Florence County Sealed Solicitation

Title: 29-22/23 Dist. 3 Road Resurfacing With HMA and Partial Reclamation of Existing Asphalt - RE-BID

Deadline: 5/8/2023 10:00 AM   (UTC-05:00) Eastern Time (US & Canada)

Status: Awarded

Solicitation Number: 29-22/23

Description: Florence County, South Carolina is accepting bids from qualified vendors to furnish all materials and labor for road resurfacing with HMA and partial reclamation of existing asphalt for Sally Hill Farm Rd. in Florence County.


Documents:

Documents as of 4/24/2023
Login to view documents
Addition 1

Posted: 5/8/2023

Type of Addition: In Review

Addition 2

Posted: 5/8/2023

Type of Addition: Bid Tab

Overview: Only one (1) bid received.

Documents:

Addition 3

Posted: 7/24/2023

Type of Addition: Award Information

Overview: Awarded to C. R. Jackson of Darlington, SC on 6-15-23.

Amount: $218,095.50

Question 1

Posted: 4/27/2023

Question: Please verify contract duration. Page 15 states "The contractor has thirty (90) calendar days from the date of the Notice to Proceed letter to complete the project." Also, the Liquidated Damages section on page 3 states "The time limit that is set for this project is _____________ (___) calendar days (get this information from Marion)."

Response: Completion date is 90 (ninety) calendar days from the date of the Notice to Proceed Letter. Liquidated Damages date is stated on page 8 as "21 calendar days after the Notice of Award and is the same for page 13.

Posted: 5/8/2023

Type of Addition: In Review

Posted: 5/8/2023

Type of Addition: Bid Tab

Overview: Only one (1) bid received.

Documents:

Posted: 7/24/2023

Type of Addition: Award Information

Overview: Awarded to C. R. Jackson of Darlington, SC on 6-15-23.

Amount: $218,095.50

Posted: 4/27/2023

Question: Please verify contract duration. Page 15 states "The contractor has thirty (90) calendar days from the date of the Notice to Proceed letter to complete the project." Also, the Liquidated Damages section on page 3 states "The time limit that is set for this project is _____________ (___) calendar days (get this information from Marion)."

Response: Completion date is 90 (ninety) calendar days from the date of the Notice to Proceed Letter. Liquidated Damages date is stated on page 8 as "21 calendar days after the Notice of Award and is the same for page 13.