Dorchester County Sealed Solicitation
Title: Construction Manager at Risk (CMAR) for Edisto Tribal Council Community Building
Deadline: 9/21/2020 2:00 PM (UTC-05:00) Eastern Time (US & Canada)
Status: Awarded
Solicitation Number: RFP 2021-08
Description:
Documents:
Documents as of 8/19/2020 |
---|
Login to view documents |
Login to view documents |
Addition 1
Posted: 9/8/2020
Type of Addition: Addendum
Overview: Addendum to extend the milestone dates.
Documents:
Addition 2
Posted: 9/21/2020
Type of Addition: In Review
Addition 3
Posted: 9/21/2020
Type of Addition: In Review
Addition 4
Posted: 10/16/2020
Type of Addition: Award Information
Overview: Awarded to Mitchell Construction
Documents:
Question 1
Posted: 9/8/2020
Question: Will the contractor just be managing this project or will he be allowed to do the actual work as well?
Response: The contractor will be managing the project as well as doing the work, while subcontracting out anything they can't or don't do (plumbing, hvac, etc.).
Posted: 9/8/2020
Type of Addition: Addendum
Overview: Addendum to extend the milestone dates.
Documents:
Posted: 9/21/2020
Type of Addition: In Review
Posted: 9/21/2020
Type of Addition: In Review
Posted: 10/16/2020
Type of Addition: Award Information
Overview: Awarded to Mitchell Construction
Documents:
Posted: 9/8/2020
Question: Will the contractor just be managing this project or will he be allowed to do the actual work as well?
Response: The contractor will be managing the project as well as doing the work, while subcontracting out anything they can't or don't do (plumbing, hvac, etc.).