | The Lane Construction Corporation |
7/21/2021 9:52:41 AM | H&M Electrical & Underground Utilities, Inc. |
7/21/2021 10:34:14 AM | On Point Surveying, Inc. |
7/21/2021 11:35:33 AM | Gemstone, LLC |
7/21/2021 12:55:21 PM | Skanska USA Civil SE |
7/21/2021 12:57:22 PM | Carter's |
7/21/2021 1:24:48 PM | Veritas Steel LLC |
7/21/2021 1:25:25 PM | Watson Civil Construction, Inc. |
7/21/2021 3:03:38 PM | CEMEX |
7/21/2021 3:09:49 PM | COLECON |
7/21/2021 4:27:54 PM | R. J. Watson, Inc. |
7/22/2021 9:48:16 AM | Leware Construction Company |
7/22/2021 9:48:39 AM | Elipsis Engineering & Consulting LLC |
7/22/2021 9:49:05 AM | Southland Construction, Inc. |
7/22/2021 9:49:57 AM | Ram Tool And Supply |
7/22/2021 9:52:23 AM | Intertek/PSI (Professional Service Industries,Inc.) |
7/22/2021 9:53:15 AM | Synergy Earth Systems, LLC |
7/22/2021 9:54:49 AM | Jr. Davis Construction Co., Inc. |
7/22/2021 9:58:19 AM | The Arnold Group of Florida, Inc. |
7/22/2021 9:58:25 AM | Surface Preparation Technologies, LLC |
7/22/2021 10:07:46 AM | Mill-It Corporation |
7/22/2021 10:10:01 AM | geotechnical foundations |
7/22/2021 10:12:35 AM | Junior Davis Construction Company, Inc. |
7/22/2021 10:13:11 AM | EMSI |
7/22/2021 10:15:11 AM | Precision Contracting Services, Inc. |
7/22/2021 10:27:11 AM | Gosalia Concrete Constructors, Inc. |
7/22/2021 10:35:19 AM | Brevard Concrete Paving |
7/22/2021 10:57:16 AM | A2 Group, Inc. |
7/22/2021 11:01:28 AM | NicNevol Engineering Services, Inc. |
7/22/2021 12:01:43 PM | Preferred Materials Inc |
7/22/2021 12:14:24 PM | ASAP Installations |
7/22/2021 12:52:13 PM | Chubb Surety |
7/22/2021 1:11:09 PM | CTI-Construction Testing & Inspection |
7/22/2021 1:11:28 PM | ASAP Specialty Foundations, LLC |
7/22/2021 1:38:46 PM | Tricon Precas LTD |
7/22/2021 2:44:11 PM | UFG |
7/22/2021 5:36:44 PM | Florida Structural Steel |
7/22/2021 6:06:33 PM | GLF Construction Corporation |
7/23/2021 9:33:48 AM | Vecellio & Grogan, Inc. |
7/23/2021 10:11:12 AM | Construction Journal |
7/23/2021 10:32:34 AM | RAINBOW DISTRIBUTORS USA |
7/23/2021 12:29:48 PM | D-MAC Industries Inc. |
7/23/2021 3:51:46 PM | Rocal, Inc |
7/23/2021 6:02:08 PM | RS&H |
7/24/2021 10:04:58 AM | Spring Precast LLC |
7/25/2021 10:06:31 AM | Daktronics, Inc. |
7/26/2021 9:06:36 AM | Shelby Erectors |
7/26/2021 3:30:02 PM | Webber, LLC |
7/26/2021 5:55:20 PM | Standard Concrete Products, Inc. |
7/28/2021 11:59:30 AM | ADS |
7/28/2021 1:43:47 PM | Bob's Barricades |
7/28/2021 1:56:14 PM | McShea Contracting |
7/29/2021 11:22:07 PM | Ferguson Water Works |
7/30/2021 8:51:14 AM | Middlesex Paving, LLC. |
7/30/2021 10:53:31 AM | County Materials |
8/3/2021 10:18:33 AM | Pearls Construction, LLC |
8/6/2021 3:48:35 PM | John B. Webb & Associates |
8/9/2021 8:16:07 AM | Atlantic Pipe Services, LLC |
8/9/2021 11:58:19 AM | PSI |
8/12/2021 7:22:04 AM | Eco Partnering Innovations, LLC |
8/12/2021 12:05:49 PM | Concrete Impressions of Florida, Inc. |
8/12/2021 12:06:31 PM | Moffatt & Nichol, In |
8/12/2021 12:08:31 PM | Dane Construction and Company, Inc. |
8/12/2021 12:09:33 PM | Dixie Lime And Stone Company |
8/12/2021 12:12:43 PM | Brevard Concrete Paving, Inc. |
8/12/2021 12:24:39 PM | Genesis Project Controls Group, LLC |
8/12/2021 12:27:19 PM | The Middlesex Corporation |
8/12/2021 1:03:19 PM | ConstructConnect |
8/12/2021 1:09:34 PM | Hubbard Construction Company |
8/12/2021 1:13:13 PM | Comelco, Inc. |
8/12/2021 1:26:56 PM | Lane Construction |
8/12/2021 2:32:08 PM | Nadic Engineering Services |
8/12/2021 2:59:05 PM | C. Slagter Construction, Inc. |
8/12/2021 3:00:57 PM | Turtle Infrastructure Partners, LLC |
8/12/2021 3:13:08 PM | TEG Engineering |
8/12/2021 3:41:58 PM | Lane Construction |
8/12/2021 4:59:09 PM | Shelby Erectors, Inc. |
8/12/2021 5:39:12 PM | OHL USA |
8/12/2021 6:11:13 PM | Dodge Data |
8/13/2021 1:27:04 PM | Bob's Barricades, Inc. |
8/16/2021 4:01:01 PM | Penhall Company |
8/17/2021 10:35:55 AM | Conti |
8/20/2021 4:00:23 PM | Granite Construction |
8/25/2021 9:48:11 AM | Prince Contracting, LLC |
8/26/2021 4:17:31 PM | OHL USA, Inc |
8/29/2021 5:24:55 PM | Montalvo Mejia Construction |
8/30/2021 2:47:28 PM | Sacyr |
9/3/2021 11:29:59 AM | United Signs and Signals |
9/14/2021 4:46:45 PM | Highway Safety Devices, Inc. |
9/16/2021 9:15:23 AM | Atlas Engineering Group Inc |
9/18/2021 1:10:40 PM | Storm Companies, Inc. |
9/20/2021 11:13:23 AM | Absolute Line Technologies, Inc. |
9/20/2021 11:57:31 AM | Ledstar, Inc. |
9/20/2021 5:18:29 PM | Smith Site Development South LLC |
9/21/2021 1:13:37 PM | Chinchor Electric, Inc. |
9/21/2021 2:23:14 PM | Southland Construction Inc. |
9/21/2021 3:57:13 PM | JME-Son, LLC |
9/23/2021 7:19:06 AM | Timmons Contracting Inc |
9/23/2021 1:41:06 PM | Maylor Foundation Contractors |
9/24/2021 3:46:44 PM | Seminole Precast LLC |
9/27/2021 7:00:55 AM | Redland Company |
9/29/2021 2:05:27 PM | Southern Striping Solutions, LLC. |
9/30/2021 11:55:23 AM | County Materials |
10/1/2021 12:30:35 PM | Tierra, Inc. |
10/6/2021 1:38:50 PM | T.Y. Lin International |
10/9/2021 4:58:04 PM | RFx Analyst, Inc. |
10/13/2021 1:25:58 PM | JC Machine Works Corp |
10/18/2021 3:35:55 PM | Cloverleaf Corporation |
10/20/2021 9:05:43 AM | Superior Construction Company Southeast, LLC |
10/28/2021 2:55:56 PM | Integrated Synergy Inc. |
11/2/2021 2:08:21 PM | Florida Industrial Electric |
11/3/2021 8:39:53 PM | JCA Surety Group |
11/18/2021 12:29:32 PM | Kimley-Horn and Associates, Inc. |
11/18/2021 3:32:50 PM | MRM Construction LLC |
11/29/2021 9:53:56 AM | ASAP Installations |
12/2/2021 12:12:21 PM | AngleRight Surveying, LLC |
12/7/2021 10:32:36 AM | Rampart Hydro Services, LP |
12/10/2021 9:05:09 AM | AECOM |
12/10/2021 2:25:33 PM | Kiewit Infrastructure South Co. |
12/27/2021 3:01:12 PM | AJ General Construct.com |
12/29/2021 11:21:06 AM | TranSystems |
1/27/2022 6:48:42 AM | Southern Development & Construction |
1/28/2022 9:50:22 AM | SiteScope Inc. |
1/28/2022 3:21:42 PM | Blount-Sanford Contracting Company, Inc. |
2/4/2022 3:30:47 PM | Garcia Civil Contractors, LLC |
2/7/2022 3:22:30 PM | Finishing Systems of Florida |
2/8/2022 1:11:11 AM | Porter Pipe Installation |
2/15/2022 8:19:49 AM | JB Supply LLC |
3/7/2022 9:26:42 AM | Lane Construction Corp. |
3/30/2022 9:15:07 PM | DRMP |
4/11/2022 12:24:48 PM | A2 Group, Inc. |
4/11/2022 4:41:32 PM | Olympus Painting Contractors Inc |
4/14/2022 11:38:42 AM | BKW CONSTRUCTION LLC |
4/19/2022 8:37:51 AM | Universal Engineering Sciences |
5/9/2022 11:00:06 AM | Ranger Construction Industries, Inc. |
5/17/2022 8:27:33 AM | Echezabal & Associates, Inc. |
5/17/2022 8:38:00 AM | DRMP Inc. |
5/17/2022 11:10:19 AM | exp U.S. services inc |
5/18/2022 1:33:12 PM | Hubbard Construction Company |
5/19/2022 10:09:28 AM | Danton Hydroblasting |
6/13/2022 3:39:14 PM | KCG Transportation Services |
7/12/2022 10:22:27 AM | Deltek |
7/18/2022 8:33:46 AM | Scalar Consulting Group Inc. |
8/4/2022 4:17:36 PM | RK&K |
10/5/2022 10:29:33 PM | Triple Crown Construction, LLC |
12/26/2022 5:15:55 PM | DRMP |
1/12/2023 9:50:02 AM | J. Mori Painting, Inc. |
2/3/2023 8:49:27 AM | Protean Design Group, Inc. |
3/30/2023 1:23:01 AM | Qualis Concrete LLC |
5/25/2023 10:07:22 AM | A2 Group, Inc. |
6/14/2023 8:31:41 AM | Gibbs & Register, Inc. |
7/18/2023 9:04:22 AM | HDR |
10/17/2023 10:09:23 AM | VHB |
11/28/2023 10:21:59 AM | Preferred Materials, Inc. |
2/6/2024 12:57:21 PM | UES |
2/12/2024 2:42:37 AM | PWXPress |
2/16/2024 12:42:03 PM | CDM Smith |
2/29/2024 10:43:02 AM | AECOM |
4/1/2024 2:06:51 PM | BASE Consultants |
5/30/2024 3:06:37 PM | SACYR |
6/26/2024 2:31:11 PM | Southeast Highway |
10/15/2024 7:21:22 AM | Ardurra Group, Inc. |
12/5/2024 8:44:55 AM | Oglesby Construction Inc. |
Addition 1
Posted: 6/1/2021
Type of Addition: Public Notice
Overview: 001802 Bid Opening Notice 7/14/2021
Documents:
Addition 2
Posted: 6/15/2021
Type of Addition: 001802 - Public Notice
Overview: Pre-Bid Meeting Sign-in Sheet 001802
Documents:
Addition 3
Posted: 6/25/2021
Type of Addition: Addendum No. 1
Overview:
This Addendum forms a part of the Contract
Documents and modifies the original bidding documents dated May 2021, as noted
below. Acknowledge receipt of this Addendum in the space provided on the
Proposal form. Failure to do so may subject the bidder to disqualification. This
Addendum consists of 6 pages and the following attachments: FDEP 404 Wetlands Permit public notice (State
404 Program Public Notice); Revised Plan Sheets; and New Plan Sheets. Reference
Documents (9-14-06 As Built Set.pdf; LNB & 417 Interchange Irrigation
Plans.pdf; KMZ file via link; and 417-150_Approved ERP.pdf) are included as separate documents.
Deadline: 7/21/2021 1:30 PM
Solicitation #: 001802
Documents:
Addition 4
Posted: 6/25/2021
Type of Addition: REVISED-Public Notice
Overview: 001802 REVISED-Bid Opening Notice 7/21/2021
Documents:
Addition 5
Posted: 7/2/2021
Type of Addition: Addendum No. 2
Overview:
This Addendum forms a part of the Contract
Documents and modifies the original bidding documents dated May 2021, as noted
below. Acknowledge receipt of this Addendum in the space provided on the
Proposal form. Failure to do so may subject the bidder to disqualification. This
Addendum consists of 3 pages and the following attachment: Revised Plansheets.
Solicitation #: 001802
Documents:
Addition 6
Posted: 7/14/2021
Type of Addition: Addendum No. 3
Overview:
This Addendum forms a part of the Contract
Documents and modifies the original bidding documents dated May 2021, as noted
below. Acknowledge receipt of this Addendum in the space provided on the
Proposal form. Failure to do so may subject the bidder to disqualification. This
Addendum consists of 6 pages and the following attachments: Revised Bid Form; Revised Plan Sheets; New and
Revised Special Provisions; Fuel Adjustment Sheet; and the following reference
document is included separately: Roadway Soil Survey (417-151_GEOTECH_Roadway
Soil Survey addendum 3).
Solicitation #: 001802
Documents:
Addition 7
Posted: 7/22/2021
Type of Addition: In Review
Overview: The Bid Opening for SR 417 WIDENING FROM BOGGY CREEK ROAD TO NARCOOSSEE ROAD; Project No. 417-151; ITB-001802 was held at a duly noticed meeting on Wednesday, July 21, 2021, commencing at 1:30 p.m. at the Central Florida Expressway Authority Administrative Building, Orlando, Florida. The bids for the following companies were opened and announced verbally along with the bid total amount.
Documents:
Addition 8
Posted: 8/12/2021
Type of Addition: Bid Tabulation 001802
Overview:
Documents:
Addition 9
Posted: 8/12/2021
Type of Addition: Award Information
Overview: On August 12, 2021 the CFX Board members awarded the Contract to the following firm, contingent upon final execution of the contract by both parties: Ranger Construction Industries, Inc., 1200 Elboc Way, Winter Garden, Florida 34787
Amount: $61,810,653.72
Documents:
Posted: 6/1/2021
Type of Addition: Public Notice
Overview: 001802 Bid Opening Notice 7/14/2021
Documents:
Posted: 6/15/2021
Type of Addition: 001802 - Public Notice
Overview: Pre-Bid Meeting Sign-in Sheet 001802
Documents:
Posted: 6/25/2021
Type of Addition: Addendum No. 1
Overview:
This Addendum forms a part of the Contract
Documents and modifies the original bidding documents dated May 2021, as noted
below. Acknowledge receipt of this Addendum in the space provided on the
Proposal form. Failure to do so may subject the bidder to disqualification. This
Addendum consists of 6 pages and the following attachments: FDEP 404 Wetlands Permit public notice (State
404 Program Public Notice); Revised Plan Sheets; and New Plan Sheets. Reference
Documents (9-14-06 As Built Set.pdf; LNB & 417 Interchange Irrigation
Plans.pdf; KMZ file via link; and 417-150_Approved ERP.pdf) are included as separate documents.
Deadline: 7/21/2021 1:30 PM
Solicitation #: 001802
Documents:
Posted: 6/25/2021
Type of Addition: REVISED-Public Notice
Overview: 001802 REVISED-Bid Opening Notice 7/21/2021
Documents:
Posted: 7/2/2021
Type of Addition: Addendum No. 2
Overview:
This Addendum forms a part of the Contract
Documents and modifies the original bidding documents dated May 2021, as noted
below. Acknowledge receipt of this Addendum in the space provided on the
Proposal form. Failure to do so may subject the bidder to disqualification. This
Addendum consists of 3 pages and the following attachment: Revised Plansheets.
Solicitation #: 001802
Documents:
Posted: 7/14/2021
Type of Addition: Addendum No. 3
Overview:
This Addendum forms a part of the Contract
Documents and modifies the original bidding documents dated May 2021, as noted
below. Acknowledge receipt of this Addendum in the space provided on the
Proposal form. Failure to do so may subject the bidder to disqualification. This
Addendum consists of 6 pages and the following attachments: Revised Bid Form; Revised Plan Sheets; New and
Revised Special Provisions; Fuel Adjustment Sheet; and the following reference
document is included separately: Roadway Soil Survey (417-151_GEOTECH_Roadway
Soil Survey addendum 3).
Solicitation #: 001802
Documents:
Posted: 7/22/2021
Type of Addition: In Review
Overview: The Bid Opening for SR 417 WIDENING FROM BOGGY CREEK ROAD TO NARCOOSSEE ROAD; Project No. 417-151; ITB-001802 was held at a duly noticed meeting on Wednesday, July 21, 2021, commencing at 1:30 p.m. at the Central Florida Expressway Authority Administrative Building, Orlando, Florida. The bids for the following companies were opened and announced verbally along with the bid total amount.
Documents:
Posted: 8/12/2021
Type of Addition: Bid Tabulation 001802
Overview:
Documents:
Posted: 8/12/2021
Type of Addition: Award Information
Overview: On August 12, 2021 the CFX Board members awarded the Contract to the following firm, contingent upon final execution of the contract by both parties: Ranger Construction Industries, Inc., 1200 Elboc Way, Winter Garden, Florida 34787
Amount: $61,810,653.72
Documents: