City of Aztec Sealed Solicitation

Title: ITB 2025-861 Hartman Park Field Lighting

Deadline: 1/30/2025 3:00 PM   (UTC-07:00) Mountain Time (US & Canada)

Status: Cancelled

Solicitation Number: ITB 2025-861

Description: Hartman Park Football Field Lighting project in Aztec, N.M. involves installing four lighting poles with concrete
anchor bases, rebar cages, electrical conduit, and wiring, as well as transporting and assembling fixtures
per design standards, coordinating with city departments for trenching and electric service connections,
and ensuring proper compaction and installation of all components.


Documents:

Documents as of 12/9/2024
ITB_2025_861_Hartman_Park_Field_Lighting.pdf
Addition 1

Posted: 12/17/2024

Type of Addition: Addendum 1

Overview: Correction of Basis of Bid and Wage Decision

Deadline: 1/16/2025 3:00 PM

Solicitation #: ITB 2025-861

Documents:

Addition 2

Posted: 12/31/2024

Type of Addition: Addendum 2

Overview: Revised Bid Due Date

Non-Mandatory  Pre-bid Meeting
GeoMat Report

Pre-Bid Meeting Details: Aztec City Hall, 201 W. Chaco, Aztec, N.M. 87410

Solicitation #: ITB 2025-861

Documents:

Addition 3

Posted: 1/16/2025

Type of Addition: Addendum 3

Overview: Includes pictures light poles, mounting arm and control box, Lighting Specs for LumaSport 8 LS-640 model, Bill of materials and Question and Answers asked.

Solicitation #: ITB 2025-861

Documents:

Addition 4

Posted: 1/27/2025

Type of Addition: Addendum 4

Overview: Provided a one line drawing of the electrical installation (Exhibit D), also questions and answers.

Deadline: 1/30/2025 3:00 PM

Solicitation #: ITB 2025-861

Documents:

Addition 5

Posted: 1/31/2025

Type of Addition: In Review

Addition 6

Posted: 2/3/2025

Type of Addition: Award Information

Overview: Awarded to Crossfire Aggregate Services LLC

Amount: $118,798.00

Documents:

Addition 7

Posted: 2/21/2025

Type of Addition: Cancellation Information

Overview: ITB 2025-861 Hartman Park Field Lighting was rejected by the Commission. The City has decided to complete most of the work in-house, with a portion to be issued for quote submissions at a later date.

Posted: 12/17/2024

Type of Addition: Addendum 1

Overview: Correction of Basis of Bid and Wage Decision

Deadline: 1/16/2025 3:00 PM

Solicitation #: ITB 2025-861

Documents:

Posted: 12/31/2024

Type of Addition: Addendum 2

Overview: Revised Bid Due Date

Non-Mandatory  Pre-bid Meeting
GeoMat Report

Pre-Bid Meeting Details: Aztec City Hall, 201 W. Chaco, Aztec, N.M. 87410

Solicitation #: ITB 2025-861

Documents:

Posted: 1/16/2025

Type of Addition: Addendum 3

Overview: Includes pictures light poles, mounting arm and control box, Lighting Specs for LumaSport 8 LS-640 model, Bill of materials and Question and Answers asked.

Solicitation #: ITB 2025-861

Documents:

Posted: 1/27/2025

Type of Addition: Addendum 4

Overview: Provided a one line drawing of the electrical installation (Exhibit D), also questions and answers.

Deadline: 1/30/2025 3:00 PM

Solicitation #: ITB 2025-861

Documents:

Posted: 1/31/2025

Type of Addition: In Review

Posted: 2/3/2025

Type of Addition: Award Information

Overview: Awarded to Crossfire Aggregate Services LLC

Amount: $118,798.00

Documents:

Posted: 2/21/2025

Type of Addition: Cancellation Information

Overview: ITB 2025-861 Hartman Park Field Lighting was rejected by the Commission. The City has decided to complete most of the work in-house, with a portion to be issued for quote submissions at a later date.