New Mexico Highlands University Sealed Solicitation
Title: RFP 23-010 Architectual and Engineering Services
Deadline: 1/31/2023 2:00 PM (UTC-07:00) Mountain Time (US & Canada)
Status: Cancelled
Solicitation Number: 23-010
Description: This Request for Proposal is to seek out the services from an architectural, engineering and planning firm to provide the programming, planning, design, construction drawings, and construction administration.
Documents:
Documents as of 12/13/2022 |
---|
RFP 23-010 - AE Services Facilities.pdf |
Addition 1
Posted: 1/10/2023
Type of Addition: Addendum 1 RFP 23-010
Overview: Addendum 1 - Question and Answer through January 10, 2023
Solicitation #: 23-010
Documents:
Addition 2
Posted: 1/13/2023
Type of Addition: Addendum 2
Overview: Question and Answer
Solicitation #: RFP 23-010
Documents:
Addition 3
Posted: 1/20/2023
Type of Addition: Addendum 3
Overview: Additional Question and Answers
Solicitation #: RFP 23-010
Documents:
Question 1
Posted: 1/5/2023
Question: Is this RFP for a specific project?
Response: No, this RFP is for services for future projects for the University.
Question 2
Posted: 1/13/2023
Question: For Financial Statements, does the balance sheet requested need to be provided by a third party CPA and certified, or is a general company statement adequate?
Response: A certified balance sheet is required.
Question 3
Posted: 1/16/2023
Question: Under Section III Scope of Work, Item 5, there is the request that "...Architect will design the plans to include fire safety and the fire suppression system". Is the intent that the AE team provide a Performance design OR that we include a Nicet Level-3 Designer on the team (which is typically part of the GC's scope)?
Response: When applicable, the A&E team should provide fire safety plans that include a designed fire suppression system as required by the State’s Construction Industry Division.
Question 4
Posted: 1/16/2023
Question: Good Afternoon, We have the following question regarding RFP No. 23-010 NM Highlands University's request for Architectural & Engineering Services. For clarification, on page 17 – Submission Procedures. Item No. 1 is asking for the number of proposal copies but on Item 3 – sub number 5 it says the proposal will be accepted through vendorregistry.com. Does this mean we can submit through the vendor registry and not have to provide hard copies?
Response: Correct. If you are submitting via vendorregistry.com then just one submission is needed. Only if you are sending hard copies do you need to provide the specified copies.
Question 5
Posted: 1/18/2023
Question: Hello. Under TAB 2, it says we are to provide relevant experience including the term (start to finish). What exactly are you looking for when you say "term"?
Response: The sentence should have included the word "project". Please strike the content of Tab 2 and replace with the following : Provide relevant experience (preferably the last five, most current academic buildings worked on), including the project term (start to finish), a detailed description, initial and final budget per project, change order information, timeline per project, size (GSF) of projects, awards if any, and contact references. Include specific experience that would further convey your team’s qualifications for this project.
Question 6
Posted: 1/18/2023
Question: I understand a "certified" balance sheet is required. What does "certified" mean in that instance?
Response: 3rd party certification
Question 7
Posted: 1/19/2023
Question: Is a cover sheet and table of contents required? If we include these, will they be counted towards the maximum page limit of (12)?
Response: These items will not be counted towards the page limit.
Posted: 1/10/2023
Type of Addition: Addendum 1 RFP 23-010
Overview: Addendum 1 - Question and Answer through January 10, 2023
Solicitation #: 23-010
Documents:
Posted: 1/13/2023
Type of Addition: Addendum 2
Overview: Question and Answer
Solicitation #: RFP 23-010
Documents:
Posted: 1/20/2023
Type of Addition: Addendum 3
Overview: Additional Question and Answers
Solicitation #: RFP 23-010
Documents:
Posted: 1/5/2023
Question: Is this RFP for a specific project?
Response: No, this RFP is for services for future projects for the University.
Posted: 1/13/2023
Question: For Financial Statements, does the balance sheet requested need to be provided by a third party CPA and certified, or is a general company statement adequate?
Response: A certified balance sheet is required.
Posted: 1/16/2023
Question: Under Section III Scope of Work, Item 5, there is the request that "...Architect will design the plans to include fire safety and the fire suppression system". Is the intent that the AE team provide a Performance design OR that we include a Nicet Level-3 Designer on the team (which is typically part of the GC's scope)?
Response: When applicable, the A&E team should provide fire safety plans that include a designed fire suppression system as required by the State’s Construction Industry Division.
Posted: 1/16/2023
Question: Good Afternoon, We have the following question regarding RFP No. 23-010 NM Highlands University's request for Architectural & Engineering Services. For clarification, on page 17 – Submission Procedures. Item No. 1 is asking for the number of proposal copies but on Item 3 – sub number 5 it says the proposal will be accepted through vendorregistry.com. Does this mean we can submit through the vendor registry and not have to provide hard copies?
Response: Correct. If you are submitting via vendorregistry.com then just one submission is needed. Only if you are sending hard copies do you need to provide the specified copies.
Posted: 1/18/2023
Question: Hello. Under TAB 2, it says we are to provide relevant experience including the term (start to finish). What exactly are you looking for when you say "term"?
Response: The sentence should have included the word "project". Please strike the content of Tab 2 and replace with the following : Provide relevant experience (preferably the last five, most current academic buildings worked on), including the project term (start to finish), a detailed description, initial and final budget per project, change order information, timeline per project, size (GSF) of projects, awards if any, and contact references. Include specific experience that would further convey your team’s qualifications for this project.
Posted: 1/18/2023
Question: I understand a "certified" balance sheet is required. What does "certified" mean in that instance?
Response: 3rd party certification
Posted: 1/19/2023
Question: Is a cover sheet and table of contents required? If we include these, will they be counted towards the maximum page limit of (12)?
Response: These items will not be counted towards the page limit.