Okaloosa County Sealed Solicitation
Title: Old Bethel Road Sidewalk Improvements
Deadline: 8/31/2022 3:00 PM (UTC-06:00) Central Time (US & Canada)
Status: Awarded
Solicitation Number: ITB PW 56-22
Description: The project consists of constructing sidewalk along Old Bethel Rd going west from Davidson Middle School and other associated work including clearing and grubbing, earthwork, maintenance of traffic, concrete retaining walls, and other improvements. The work is further defined as shown on the Plans and as described by the Contract Documents.
Documents:
Documents as of 7/21/2022 |
---|
Login to view documents |
Addition 1
Posted: 8/19/2022
Type of Addition: Addendum 1
Overview: ADDENDUM 1
ITB WS 56-22
Please find the attached document and information below, for the above referenced Addendum 1. This Addendum is hereby made a part of the Contract Documents and Specifications of the above referenced project. All other requirements of the original Contract Documents and Specifications shall remain effective in their respective order.
I. This addendum is being issued to answer questions submitted by potential vendors:
Question #1: Plan sheet C15 shows the sidewalk installation behind or "off" the Right-of-Way (R/W). Is this correct?
Answer #1: Yes, the area behind the R/W is County property, specifically County Pond 10. Please see attached is pdf showing the pond and that it is County property.
Question #2: Sheet C3 details specific working hours; is this specific to work in the roadway, or does this include work off the roadway in the back of the R/W where the sidewalk will be installed?
Answer #2: Hours are for ALL work at those locations due to school hours.
*The solicitation opening date remains August 31, 2022 at 3:00 p.m. (CST)*
Deadline: 8/31/2022 3:00 PM
Solicitation #: ITB WS 56-22
Documents:
Addition 2
Posted: 5/17/2024
Type of Addition: Award Information / LAS Contracting Corp / 9/9/22
Documents:
Question 1
Posted: 8/15/2022
Question: Plan sheet C15 shows the sidewalk installation behind or "off" the R/W. Is this correct?
Response: See Addendum #1
Question 2
Posted: 8/15/2022
Question: Sheet C3 details specific working hours; Is this specific to work in the roadway, or does this include work off the roadway in the back of the R/W where the sidewalk will be installed?
Response: See Addendum #1
Posted: 8/19/2022
Type of Addition: Addendum 1
Overview: ADDENDUM 1
ITB WS 56-22
Please find the attached document and information below, for the above referenced Addendum 1. This Addendum is hereby made a part of the Contract Documents and Specifications of the above referenced project. All other requirements of the original Contract Documents and Specifications shall remain effective in their respective order.
I. This addendum is being issued to answer questions submitted by potential vendors:
Question #1: Plan sheet C15 shows the sidewalk installation behind or "off" the Right-of-Way (R/W). Is this correct?
Answer #1: Yes, the area behind the R/W is County property, specifically County Pond 10. Please see attached is pdf showing the pond and that it is County property.
Question #2: Sheet C3 details specific working hours; is this specific to work in the roadway, or does this include work off the roadway in the back of the R/W where the sidewalk will be installed?
Answer #2: Hours are for ALL work at those locations due to school hours.
*The solicitation opening date remains August 31, 2022 at 3:00 p.m. (CST)*
Deadline: 8/31/2022 3:00 PM
Solicitation #: ITB WS 56-22
Documents:
Posted: 5/17/2024
Type of Addition: Award Information / LAS Contracting Corp / 9/9/22
Documents:
Posted: 8/15/2022
Question: Plan sheet C15 shows the sidewalk installation behind or "off" the R/W. Is this correct?
Response: See Addendum #1
Posted: 8/15/2022
Question: Sheet C3 details specific working hours; Is this specific to work in the roadway, or does this include work off the roadway in the back of the R/W where the sidewalk will be installed?
Response: See Addendum #1