Whitfield County Schools Sealed Solicitation
Title: Facilities - Southeast High Staff Restroom Renovations
Deadline: 10/24/2025 2:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status: Awarded
Solicitation Number: WCS-ARC-2026-001
Description: The project includes necessary renovations to provide six new staff restrooms. The project includes a new entrance door and frame for the existing courtyard. The full requirements for construction of the Project, and the duties and responsibilities of the contractor whose Proposal is accepted (“Successful Contractor”), are set forth in the Contract Documents which include the Instructions to Proposers; the Contract for Construction and Incorporated General Conditions (the “Contract”); any supplementary and other conditions; the drawings; the specifications; and any addenda issued by the Architect.
Pre-Bid Meeting Date: 10/8/2025 2:00 PM
Pre-Bid Meeting Details: Any Contractor who intends to submit a Proposal is required to attend a Pre-Proposal Meeting, which will be held on the 8th day of October 2025, at 2:00 p.m. at the project site. Please arrive early and check in at the front entrance to the school. Any contractor arriving more than 5 minutes late will not be permitted to attend.
Documents:
| Documents as of 9/25/2025 |
|---|
| Login to view documents |
| Login to view documents |
Addition 1
Posted: 10/15/2025
Type of Addition: Addendum 1
Overview: Updates, changes, and answering questions to the RFP.
Solicitation #: WCS-ARC-2026-001
Documents:
Addition 2
Posted: 10/18/2025
Type of Addition: Addendum 2
Overview: Updates, changes, and answering questions to the RFP.
Solicitation #: WCS-ARC-2026-001
Documents:
Addition 3
Posted: 10/20/2025
Type of Addition: Addendum 3
Overview: Updates and changes to the RFP.
Solicitation #: WCS-ARC-2026-001
Documents:
Addition 4
Posted: 11/5/2025
Type of Addition: Award Information
Overview: Awarded to Multiplex at the November 3rd Board Meeting.
Amount: $377,400.00
Question 1
Posted: 10/14/2025
Question: Sheet A/1.3 Note # 4 States Provide $4500 ALLOWANCE for Installation of Card Access. Section 0120-3, Paragraph 3.2B States a General Construction Allowance of $50,000. Is the $4500 allowance in Addition to the $50,000?
Response: Questions shall be included in Addendum No. 1.
Question 2
Posted: 10/14/2025
Question: Specification 15900 Paragraph 1.6D state an Alternate price for Delta Controls. No Alternates show up on the BID Form, please clarify.
Response: Questions shall be included in Addendum No. 1.
Question 3
Posted: 10/14/2025
Question: Specification Section 15980 Paragraph references Division 22 and Division 23. Division 22 & 23 not found in specification. Please clarify
Response: Questions shall be included in Addendum No. 1.
Question 4
Posted: 10/14/2025
Question: The contract Section 5.6.1.2- Are there any funding delay Damages involved with this project?
Response: Questions shall be included in Addendum No. 1.
Question 5
Posted: 10/14/2025
Question: The contract section 6.1.2 and 7.2.2 states Excluding permits and fees normally the responsibility of the Contractor, the Owner shall obtain all approvals, easements and the like required for construction and shall pay for necessary easements and charges for construction, use, or occupancy of permanent structures or for permanent changes in existing facilities. Please clarify if there will be a cost for building permits and fees, and are there other permits and fees that are the resp onsibilty of the Contractor?. Has the County Fire Marshall and Building Inspector already reviewed the drawings?
Response: Questions shall be included in Addendum No. 1.
Question 6
Posted: 10/14/2025
Question: Section 00090 Paragraph 5.5 states that the contractor has 30 Days after Date Of Substanial Completion to complete. Section 00150, Paragraph B, Item # 12 shows only 13 day after date Of Substantial Completion to complete. Which date is correct?
Response: Questions shall be included in Addendum No. 1.
Question 7
Posted: 10/14/2025
Question: Specification Section 01020 Paragraph 1.6 LUMP SUM ALLOWANCES Section B. Please clarify this Paragraph. Is this allowance included with the in the $50,000 Contingency Allowances? Have not found any references in remaining specs or plans.
Response: Questions shall be included in Addendum No. 1.
Question 8
Posted: 10/14/2025
Question: Can demolition work on the 2nd floor begin after receiving the Notice to proceed before demolition of the 1st floor on November 22, 2025?
Response: Questions shall be included in Addendum No. 1.
Question 9
Posted: 10/14/2025
Question: Spec section 13915 paragraph 1.6D- The Fire Marshall referenced, is this the State or local Fire Marshall?
Response: Questions shall be included in Addendum No. 1.
Question 10
Posted: 10/14/2025
Question: Spec Section 15 & 16 references Division 7 Section Through-Penetration Fire stop Systems. This section has not been found. Is this described on Sheet A/0.2?
Response: Questions shall be included in Addendum No. 1.
Question 11
Posted: 10/15/2025
Question: Reference Spec Section 15980 Paragraph 1.2D Please provide the name and contact info for the CxA work, that the Owner has contracted with.. Paragraph 1.2C references Division 22 & 23. There are no Division 22 or 23 in the specifications. Please clarify
Response: Questions shall be included in Addendum No. 1.
Question 12
Posted: 10/15/2025
Question: Reference Sheet A/0.1, General Life Safety Notes # 2 states to provide 4 each fire extinguisher. No specification has been found to describe the Fire Extinguishers. Please Clarify
Response: Questions shall be included in Addendum No. 1.
Question 13
Posted: 10/15/2025
Question: Reference Sheet A/0.1 Note # 3, states Contractor shall submit Fire Alarm and Fire Sprinkler plan to the Fire Marshall office for review and permit. Contractor shall be in possession of permit prior to commencement of work. According to the preliminary Construction Schedule, Notice to Proceed will be issued on November 6, 2025. This allows only 16 days total with 4 of those days being on weekends. This will only allow 12 working days to produce these submittals, deliver to Fire Marshall for review and approval. Not knowing how long the Fire Marshall will take to review and issue permit. The building inspector will not issue building permit until the Fire Marshall permit has been issued. Work could possibly be delayed as work cannot start until all permits have been received. This process could delay the Start of the work on November 22, 2025, if permits have to be issued before starting work. Knowing that the work needs to be completed while students are on Thanksgiving break, what happens if the permits are not received by this date? Money can be added for any liquidated damages but the Contractor has no control on time involved in Building officials review and issuance of Permits.
Response: Questions shall be included in Addendum No. 1.
Question 14
Posted: 10/15/2025
Question: Reference Sheet A/0.1 Note # 1. There are several models of the recessed Knox box. Please provide the model number of the Knox Box, as pricing varies.
Response: Questions shall be included in Addendum No. 1.
Question 15
Posted: 10/17/2025
Question: 1. E1.1 Lighting Keynotes #6 - 2/E4-01A not a part of drawing set. Please advise 2. E1.1 Lighting Keynotes #6 - Security panel/MDF room not shown. Please advise 3. E1.1 Lighting Keynotes #6 - Keypad not shown on drawings only card reader box. Please advise 4. E1.1 Lighting Keynotes #6 - 120-volt Emergency Panel not shown on drawings. Please advise 5. E1.1 Lighting Keynotes #8 & #9 - Family Consumer Science no shown. Please advise
Response: Questions shall be included in Addendum No. 2.
Posted: 10/15/2025
Type of Addition: Addendum 1
Overview: Updates, changes, and answering questions to the RFP.
Solicitation #: WCS-ARC-2026-001
Documents:
Posted: 10/18/2025
Type of Addition: Addendum 2
Overview: Updates, changes, and answering questions to the RFP.
Solicitation #: WCS-ARC-2026-001
Documents:
Posted: 10/20/2025
Type of Addition: Addendum 3
Overview: Updates and changes to the RFP.
Solicitation #: WCS-ARC-2026-001
Documents:
Posted: 11/5/2025
Type of Addition: Award Information
Overview: Awarded to Multiplex at the November 3rd Board Meeting.
Amount: $377,400.00
Posted: 10/14/2025
Question: Sheet A/1.3 Note # 4 States Provide $4500 ALLOWANCE for Installation of Card Access. Section 0120-3, Paragraph 3.2B States a General Construction Allowance of $50,000. Is the $4500 allowance in Addition to the $50,000?
Response: Questions shall be included in Addendum No. 1.
Posted: 10/14/2025
Question: Specification 15900 Paragraph 1.6D state an Alternate price for Delta Controls. No Alternates show up on the BID Form, please clarify.
Response: Questions shall be included in Addendum No. 1.
Posted: 10/14/2025
Question: Specification Section 15980 Paragraph references Division 22 and Division 23. Division 22 & 23 not found in specification. Please clarify
Response: Questions shall be included in Addendum No. 1.
Posted: 10/14/2025
Question: The contract Section 5.6.1.2- Are there any funding delay Damages involved with this project?
Response: Questions shall be included in Addendum No. 1.
Posted: 10/14/2025
Question: The contract section 6.1.2 and 7.2.2 states Excluding permits and fees normally the responsibility of the Contractor, the Owner shall obtain all approvals, easements and the like required for construction and shall pay for necessary easements and charges for construction, use, or occupancy of permanent structures or for permanent changes in existing facilities. Please clarify if there will be a cost for building permits and fees, and are there other permits and fees that are the resp onsibilty of the Contractor?. Has the County Fire Marshall and Building Inspector already reviewed the drawings?
Response: Questions shall be included in Addendum No. 1.
Posted: 10/14/2025
Question: Section 00090 Paragraph 5.5 states that the contractor has 30 Days after Date Of Substanial Completion to complete. Section 00150, Paragraph B, Item # 12 shows only 13 day after date Of Substantial Completion to complete. Which date is correct?
Response: Questions shall be included in Addendum No. 1.
Posted: 10/14/2025
Question: Specification Section 01020 Paragraph 1.6 LUMP SUM ALLOWANCES Section B. Please clarify this Paragraph. Is this allowance included with the in the $50,000 Contingency Allowances? Have not found any references in remaining specs or plans.
Response: Questions shall be included in Addendum No. 1.
Posted: 10/14/2025
Question: Can demolition work on the 2nd floor begin after receiving the Notice to proceed before demolition of the 1st floor on November 22, 2025?
Response: Questions shall be included in Addendum No. 1.
Posted: 10/14/2025
Question: Spec section 13915 paragraph 1.6D- The Fire Marshall referenced, is this the State or local Fire Marshall?
Response: Questions shall be included in Addendum No. 1.
Posted: 10/14/2025
Question: Spec Section 15 & 16 references Division 7 Section Through-Penetration Fire stop Systems. This section has not been found. Is this described on Sheet A/0.2?
Response: Questions shall be included in Addendum No. 1.
Posted: 10/15/2025
Question: Reference Spec Section 15980 Paragraph 1.2D Please provide the name and contact info for the CxA work, that the Owner has contracted with.. Paragraph 1.2C references Division 22 & 23. There are no Division 22 or 23 in the specifications. Please clarify
Response: Questions shall be included in Addendum No. 1.
Posted: 10/15/2025
Question: Reference Sheet A/0.1, General Life Safety Notes # 2 states to provide 4 each fire extinguisher. No specification has been found to describe the Fire Extinguishers. Please Clarify
Response: Questions shall be included in Addendum No. 1.
Posted: 10/15/2025
Question: Reference Sheet A/0.1 Note # 3, states Contractor shall submit Fire Alarm and Fire Sprinkler plan to the Fire Marshall office for review and permit. Contractor shall be in possession of permit prior to commencement of work. According to the preliminary Construction Schedule, Notice to Proceed will be issued on November 6, 2025. This allows only 16 days total with 4 of those days being on weekends. This will only allow 12 working days to produce these submittals, deliver to Fire Marshall for review and approval. Not knowing how long the Fire Marshall will take to review and issue permit. The building inspector will not issue building permit until the Fire Marshall permit has been issued. Work could possibly be delayed as work cannot start until all permits have been received. This process could delay the Start of the work on November 22, 2025, if permits have to be issued before starting work. Knowing that the work needs to be completed while students are on Thanksgiving break, what happens if the permits are not received by this date? Money can be added for any liquidated damages but the Contractor has no control on time involved in Building officials review and issuance of Permits.
Response: Questions shall be included in Addendum No. 1.
Posted: 10/15/2025
Question: Reference Sheet A/0.1 Note # 1. There are several models of the recessed Knox box. Please provide the model number of the Knox Box, as pricing varies.
Response: Questions shall be included in Addendum No. 1.
Posted: 10/17/2025
Question: 1. E1.1 Lighting Keynotes #6 - 2/E4-01A not a part of drawing set. Please advise 2. E1.1 Lighting Keynotes #6 - Security panel/MDF room not shown. Please advise 3. E1.1 Lighting Keynotes #6 - Keypad not shown on drawings only card reader box. Please advise 4. E1.1 Lighting Keynotes #6 - 120-volt Emergency Panel not shown on drawings. Please advise 5. E1.1 Lighting Keynotes #8 & #9 - Family Consumer Science no shown. Please advise
Response: Questions shall be included in Addendum No. 2.