County of Beaufort Sealed Solicitation

Title: Request for Qualifications Construction Manager-at-Risk for the Beaufort County Public Works Complex

Deadline: 6/26/2024 3:00 PM   (UTC-05:00) Eastern Time (US & Canada)

Status: Cancelled

Solicitation Number: RFQ 062624

Description: It is the intention of Beaufort County to select a Construction Manager at Risk (CM-R) to provide comprehensive pre-construction and construction services for the new Beaufort County Public Works Facility at 120 Shanklin Road, Beaufort, SC.


Pre-Bid Meeting Date: 6/5/2024 2:00 PM

Pre-Bid Meeting Details: This is a virtual meeting. Emails victoria.moyer@bcgov.net to receive your invite


Documents:

Documents as of 5/22/2024
Login to view documents

PLANHOLDERS:

Date Company Name
5/22/2024 10:48:34 AM M.B. Kahn Construction
5/22/2024 10:51:25 AM JE Dunn Construction
5/22/2024 10:52:04 AM JE Dunn Construction
5/22/2024 11:04:55 AM John Crews Construction, LLC
5/22/2024 11:06:52 AM Reeves Young
5/22/2024 11:08:37 AM Roy Anderson Corp
5/22/2024 11:13:42 AM CPPI
5/22/2024 11:17:06 AM Samet Corporation
5/22/2024 11:29:15 AM C. Merrill Construction
5/22/2024 11:29:35 AM Monteith Construction Corp.
5/22/2024 11:34:18 AM Design Build Construction
5/22/2024 12:31:20 PM Fraser Construction Company, LLC
5/22/2024 1:30:52 PM Trident Construction
5/22/2024 1:41:11 PM Beaufort Construction of SC LLC
5/22/2024 1:44:50 PM ATM Development LLC
5/22/2024 1:58:21 PM Ajax Building Company, LLC
5/22/2024 1:58:56 PM Paul S. Akins Company, Inc.
5/22/2024 2:01:14 PM Mitchell Construction Company
5/22/2024 2:15:03 PM Genesis Construction Company, LLC.
5/22/2024 2:51:53 PM GMK Associates, Inc.
5/22/2024 2:59:21 PM Shoreline Construction
5/22/2024 3:04:09 PM Reeves Young
5/22/2024 3:33:57 PM Deltek
5/22/2024 4:16:15 PM envirobidnet
5/23/2024 12:27:43 AM AG Ltd
5/23/2024 1:40:30 AM North America Procurement Council Inc., PBC
5/23/2024 6:07:11 AM Alliance Consulting Engineers, Inc.
5/23/2024 7:08:17 AM IMS
5/23/2024 8:19:20 AM J. Davis Construction
5/23/2024 8:31:21 AM APAC-Atlantic, Inc.
5/23/2024 9:33:55 AM Ward Edwards, Inc.
5/23/2024 10:23:42 AM THS Constructors
5/23/2024 11:13:06 AM IP Builders, Inc.
5/23/2024 1:42:06 PM LS3P
5/23/2024 3:00:13 PM K-Con Building Systems
5/23/2024 3:29:42 PM Choate Construction Company
5/23/2024 6:20:40 PM Dodge Data & Analytics
5/24/2024 6:30:40 AM ConstructConnect
5/24/2024 10:03:39 AM McMillan Pazdan Smith Architecture
5/24/2024 1:32:11 PM PWXPress
5/24/2024 4:07:58 PM Cumming Corp
5/28/2024 7:57:02 AM Edifice
5/28/2024 9:37:07 AM Anchor Construction Management, LLC
5/28/2024 11:18:16 AM TranSytems
5/28/2024 12:12:08 PM AMANSWELL, LLC
5/28/2024 1:05:00 PM Mitchell Brothers, Inc.
5/28/2024 2:13:18 PM Exterior Building Services, LLC
5/30/2024 9:00:33 AM Collins Construction Services, Inc.
5/31/2024 11:38:37 AM HITT Contracting Inc.
5/31/2024 12:59:17 PM Bowman Consulting Group Ltd
5/31/2024 1:59:50 PM Trident Construction, LLC
6/3/2024 9:30:27 AM Gulf Stream Construction
6/3/2024 10:09:40 AM BOTTOMLINE CONSTRUCTION
6/7/2024 4:19:35 PM Stewart-Cooper-Newell Architects
7/9/2024 10:08:56 AM Bluffton Township Fire District
9/4/2024 12:02:45 PM Hill Construction
Question 1

Posted: 5/22/2024

Question: On the Vendor Registry posting, it lists the pre-bid meeting as June 5. On the RFQ, it lists the pre-bid meeting as June 6. Thank you.

Response: The meeting is June 5.

Posted: 5/22/2024

Question: On the Vendor Registry posting, it lists the pre-bid meeting as June 5. On the RFQ, it lists the pre-bid meeting as June 6. Thank you.

Response: The meeting is June 5.